Liebherr Cranes Install Key Structures for New Landgrafen Bridge in Germany’s Ahr Valley

liebherr-ltm1750-richter
Two Liebherr LTM 1750-9.1 mobile cranes operated by Richter Kran und Schwerlast GmbH have successfully installed major bridge components and steel structures for the new Landgrafen Bridge in Bad Neuenahr-Ahrweiler, Germany.

The lifting operation marks a significant milestone in the reconstruction of infrastructure in the Ahr Valley, where the original bridge was completely destroyed during the devastating floods of July 2021.

The project was undertaken for construction company Leonhard Weiss GmbH & Co. KG and heavy haulage and crane specialist Dietmar Floßdorf GmbH & Co. KG. The two Liebherr heavy-duty cranes were deployed to handle the precise installation of heavy bridge elements and steel structures.

Tandem lift of 105 tonnes at a reach of up to 38 metres

The focus of the operation was the lifting of a bridge segment with a total weight of 105 tonnes, which was moved jointly by both LTM 1750‑9.1 cranes in a tandem lift. The maximum outreach was 38 metres. Both cranes were configured with a 28-metre luffing jib and 204 tonnes of counterweight each, thus providing the necessary reserves for the precise lift.

Due to the confined space directly on the banks of the River Ahr, the cranes had to be set up close together. An additional technical feature was the use of a triangular spreader, which ensured that the load was distributed evenly between both cranes.

Lift in the early hours of the morning – for good reason

The crucial main lift was deliberately carried out at 4 am. At this time of day, temperatures were at their lowest, thereby minimising the thermal expansion of the steel component. At higher temperatures, there would have been a risk that the bridge girder would not have fitted precisely into the designated abutments due to expansion.

“The team and everyone involved did an excellent job. The operation went ahead without any complications or incidents – exactly as planned,” says Thorsten Mahlberg, project manager at Dietmar Floßdorf GmbH & Co. KG.

Precision work in a very confined space

The logistical and technical challenges began right from the set-up stage: first, the first LTM 1750‑9.1 was positioned and erected. This crane then assisted with the set-up of the second unit. During the tandem lift, the utmost concentration was required – particularly to ensure the load on the triangular crossbeam remained precisely and evenly distributed at all times.

“A specialised operation in very confined spaces. A major challenge – but in the end, everything went to plan,” reports Manuel Bergmann, crane operator of the blue LTM 1750‑9.1. Michael Schmieder, operator of the white LTM 1750‑9.1, also emphasises the precision required: “We had to work with great concentration and precision to keep the load on the triangular crossbeam and on both cranes constant. I’m very relieved that everything went according to plan.”

The successful tandem lift impressively demonstrates how high-performance crane technology, careful planning and an experienced team enable precise and safe solutions even under the most difficult conditions. Once the main assembly was complete, one of the LTM 1750‑9.1s was dismantled, whilst the second crane was moved to the opposite bank to carry out further remaining work there.
📅 Published on: 23 June 2026
🔗 Share:
We Value Your Comment
How useful is this information?

NBM Media

30+ years of reporting on infrastructure, construction, architecture, & real estate across print, digital, and social media.