Sumadhura Group Sets Record for Fastest Concrete Pour in Hyderabad's Real Estate
Sumadhura Group, a leading real estate developer in South India, achieved a groundbreaking milestone in Hyderabad’s residential real estate sector by completing a continuous concrete pour of 6,000 cubic meters in just 50 hours. The feat was accomplished for their uber-luxury project, Palais Royale, between December 28 and December 30.

This record-breaking accomplishment underscores Sumadhura Group's commitment to on-time project delivery while maintaining exceptional standards of quality, safety, and innovation. It is one of the largest and fastest concrete pours ever executed in Hyderabad’s residential real estate industry.
The operation involved a team of over 85 technical experts and 300 workers working around the clock. Utilizing 74 concrete millers, boom placers, and pumps, the team ensured seamless execution. The structure features intricate detailing, including eight layers of steel reinforcement at the base and six at the top, with a multi-level finish for the concrete surface.
This milestone highlights Sumadhura Group’s use of cutting-edge engineering, advanced construction techniques, and efficient logistics, reaffirming their leadership in delivering high-quality, innovative projects.
Naveen Kumar Gunda, Director-Operations, Sumadhura Group said, “With this significant achievement, we have not only made substantial progress in the construction and development of our project, Palais Royale, we have set a new standard for construction in the residential real estate landscape of Hyderabad. Through efficient execution and a commitment to high-quality standards, we have showcased our expertise in managing complex mega projects, ensuring seamless operational efficiency, and utilizing advanced construction techniques. On this occasion, I would like to express my gratitude and congratulate Sumadhura’s team of professionals for their unwavering dedication and commitment in achieving this milestone. Our goal is to pioneer modern construction techniques in the real estate sector and this accomplishment marks another significant step towards attaining that vision. We will continue to achieve several of these milestones that our customers, partners, and team members can take pride in.”
Although the task presented a significant challenge, the project organizers and managers prioritized the safety of the workmen on-site. The operation began with the challenge of preparing and clearing the roads leading to the construction site, ensuring minimal disruption to public use. This project was carried out in the heart of the financial district, where managing traffic posed a significant challenge, further showcasing the ability to deliver outstanding results under demanding conditions.
One of the most prestigious offerings by Sumadhura, Palais Royale is spread across 7.35 acres of land parcel with a saleable area of 2.6 mn sq ft.The offering will feature a magnificent 52-storeyed high-rise tower spread across three wings and comprise of 523 units of 4 & 5 bed residences. This uber-luxury residential project is located at the Financial District of Hyderabad, which offers seamless connectivity to major business hubs, entertainment zones, and lifestyle destinations. The project commenced in July 2024 and is expected to be completed towards the end of 2029.
2 comments
-
Setting records like pouring 6000 MT of concrete in 50 hours is undoubtedly a remarkable logistical achievement, but it raises significant concerns about quality and long-term structural integrity. Rapid construction often challenges, Quality Control uniformity, and compaction, potentially leading to cracks, reduced strength, and durability issues if not properly managed. A robust testing regime, including slump tests, cube tests, and real-time monitoring, is essential to ensure compliance with standards, but such speed may limit the time for systematic testing and risk the occurrence of segregation,, or uneven stress distribution. Worker fatigue during prolonged operations can further compromise vigilance and oversight, increasing the likelihood of errors. While such milestones are motivating for stakeholders, they should never overshadow the primary goal of constructing safe, resilient structures. Achievements like these must be backed by rigorous quality control and adherence to engineering standards to ensure they are not at the expense of safety or long-term performance.
-