The art of Scaffolding - Layher Allround Bridging Systems Ideal to Access Railway Station
Mithilesh Kumar, Director, Layher Scaffolding Systems Pvt Ltd
Railway Station in Melbourne, Australia
When a footbridge is built, the Allround bridging system is connected to Allround standards using the wedge-heads provided on the sides of the posts. Depending on application, either event decks or steel decks can be used. The bridge can also be clad using Layher Protect cassettes and roofed. The bridge is mounted on Layher heavy-duty supports with specially designed support elements. These support elements permit pre-assembly on the ground and subsequent insertion by crane, which is a major advantage when spanning bridges across roads.
Application of Layher Allround Bridging Systems to Access Station
Refurbishing work with ongoing operation: after demolition of the existing bridge, a temporary bridge solution was needed to allow passengers to cross the tracks safely. This is where the flexibility of Layher’s Allround equipment came into its own. With the Allround bridging system, efficient building was possible not just of two free-standing bridges, its rapid assembly: the combination with the Allround construction kit also permitted integration of a stairway structure plus a wheelchair ramp for unimpeded access.When railway stations are refurbished, their highly frequented nature plus the need to maintain rail services are severe challenges for the planners. A current example: demolition of a pedestrian bridge. To ensure that railway passengers can continue to cross the tracks safely during new construction work, a temporary and free-standing bridge including stairway access and – for unimpeded access – a wheelchair ramp each having an effective loading capacity of 5 kN/m² were needed which is fulfilled by using combination of Layher Allround wedge head connection, Bridging Systems and its comprehensive range of components plus supplementary parts with unlimited possibilities for use.
Railway Station in Melbourne, Australia
Access to the bridges took the form of two stairways and a wheelchair ramp. For these jobs too, the Layher product range always has the right components to hand: from lightweight aluminium platform stairways and separate stairway stringers for different loads, to child safety guard rails. For the safety of the many passengers, the scaffolding constructors selected for the stairway access two parallel structures to match the double bridge solution. The combination of size 750 stairway stringers and standard decks used as steps permits variable widths of the stairways: in this case 2 metres, matching the width of the bridges. Thanks to the convenient pitch dimensions, the size 750 stairway stringer is also ideal for public areas.
The 100 metre long wheelchair ramp was also built on the basis of the Layher system range. For the substructure, the scaffolding erectors chose a combination of lattice beams and Allround equipment. Thanks to the option of flexible height adjustment, the ramp could be built with exactly the required inclination of 4 degrees including its horizontal intermediate platforms – and in a space-saving U-shape. Wheelchair-suitable and child-safety guard rails ensure a high degree of safety during use. In this way, the Layher Allround Bridging systems build a solution for access of passengers which is not only tailor-made, but also economical and time saving (constructed in just 10 days).
NBM&CW August 2014