Completes 13 Deck Slabs in 46 days

Ashoka Buildcon Sets Another Milestone at Bundelkhand Expressway

The Bundelkhand site team achieved yet another feat on 15 Jan 2022 by completing 13 deck slabs of varying types in just 46 days. Therefore, it is a demonstration of exemplary display of overall project executing capabilities of the organization, similar to continuous laying of Dense Bituminous Macadam (DBM) and Bituminous Concrete (BC) layers executed in recent past at this project only.

The site has decked 12,000 sqm for various structures which were in different stages of works on 1st December, before embarking on decking works (listed Table 1):

Sl. No Structure type Deck Area Status as on Dec 1st 2021 Slab Completion Date
1 Major Bridge at 138 (3 Spans ) 100.15*17.5*2 = 3505 sqm Girder in two spans (10 Nos) yet to be launched on RHS Diaphragms were in progress in LHS slab LHS : 15th Dec 2021 RHS : 11th Jan 2022
2 Flyover @ 141 (2 spans) 60*17.5 *2 = 2100 sqm Only 5 girders launched out of 20. LHS : 24th Dec 2021 RHS : 15th Jan 2022
3 Minor Bridge @ 119 (2 spans) 50.69*17.5*2 = 1775 sqm Girders launched with completion of Diaphragms.  Reinforcement nearing completion for RHS RHS : 1st Dec 2021 LHS : 27th Dec 2021
4 Minor Bridge @ 120 (single span) 39.8*17.5*2 = 1393 sqm Girders launched without diaphragm construction RHS : 12th  Dec 2021 LHS : 4th Jan 2022
5 5 cell Minor Bridge @126 57.46*17.5*2 = 2011 sqm Reinforcement near completion for LHS. Six lifts wall to be taken up for RHS. LHS : 1st Dec 2021 RHS: 18th Dec 2021
6 4 cell Minor Bridge cum LVUP @ 136 MNB : 45.80 *17.5*1 = 802 sqm
LVUP : 11.82*17.5 *2 = 414 sqm
Reinforcement for MNB in progress. VUP Raft completed for both carriageways. MNB RHS : 17th Dec 2021 LVUP LHS : 29th Dec 2021 LVUP RHS : 4th Jan 2022
  Total Deck Area 12000 sqm    
Equivalent 3-lane bridge deck construction of 1.142 km in 46 days
Quantum of work for the above structures:
  • Concrete : 5617 cum
  • Reinforcement steel : 1091 tons
The Structures team at site has simultaneously launched the balance 25 girders in just 6 days, handling almost 1705 tons to facilitate completion of the slab work at the Major Bridge and Flyover.

Ashoka Buildcon Sets Another Milestone at Bundelkhand Expressway

Other key factors considered towards mobilization of formwork materials to match the speed, de-shuttering from one side and re-using at second side, shifting of materials from one location to another, staging activities in box structures, and completion of wall in a few structures, to ensure deck slab concreting in record time.

Approximately 460 labourers were on the task to achieve this intended outcome. Innovative strategies included usage of profile deck-sheeting, small brackets between girders to fix reveal pins, plyboard shutters for diaphragm works for easy handling, deploying separate gangs for each span to work parallelly etc. to ensure that the project meets client’s requirement of opening both sides of the carriageway before March 2022.

The mission was targeted for completion in maximum 35 days but the rains that lasted for almost six days and the extreme cold in the last week of December led to some breaks in the work.

In doing so, Ashoka Buildcon Limited has put its place in the map of Bundelkhand Expressway Project for completing all the slabs of Main Carriageway ahead of other packages of the projects, and this led to Customer Delight experience for all stakeholders including UPEIDA.

This challenging mission was possible due to support of UPEIDA, ICT and RITES.
Subgrade makes the formation level of the road crust. The material specifications of subgrade material are therefore more demanding than the soil used in general fill or embankment. In some construction projects, it becomes difficult to get the required subgrade

Read more ...

Atasi Das, Assistant Vice President, G R Infraprojects, explains the concept of the Perpetual Pavement in India’s expressway constructions and its practical implementation with due consideration of layers, materials, and thicknesses

Read more ...

Dr. Rakesh Kumar, Senior Principal Scientist & Pankaj Goel, Senior Technical Officer, Rigid Pavements Division,CSIR-Central Road Research Institute (CRRI), New Delhi, give information on the Performance of Curing Compounds in Strengthening

Read more ...

The construction and maintenance of roads with flexible pavements in very cold regions where annual temperatures range between +30oC to -35oC has got its own challenges. The bitumen in the asphalt layer becomes hard at such low temperatures

Read more ...

Er. Devjyoti Paul, Project Manager & Er. Harpreet Singh, Chief Project Manager, B&SEC, share the technical and construction features of three bowstring girder ROBs, recently constructed under Package I & III of Purvanchal Expressway in the state of Uttar Pradesh

Read more ...

Use of Extruded Polystyrene Sheets (XPS) in the construction of the Zojila Approach Road has been especially effective as XPS is the most suitable, convenient, and cheaper solution for mitigating frost action on pavements, increasing the life of pavements

Read more ...

The Indian road network is the second largest globally, with a length of around 63.86 lakh km. The outbreak of the virus towards end-FY20 had created panic globally, leading to the temporary suspension of economic activity

Read more ...

Roads and Railways boost awards; tenders up marginally Overall tendering grew 5% YoY during H1FY22 Awarding activity grew at a 2-year CAGR of 22% in H1FY22 Infrastructure credit near all-time highs

Read more ...

There are many challenges being faced by the highway sector such as ensuring availability of construction materials and machinery, timely completion of projects, availability of trained human resources

Read more ...

Practical Recommendations for Construction of Longitudinal Joints in Hot Mix Asphalt (HMA) Pavements Rajib B. Mallick, Ralph White Family Distinguished Professor, Civil and Environmental Engineering, Worcester Polytechnic Institute (WPI), Massachusetts, USA, and Veeraragavan

Read more ...

Plant and Equipment Determine Quality of Road Construction Road Infrastructure projects are time constrained; early completion of project entitles rewards while delays attract penalties. The plants and equipment being used determines the quality of the road

Read more ...

Designing roads and highways efficiently with the right materials will help achieve optimum construction cost, lower maintenance, and reduce life cycle costs. Ash from coal-fired thermal power

Read more ...

Rodic Consultants has emerged as a leader in the infrastructure consulting space with state-of-the-art engineering solutions, and a proven track record of timely completion of projects across sectors

Read more ...

Readymade Kandhal Pothole Patching Mix was adopted as Indian Roads Congress (IRC) Standard Specification IRC: 116-2014 for Readymade Bituminous Pothole Patching Mix Using Cut-Back Bitumen. All concerned

Read more ...

The Bundelkhand Expressway is a 296-km long, 4-lane wide (expandable to 6 lanes) access-controlled expressway in the state of Uttar Pradesh. It will connect Gonda village in Chitrakoot district with Agra–Lucknow

Read more ...

This case study briefly discusses the planning, design and construction of Package 3 of the Purvanchal Expressway. Package-3 of the Purvanchal Expressway is a 41.7km long section of the 340.82km long

Read more ...

Since the 1980’s billions of dollars have been invested in developing methods to make pavement design and construction more sustainable through the re-use of existing resources. This includes insitu recycling and

Read more ...

India has the second largest road network in the world, spanning a total of 5.89 million km, transporting 64.5% of all goods in the country. Nearly 90% of India's total passenger traffic uses the road network to commute

Read more ...

India generates nearly 26,000 tonnes of plastic waste every day, making it the 15th biggest plastic polluter globally. Discarded plastic waste litter the country’s roads, rivers and also form huge mounds in garbage

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.
Click here to subscribe.