LDA Vice-Chairperson Prathamesh Kumar inspected the project on Tuesday and directed officials to expedite development work. He set a one-month deadline to improve progress and restore roads dug up for stormwater drainage works.
The project covers seven villages and 10 hamlets. Under the land-pooling policy, 1,465 farmers have so far been allotted 2,197 developed plots.
During the review, Kumar found that only three roads had reached the granular sub-base stage, despite 40 tenders being issued for work on 25 roads and development activities in two sectors.