Ashoka Buildcon Sets Another Milestone at Bundelkhand Expressway

Completes 13 Deck Slabs in 46 days

Ashoka Buildcon Sets Another Milestone at Bundelkhand Expressway

The Bundelkhand site team achieved yet another feat on 15 Jan 2022 by completing 13 deck slabs of varying types in just 46 days. Therefore, it is a demonstration of exemplary display of overall project executing capabilities of the organization, similar to continuous laying of Dense Bituminous Macadam (DBM) and Bituminous Concrete (BC) layers executed in recent past at this project only.

The site has decked 12,000 sqm for various structures which were in different stages of works on 1st December, before embarking on decking works (listed Table 1):