4/6 Laning Hyderabad – Vijayawada – Machilipatnam NH–9

Project Summary

Feasibility and Detailed Project Report for 4/6 Laning of Hyderabad-Vijayawadaand Vijayawada-Machilipatnam Under NHDP Phase III

Organization: Scott Wilson Kirkpatrick India Pvt Ltd.

BE Awards Category: Civil Road Infrastructure

Location: India

Project Objective: Widening India’s NH-9 from Hyderabad to Machilipatnam, including evaluation of multiple bypass options for eight sections of roadway.

Bentley Products

MXROAD V8 XM Edition

India’s NH-9 highway runs from Hyderabad, the capital city of state of Andhra Pradesh, to Machilipatnam, a port on the Bay of Bengal. As part of its National Highways Development Project, an ambitious four-phase program to upgrade about 25,000 kilometers of key national highways, the National Highways Authority of India (NHAI) plans to expand this road from two to four or six lanes and examine alternative alignments at certain towns to alleviate congestion.

The expansion will employ a buildoperate- transfer model, under which the government carries out preliminary work such as land acquisition and utility removal before turning the construction and operation over to a private concessionaire. Scott Wilson Kirkpatrick India Pvt Ltd (SWK India) was contracted by NHAI to prepare a feasibility study and detailed project report for the NH-9 expansion.

The project was split into two segments: the stretch from Hyderabad to Vijayawada and the stretch from Vijayawada to Machilipatnam. Highway construction is scheduled to start and finish by March 2010. The total length of the road is approximately 121 kilometers and the project cost is estimated to be $190 million.

Project Requirements

NH-9 runs mainly across a plain, with rolling terrain in some stretches. It passes through four major towns and many small villages along its route. The project itself includes 21 bridges, 197 culverts, and one railway crossing. The project is a partially controlled access road, so SWK India took this into consideration when planning the service roads and road safety, as well as the types of intersections, flyovers, and underpasses required.

As part of its work, SWK India examined the technical, economic, and financial viability of upgrading the two sections of NH-9 to a four–or six–lane divided highway. As the existing road was in good condition, the design called for the building of a new two-lane highway on one side of the existing road, with a median separating the two. Adopting this approach meant full utilization of the already acquired right of-way and reduction of time spent in securing additional land. However, the existing right-of-way proved to be minimal, so a large amount of private land had to be acquired. SWK India identified the additional land needed, generated the coordinate data, and staked the areas out on the ground before verifying and transferring the data back onto revenue maps used to contact landowners.

The project report provided designs for the highway, pavement (with options for flexible or rigid pavement), overlay, bridges, cross-drainage structures, grade-separated structures, and service roads. SWK India calculated quantities for many items and generated detailed working drawings as well as cost estimates. Other reports produced included the analyses of economic viability and environmental and social feasibility (with action plans as appropriate), as well as all documents needed for the bidding process.

NHAI also required SWK India to include the kind of financial returns that could be generated through tolls and other revenues. It would use these to help attract private businesses to build and operate its new roads. During the process, SWK India found that while the stretch from Vijayawada to Vuyyuru was likely to have sufficient traffic for a build-operate-transfer operator to recover its costs, the stretch from Vuyyuru to Machilipatnam did not. Having this data meant NHAI was able to seek assurances from the Andhra Pradesh state government over the planned development of Machilipatnam as a deepwater port facility, thereby increasing the amount of goods transported on that stretch of roadway.

Design in the Fast Lane

Initial topographic surveys took three to four months to complete, and during this process SWK India was able to fix preliminary alignments. Once the survey data was available, the firm could check them against field conditions using MXROAD and complete the detailed engineering of 121 kilometers of roadway.

NHAI identified eight locations where bypasses could relieve congestion near towns. For each bypass location, SWK India prepared several alternative alignments before running a cost/benefit analysis on each. The bypass for the towns of Kodad and Pamaru proved to be particularly challenging, as the alignments had to be routed to minimize interference with agricultural fields, cart paths, field channels, and a major canal surrounding the towns.

There were also situations in which a bypass had already been proposed and the land-acquisition process completed. In these cases, SWK India fixed the road alignment according to earlier plans using non-digital details provided by NHAI.

In total, SWK India ended up designing nearly 200 kilometers of road because of the multiple alignment options required. For each case, SWK India used revenue maps to determine the extent of land acquisition already completed as well as the new land required along the centerline of the planned route.

Finally, the road designs were evaluated for safety by outside experts. SWK India was able to create 3D visualizations of the project in order to convey sight distances and their suitability for the surrounding terrain along the road.

Venkat Sheela, principal engineer for SWK India, noted the robustness of MXROAD, including the ability to output the coordinates of utilities that needed to be moved, trees that needed to be cut, and structures that required complete removal. The software, he said, enabled an integrated workflow that extended from processing the survey data all the way through to preparing land-acquisition plans, relocating utilities, and generating quantity takeoffs. SWK India has used.

MXROAD for 12 years, and Mr. Venkat believes that it is “the right kind of software for such a complex project.” He added that the functionality of MXROAD helped the firm cut design time. The engineers prepared input files to create roadway edges, apply camber and superelevation as well as create verges, shoulders, lay-bys, median openings, junctions, and earthwork styles. Managing the different phases of engineering design on a single platform helped ensure a consistent and uniform design product, even extending to small details such as linetypes and styles. The coordinated workflow ensured that different departments were always working on the current version of the design.
NBM&CW December 2007
Performance of Thin White Topping (TWT) Overlay for NH-848

Performance of Thin White Topping (TWT) Overlay for NH-848

Vikas V. Thakar, MD, Pavetech Consultants India, presents the uses and advantages of TWT as a cost-effective treatment and a sustainable solution for rehabilitating and strengthening of flexible pavements, as seen in the NH-848 Nashik

Read more ...

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

Satish Pandey, Principal Scientist at CSIR-CRRI, New-Delhi, and Associate Professor, Academy of Scientific and Innovative Research, gives a brief overview of Hot Mix recycling process using bio-oil based rejuvenator REJUPAVE to facilitate

Read more ...

Safety Challenges On Indian Roads

Safety Challenges On Indian Roads

S.K. Nirmal, Secretary General, Indian Roads Congress, Director General (Road Development) & Special Secretary (Retd), MoRTH, gives an overview of India’s road network, causes of road accidents, and the safety measures and policies required

Read more ...

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

The Palkhi Marg holds deep significance as a pathway of faith for devotees of Lord Vitthal. Every year, thousands of ‘warkaris’ embark on a spiritual journey to the temple town of Pandharpur in Maharashtra. With the vision to create a Bhakti Marg and ensure

Read more ...

Delhi Vadodara Expressway Package-1 An overview

Delhi Vadodara Expressway Package-1 An overview

The Delhi-Vadodara Expressway is a part of the most anxiously awaited Delhi-Mumbai Expressway - the foundation stone for which was laid on March 8th 2019. Also referred to as the Delhi-Mumbai Industrial Corridor, it is planned as part of the Bharatmala

Read more ...

Bonded Rigid Pavement - A New Edge Concrete Pavement

Bonded Rigid Pavement - A New Edge Concrete Pavement

The exponential growth of the highway infrastructure in the past two decades has increased demand for long-lasting, durable pavements. Rigid pavements are suitable for heavily trafficked areas and are found to be performing satisfactorily with minimum

Read more ...

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

Through its unwavering commitment to road safety, eco-conscious practices, and visionary solutions, the Border Roads Organisation is elevating the standard of road infrastructure development in India. In Arunachal Pradesh, its contributions

Read more ...

Engineering Measures for Pothole Prevention

Engineering Measures for Pothole Prevention

Roads, pavements, and other paved surfaces have depressions in them called potholes which are caused by a variety of conditions. They not only present a serious risk to traffic and pedestrians, but also necessitate expensive repairs by local governments and

Read more ...

Pavement Marking Essential For Road Safety

Pavement Marking Essential For Road Safety

Vivek Singh, Founder, BuildStreet delves into the significance of pavement marking, its objective, and importance, with a focus on Hot Applied Thermoplastic paint - the predominant choice for road markings in India, its technical aspects, application methodology

Read more ...

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

Ghaziabad Aligarh Expressway Private Limited (GAEPL), under the guidance of Cube Highways, has set an example of speedy, safe, and sustainable road construction through research, integration of advanced technology, following best international practices

Read more ...

Indian Companies Delivering Projects Overseas

Indian Companies Delivering Projects Overseas

External affairs minister S. Jaishankar during his visit interacted with the workers and the senior staff, and lauded the role of Indian infra companies, saying that he was “impressed by their enthusiasm”. “Strong economics will complement shared values in taking

Read more ...

NHAI awards 6,003 km of highway projects in FY23

NHAI awards 6,003 km of highway projects in FY23

According to Motilal Oswal Financial Services, the infra project awarding activity picked up and gathered pace in Q4 of FY23, with NHAI awarding total projects of 6,003 km in FY23, much below its FY23 target of 6,500 km. The total value of projects awarded

Read more ...

Is the Indian Road Sector Navigating a Smooth Journey?

Is the Indian Road Sector Navigating a Smooth Journey?

This report covers the current state of the Indian Road Sector, performance of road projects under Hybrid Annuity Model, financial performance of major road developers, and the outlook for FY24. CareEdge Ratings analysed 235 HAM projects awarded between

Read more ...

Balanced Mix Design for Bituminous Mixes

Balanced Mix Design for Bituminous Mixes

As more than 90% of the roads in India have bituminous surfacing, a proper bituminous mix design also assumes significance for better performance of the bituminous roads. India is currently witnessing huge investments by the Indian Government towards

Read more ...

Sustainable Road Construction in Hilly Region

Sustainable Road Construction in Hilly Region

Siksha Swaroopa Kar, Principal Scientist, Amit Kumar, Technical Officer, Krishan, Technician, Flexible Pavement Division, CSIR-CRRI, New Delhi, discuss mechanized laying of cold bituminous layer, the mixer and paver that have been fabricated, and the effectiveness

Read more ...

Implementation of Road Maintenance Management System - Benefits & Technologies

Implementation of Road Maintenance Management System - Benefits & Technologies

The maintenance of road pavements is essential to ensure the safety, reliability, and sustainability of road networks. A road maintenance management system (RMMS) involves effective management of resources to optimize the life cycle of roads, reduce maintenance

Read more ...

Replacement of Steel Reinforcement with  Synthetic Fibre for Concrete Pavement & Floor

Replacement of Steel Reinforcement with Synthetic Fibre for Concrete Pavement & Floor

Manoj Didwania, Adani Total Gas Ltd, Dharamsinh Desai University (DDU-Nadiad), Cept University, presents a paper on the use of Macro Synthetic Reinforcement Fibre (MSRF) as full or partial replacement of Steel Reinforcement for Concrete Pavement

Read more ...

GTI® Reinforced Soil Slope System

GTI® Reinforced Soil Slope System

GTI® is involved in developing environmentally friendly construction products and systems, which are critical for achieving infrastructure growth in a sustainable manner. The company’s GTI® Sloping Fascia Unit and the new system GTI® Reinforced Soil Slopes

Read more ...

CRISIL: Debt to rise for road developers amid strong revenue growth

CRISIL: Debt to rise for road developers amid strong revenue growth

Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.