Apurvakriti Infra Begins Track Work for Mumbai Metro Line 4 & 4A
Apurvakriti Infrastructure has started track plinth casting at Majiwada station for Mumbai Metro’s Line 4 & 4A (Green Line). Line 4 spans 32.32 km from Bhakti Park (Wadala) to Kasaravadavali with 32 stations, while Line 4A adds 2.88 km from Kasaravadavali to Gaimukh via 2 stations. This work is part of Package CA-161, a ₹21.88 crore contract awarded by MMRDA in September 2023, with a two-year track installation deadline. Apurvakriti will install ballastless tracks on the 15.77 km section between Mulund Fire Station and Gaimukh, including a siding track at Gaimukh Station.