Work for metro depot construction was awarded to Lisha Engineers in October 2020 involving ₹112.63 crore investments and is expected to be completed by June 2022. The Priority Corridor of Agra Metro comprises construction of 6 km long section from Taj East Gate to Jama Masjid with six stations for which contract has been awarded to Sam India Built Well Pvt. Ltd. for the elevated portion with a length of 3-km with 3 stations namely – Fatehabad Road, Basai & Taj East Gate. However, tender is still pending for the underground section of the length of 3 km that will run from Jama Masjid to Taj Mahal with three underground stations. UPMRC has set a deadline of March 2024 to start the operation of metro trains on the Priority Corridor.