Rahee Infratech Wins Nagpur Metro Track Contract

Rahee Infratech

Rahee Infratech has emerged as the lowest bidder (L1) for the ballasted and ballast-less track works in Nagpur Metro Phase-II. The contract covers the at-grade section of Reach 1A and the elevated viaduct of Reach 2A and Reach 4A.

The company secured the project with a bid of ₹174.19 crore, which includes the design, supply, installation, testing, and commissioning of tracks. Package T-02 involves installing ballasted tracks along the 1.746 km at-grade section of Reach 1A on the Orange Line, spanning 18.7 km from Khapri to Butibori MIDC ESR. This section will connect two metro stations—Eco Park and Metro City.