HCC completes first 3.82 km tunnel for Mumbai Metro III project

HCC long tunnel
In a significant milestone for the city’s metro network, Hindustan Construction Company Ltd. (HCC), completed the south bound tunnel between CST and Mumbai Central stations today. With this, HCC became the first contractor among all packages to complete the entire length of a tunnel. With an average drilling rate of around 8.2 meters per day the 3.82 km long tunnel from CST to Mumbai Central via the station boxes at Kalbadevi, Girgaon and Grant Road, was completed surmounting various challenges.

HCC team faced several geological and urban condition challenges, including the project’s proximity to the sea, tunnelling through heterogeneous reclaimed land, congested working areas and tunnelling below some of the oldest residential buildings that are over 100 years old without disturbing them. MMRCL had awarded the contract to HCC in July 2016, for the Design and Construction of Twin Tunnels by Tunnel Boring Machine (TBM) method and construction of 4 Under Ground Metro Stations at C.S.T, Kalbadevi, Girgaon and Grant Road.

HCC procured two TBMs from China with 117 m long single shield dual-mode hard rock with a 6.68 m diameter and weighing around 848 MT. It is equipped to operate in both, open or closed mode, in the predominantly fresh and slightly to moderately weathered Basalt and Breccia that was anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, HCC team successfully launched Vaitarna I (the first TBM) from the project site at Chhatrapati Shivaji Terminus on December 04, 2017. The initial drive for Vaitarna I was completed on January 11, 2018 and the Main Drive started in the 2nd week of February 2018. This TBM requires around 32 people to operate, which includes TBM operators, engineers and labourers.

HCC long tunnel projectHCC completes the 3.82 km long tunnel passing through most thickly populated areas of Mumbai between CST and Mumbai Central stations as part of the Metro III project.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to the tunnelling work, a structural survey was carried out in a 30m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. Various monitoring instruments such as Inclinometers, Magnetic Extensometers, Piezometers, Rod Extensometers, Precise level markers, Bi-Reflex targets and Crack meters, were installed at regular intervals to check and regulate ground movements to the designated limits during and after the tunnelling work.

Overcoming all the challenges the experienced HCC team managed to complete the tunnelling well within the stipulated timeline. The construction of Station buildings is currently underway. While all the station buildings are unique in design, the CST station is completely a cut and cover station, the remaining three stations would be made by NATM method.

Realtors relish ₹10,000-cr package for realty sector

Realtors have hailed the government's announcement of ₹10,000 crore special windows to provide last-mile funding for completion of ongoing housing projects which are not NPAs or facing bankruptcy proceedings Read More ...

Prestige realty enters NCR' plans ₹500-cr project

Prestige Estates has decided to foray into the Delhi-NCR market and has tied up with local developer Ace Group to launch its first housing project in Noida with an investment of around ₹500 crore. Group CEO Venkat K Read More ...

Govt awarding ₹2 lakh-cr tender for smart cities

In order to fast-track implementation of the Smart Cities Mission (SCM), the government is set to award tenders worth over ₹2 lakh crore. Apart from this, to complete these projects with finishing touches, smart city Read More ...

DURASHINE® from Tata BlueScope Steel is India's Most Trusted Brand 2019

DURASHINE®, which has received this recognition for the third time under the Colour Coated Steel Sheets category, was once again unanimously chosen by consumers through a country-wide survey conducted by IBC Info Media Read More ...

CDE attends the Urban Innovation Summit

CDE recently participated in the Urban Innovation Summit held in Lucknow. The Summit saw a formidable representation of industry experts, government officials, and corporate houses who are working towards the cause Read More ...

Road projects of ₹5 lakh-cr reach contract award stage

In a major booster to the ailing construction equipment and commercial vehicle sector, Union road transport minister Nitin Gadkari has said that the government is rolling out mega road construction projects worth Read More ...

PM launches ₹20,000-cr metro corridors in Mumbai

The Prime Minister during his recent visit to Maharashtra has laid the foundation stones for three metro projects, which will together add more than 42-km to the existing metro rail network in the city. The three corridors Read More ...

Cabinet clears ₹3,439-cr for Konkan rail connectivity

The union cabinet has approved ₹3,439 crore for rail connectivity between Konkan and western Maharashtra linking Vaibhavwadi (Sidhudurg) and Kolhapur. The entire project will be commissioned by the year 2023. According Read More ...

TN takes up ₹3,088-cr multi-deck elevated corridors

The Tamil Nadu government has decided to build a ₹3,088 crore multi-deck elevated transport corridor in Old Mahabalipuram Road (OMR) in a phased manner. The project is aimed at decongesting the road from Taramani to Read More ...

BoB approves ₹2,000-cr for Bundelkahnd e-way project

Bank of Baroda has sanctioned ₹2,000 crore for the ambitious Bundelkahnd Expressway project in Uttar Pradesh. With this initiative, other banks would also be able to fast-track the loan proposals under their consideration Read More ...

Railway explores PPP funding for ₹36,000-cr projects

The Mumbai Railway Vikas Corporation (MRVC) has initiated steps for funding two of its three projects worth ₹36,000 crore proposed under the Mumbai Urban Transport Project (MUTP)-4 on PPP model. The three projects Read More ...

Haryana clears ₹2,196-cr rail lines

The decks have been cleared for construction of two rail lines in Haryana as the Haryana Rail Infrastructure Development Corporation has completed its DPR for ₹2,196 crore rail projects. With the construction Read More ...

Blackstone in JV plans 20-mn sqft realty project

American private equity major Blackstone Group and realty developer K Raheja Corp in a joint venture have decided to take up a jointly-owned 20 million sqft commercial project, said official sources adding that the Read More ...

BEML delivers first driverless coach to Mumbai metro

BEML has recently supplied the first driverless metro coach to Mumbai Metropolitan Area Development Authority's (BMRDA). A part of the order by Mumbai Metro Rail Corporation (BMRC) for 500 coaches, it will be used Read More ...

Decks cleared for riverfront projects in Thane

Decks have been cleared for the river front projects in the Thane area of Mumbai with the Bombay High Court having recently allowed the development of eight waterfront projects, a pet project of the city's municipal Read More ...

BRO launches Miao-Vijoynagar road project in NE

The inspection and soil testing has been initiated by the BRO on Miao-Vijoynagar road project in Changlang district of Arunachal Pradesh, Additional Director General (East), BRO, PKH Singh, said that a meeting Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week