Cabinet Approves Pune Metro Phase-2 Line 4 and 4A; Rs 9,857.85 Cr Project

Pune-Metro-Phase-2-Map
The Union Cabinet, chaired by Prime Minister Narendra Modi, has approved Line 4 (Kharadi–Hadapsar–Swargate–Khadakwasla) and Line 4A (Nal Stop–Warje–Manik Baug) under Phase-2 of the Pune Metro Rail Project. This is the second major approval under Phase-2, following the sanction of Line 2A (Vanaz–Chandani Chowk) and Line 2B (Ramwadi–Wagholi/Vitthalwadi).

Spanning 31.636 km with 28 elevated stations, the two corridors will enhance connectivity across East, South, and West Pune—linking IT parks, commercial hubs, educational zones and key residential clusters.

The project, estimated at Rs 9,857.85 crore, will be completed in five years and jointly funded by the Government of India, Government of Maharashtra and external bilateral/multilateral agencies.

These lines are a vital part of Pune’s Comprehensive Mobility Plan (CMP) and will seamlessly integrate with operational and sanctioned corridors at Kharadi Bypass & Nal Stop (Line 2), and Swargate(Line 1). They will also provide an interchange at Hadapsar Railway Station and connect with future corridors towards Loni Kalbhor and Saswad Road, ensuring smooth multimodal connectivity across metro, rail, and bus networks.

From Kharadi IT Park to Khadakwasla’s scenic tourist belt, and from Hadapsar’s industrial hub to Warje’s residential clusters, Line 4 and 4A will knit together diverse neighbourhoods. Traversing Solapur Road, Magarpatta Road, Sinhagad Road, Karve Road, and the Mumbai–Bengaluru Highway, the project will ease congestion on Pune’s busiest routes while improving safety and promoting green, sustainable mobility.

According to projections, the daily ridership on Line 4 and 4A combined is expected to be 4.09 lakh in 2028, rising to nearly 7 lakh in 2038, 9.63 lakh in 2048, and over 11.7 lakh in 2058. Of this, the Kharadi–Khadakwasla corridor will account for 3.23 lakh passengers in 2028, growing to 9.33 lakh by 2058, while the Nal Stop–Warje–Manik Baug spur line will rise from 85,555 to 2.41 lakh passengers over the same period. These projections highlight the significant growth in ridership expected on Line 4 and 4A over the coming decades.

The project will be implemented by Maharashtra Metro Rail Corporation Limited (Maha-Metro), which will carry out all civil, electrical, mechanical, and systems works. Pre-construction activities such as topographical surveys and detailed design consultancy are already underway.

With this latest approval, Pune Metro’s network will expand beyond the 100 km milestone, a significant step in the city’s journey towards a modern, integrated, and sustainable urban transit system.

With Line 4 and 4A, Pune will not just get more metro tracks, it will gain a faster, greener, and more connected future. These corridors are designed to give back hours of commuting time, reduce traffic chaos, and provide citizens with a safe, reliable, and affordable alternative. In the years ahead, they will emerge as the true lifelines of Pune, reshaping urban mobility and redefining the city’s growth story.
📅 Published on: 27 November 2025