MoRTH approves ₹2,228-cr for NH projects in Goa

As of now, due to the pending work at Porvorim, traffic movement continues to be affected at the bottleneck between the Sangolda junction and Mall de Goa. In mid-2018, work on the project had commenced, but around 32 owners of houses and commercial establishments approached the Supreme Court, citing faulty land acquisition procedure. Now, a settlement has been reached and officials are targeting December 2025 for completion of the highway on stilts in Porvorim.