Indian Govt Extends Bharatmala Phase-I Completion Deadline to 2027-28

The Indian government grants a six-year extension
The Indian government grants a six-year extension, pushing the completion deadline of Bharatmala Phase-I to 2027-28. As of November 2023, 15,045 km (42 percent) of the project has been completed, with 26,418 km (76 percent) of highway stretches awarded. The revised completion schedule aims to expedite approvals for the remaining 40,412 km, addressing financial constraints and implementation challenges. The estimated project cost has risen to nearly Rs 11 trillion, reflecting increased expenses and the need for strategic planning.
📅 Published on: 27 December 2023