Procam overcomes arduous terrain with effortless scale-up to transport ODC cargo
Procam was assigned a project by a multinational Hydro Power Equipment manufacturer for their upcoming project at Chandrapuri in the hills of Uttarakhand, involving a very difficult and challenging terrain for project cargo movement. It was an arduous job to transport 3 transformers of 50 T each. Procam team conducted a feasibility study and planned the journey covering a total distance of 1560 km while considering the route conditions and detouring for safe transportation, before confirming that the cargo could be delivered safely.