In its monthly report for October 2026, MoSPI said it was monitoring 1,862 ongoing infrastructure projects across 17 central ministries and departments. Their original estimated cost of Rs 34.82 lakh crore has increased to Rs 38,11,292 crore. The report did not disclose the exact number of projects that exceeded their original cost estimates.
Total expenditure on the projects has reached Rs 17.87 lakh crore, equivalent to 46.88% of their revised estimated cost.
Of the 1,862 projects, 649, or around 35%, have achieved more than 80% physical progress, while 326 projects, accounting for 18%, have crossed 80% financial completion.
The infrastructure pipeline comprises 790 mega projects costing Rs 1,000 crore or more and 1,072 major projects costing less than Rs 1,000 crore.
The Transport and Logistics sector accounts for the largest share, with 1,324 ongoing projects having a combined cost of Rs 20.37 lakh crore.
The Ministry of Road Transport and Highways has the highest number of projects at 972, accounting for 52% of the total. Their combined revised cost stands at Rs 9.55 lakh crore, or 25% of the overall project cost.
The Ministry of Railways is implementing 288 projects with a revised cost of Rs 7.38 lakh crore, while the Ministry of Coal has 121 projects worth Rs 2.22 lakh crore. The Ministry of Petroleum and Natural Gas accounts for 117 projects worth Rs 4.42 lakh crore, and the Ministry of Power has 108 projects valued at Rs 6.55 lakh crore.
The Ministry of Housing and Urban Affairs is implementing 50 projects worth Rs 3.44 lakh crore, while the Department of Water Resources, River Development and Ganga Rejuvenation has 33 projects with a combined cost of Rs 1.93 lakh crore.
The remaining 173 projects, accounting for 9% of the total, have a combined cost of Rs 2.63 lakh crore. These are spread across departments and ministries including Higher Education, Civil Aviation, Steel, Telecommunications, Labour and Employment, Ports, Shipping and Waterways, Health and Family Welfare, Mines, DPIIT and Sports.
The report said projects were at different stages of implementation. Physical progress was higher than financial progress among projects nearing completion, while financial progress was relatively higher during the initial stages, reflecting upfront expenditure during project implementation.