TBM Launching Near Seashore: Ground Improvement by ITD Cementation

Dr. Tanumaya Mitra, Sudip Kumar Koley, Padma Tiruvengala, Naru Raju, and Prodyot Kumar Ray, at ITD Cementation India present the ground Improvement requirement for a TBM launching under Shallow Overburden close to a seashore.

Tunneling under shallow overburden is always a challenging aspect due to the possibility of blow out because of application of higher face pressure or segment uplift as there are always certain lengths of tunnel linings located in the unsolidified grout. As a result, the buoyancy induced by unsolidified grout and hydrostatic pressure may be higher than the lining gravity, which leads to the lining uplift tendency.

TBM launching under Shallow Overburden


The presence of a high water table complicates the situation even more. In the current project, TBM launching site was very close to the seashore line. The water table is almost at ground surface. Soil cover above the TBM tunnel varies from 4m to 6m for about 70 m length from the launching shaft. The soil profile consists of 6.0 m thick loose to medium dense silty sand (Navg = 8) followed by 5.5 m thick loose silty sand (Navg = 3-4) layer underlain by 4.5 m thick, soft to very stiff sandy clay layer (Navg = 22) and silty sand layer, respectively.

The combination of low soil cover, presence of a high water table and loose silty sand makes the TBM launch a daunting task. Prediction of ground movements is an essential task prior to TBM tunnelling. Hence, assessment of predicted ground movements using 2D and 3D numerical analysis, simulating the field conditions, was done.

3D Numerical Modelling of Tunneling Using EPB TBM: The steps include application of face pressure, excavation of soil slices, tail void grouting, advancement of TBM with thrust force from hydraulic jacks and installation of tunnel lining segments. A slurry wall was considered in front of the TBM launching area.

2D Numerical Modelling of Tunneling Using EPB TBM: A 2D analysis was also carried out using the same parameters to simulate the field condition. Maximum ground settlement obtained from the 2D analysis is presented in Fig. 3 and Table 2.

TBM launching under Shallow Overburden

 

Proposal of Ground Improvement Scheme and Requirement of Ground Improvement for Initial Drive

M10 concrete PCC panels of 10.0 m Length and 2m below the tunnel invert level

  • For preventing inflow of groundwater in the launching shaft
  • For limiting the potential settlements, to avoid excessive loads on D/Wall

Permeation grouting / TAM grouting

  • For preventing the running ground / cohesionless soil with water into cutter head during the initial drive after passing through the PCC panels.
  • For reducing the permeability of the sandy soil.
  • For minimizing ground movements during the initial drive under shallow overburden.

Application of Surcharge in the form of sand filled muck box

  • For preventing blow out due to accidental high face pressure
  • For preventing segment uplift
TBM launching under Shallow Overburden


Figure 4 shows the Plan of the TAM grouting area divided into six areas. The outer periphery is for Curtain grouting. The plan of the TBM launching and initial drive zone along with the provisions of PCC panels and muck carts is depicted in Fig. 5.

TBM launching under Shallow Overburden


Groutability check was done using the criteria proposed by Huang et al. (2007). Initial Trial field works were carried out. Based on the observations of the Trial works, modification in terms of grout quantity and the methods was decided. Curtain grouting was carried out using the combination of Sodium silicate and OPC grout at 1.0 m c/c all around the periphery of the area considered for the grouting. Primary grouting carried out using 1:1 mix using OPC and water and later secondary grouting and tertiary grouting carried out based on the requirement.

6 Number Field Permeability Tests carried out pre & post TAM grouting. 3 number test results at 5m to 6m test depth had to be discarded for comparison as Ground Water Table was affecting the test results.

TBM launching under Shallow Overburden


Instrumentation and Monitoring were done by placing ground settlement markers along different arrays to monitor the ground deformation due to tunneling . The maximum settlement at the chainages mentioned in Table 4 is 54.0 mm and 60.0 mm under an overburden of 4.5 m to 5.1 m. Table 5 presents the comparison of ground settlement values obtained using numerical analysis and I & M data.

NBM&CW - May 2025

No comments yet, Be the first one to comment on this.

India's Underground Construction: Tunnels for Growth

India's Underground Construction: Tunnels for Growth

India’s underground construction industry is undergoing a seismic transformation. Driven by rapid urbanization, strategic infrastructure needs, and technological advances, the nation is tunnelling through mountains, rivers, and mega cities

Read more ...

Construction of Vishnugad Pipalkoti HE Project: GR Infraprojects

Construction of Vishnugad Pipalkoti HE Project: GR Infraprojects

Dr. Rakesh Kumar Khali, Vice President Operations - Tunnel & UG Works, G R Infraprojects Limited, discusses the construction of Desilting Chambers and Connecting Tunnels for Vishnugad Pipalkoti HE Project, and highlights the planning process

Read more ...

Tunnels and Underground Spaces in Nuclear Power Plants

Tunnels and Underground Spaces in Nuclear Power Plants

As India accelerates its transition toward sustainable energy, nuclear power is emerging as a crucial pillar of low-carbon electricity generation. In this context, the innovative use of tunnels and underground spaces is redefining how nuclear

Read more ...

Curetec: Outperforming Competitors in Tunnel Segment and Sleeper Curing

Curetec: Outperforming Competitors in Tunnel Segment and Sleeper Curing

We are building tunnel segments efficiently, sustainably, and with precision for strength and durability, avers André Dienst, Managing Director.

Read more ...

Underground Construction with Diaphragm/Slurry Walls

Underground Construction with Diaphragm/Slurry Walls

The diaphragm or slurry wall technique, as discussed by Dr. N. Subramanian, represents a major advancement in modern underground construction. It offers significant benefits, including excavation stabilization, effective groundwater barriers

Read more ...

Managing Tunneling Induced Ground Movements: Geocomp

Managing Tunneling Induced Ground Movements: Geocomp

Instrumentation and monitoring are crucial for ensuring safety, stability, and quality in tunneling projects. With tunnels and metro lines being constructed worldwide, it is essential for geotechnical engineers to understand the risks

Read more ...

Why Concrete in Road Tunnels Decomposes Unexpectedly Fast: Research

Why Concrete in Road Tunnels Decomposes Unexpectedly Fast: Research

When seawater penetrates concrete in road tunnels, a biofilm is formed that breaks down the concrete. This can lead to high costs and the risk of damage if stone and concrete drop from the tunnel roof. In a new study, carried out in

Read more ...

Chinese-made TBM Exported to Solomon Islands for First Time

Chinese-made TBM Exported to Solomon Islands for First Time

On February 17th, 2025, Tunnel boring machine "Shuangjing No.1" with an excavation diameter of 4.48 meters was off the production line at the second industrial park of China Railway Construction Heavy Industry Corporation Limited (CRCHI) in Changsha.

Read more ...

Quazigund-Banihal Tunnel An Engineering Marvel

Quazigund-Banihal Tunnel An Engineering Marvel

Sanjay Kumar Sinha, Founder and Managing Director, Chaitanya Projects Consultancy, gives an inside view of how Chaitanya Projects skilfully maintains the arterial Quazigund-Banihal Tunnel in J&K, and explains the technical intricacies

Read more ...

Normet SmartScan Technology: Real-Time Monitoring of Shotcrete Application

Normet SmartScan Technology: Real-Time Monitoring of Shotcrete Application

In recent years, shotcrete technology for underground rock support has seen significant advancements, particularly with the integration of digital technologies like SmartScan and other IoT-based innovations. SmartScan, a cutting-edge

Read more ...

Innovations in Tunnelling Technologies in Hydro Project

Innovations in Tunnelling Technologies in Hydro Project

Dr. Rakesh Kumar Khali, Vice President - Operations, (Tunnel, UG Structures & Hydro Power), G.R. Infraprojects Ltd., describes the construction of the Tehri Pump Storage Project (4X250 MW) and the innovative technologies in Vertical Shafts

Read more ...

CRCHI Mining Tunnel Boring Machine (TBM) Exported to Africa

CRCHI Mining Tunnel Boring Machine (TBM) Exported to Africa

On December 18th, 2024, the FAT ceremony of mining TBM exported to Africa was held in Changsha, China. This equipment, manufactured by China Railway Construction Heavy Industry Corporation Limited (CRCHI), will be applied in the tunnel

Read more ...

Construction of Tunnel T-49A on Dharam-Qazigund Section of USBRL

Construction of Tunnel T-49A on Dharam-Qazigund Section of USBRL

Dr. Rakesh Kumar Khali, Vice President Operations-Tunnel & UG Works, G R Infraprojects, and Sharanappa Yalal, Cluster Head, J&K, Hindustan Construction Company, highlight the planning process, execution challenges, innovations

Read more ...

Robbins India to Establish TBM Manufacturing Facility in Vadodara

Robbins India to Establish TBM Manufacturing Facility in Vadodara

Encouraged by the growing business opportunities in tunnel construction for transportation infrastructure in India, Robbins India is establishing an integrated, in-house manufacturing setup in the country. This was announced

Read more ...

CRCHI Large Diameter Open-type Rock TBM Rolls off Assembly Line for South-to-North Water Diversion Project

CRCHI Large Diameter Open-type Rock TBM Rolls off Assembly Line for South-to-North Water Diversion Project

On November 22, 2024, the open-type rock TBM with an excavation diameter of 11.93 meters (the largest of its kind in China), rolled off the assembly line of China Railway Construction Heavy Industry Corporation Limited (CRCHI).

Read more ...

Record Rewritten! Chinese-made Largest Diameter (16.64 -m) Shield Machine ‘Jianghai’ Rolls off at CRCHI

Record Rewritten! Chinese-made Largest Diameter (16.64 -m) Shield Machine ‘Jianghai’ Rolls off at CRCHI

On October 31, 2024, a super-large diameter shield machine with a maximum excavation diameter of 16.64 meters rolled off the production line in Changsha, Hunan. It will be used in the construction of the world's longest underwater highway

Read more ...

India's Tunnelling Landscape: Advancements, Challenges & Future Outlook

India's Tunnelling Landscape: Advancements, Challenges & Future Outlook

Tunnelling has played a crucial role in shaping India's infrastructure landscape. From the early hand-drilled techniques employed during railway construction in the 1800s to the state-of-the-art technology driving modern metro projects

Read more ...

Minister of Road Transport & Highways: India’s Ambitious Tunnelling Plans

Minister of Road Transport & Highways: India’s Ambitious Tunnelling Plans

Shri Nitin Gadkari, Minister of Road Transport and Highways, emphasizes the importance of robust infrastructure for economic growth and outlines the government's ambitious plans for investing in high-quality tunnels, bridges, and roads.

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.