Cabinet Approves Rs 4,288 Crore Second Container Terminal at Kamarajar Port

Container Terminal at Kamarajar Port
The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, has approved the development of a second container terminal at Kamarajar Port Limited (KPL) in Tamil Nadu under the Public Private Partnership (PPP) mode.

The project will be implemented on a Design, Build, Finance, Operate and Transfer (DBFOT) basis at an estimated cost of Rs 4,288.26 crore, including GST. The terminal will have a 900-metre-long berth, a design draft of 18 metres and an annual handling capacity of 2 million Twenty-foot Equivalent Units (TEUs).

The project will be developed in two phases, with Phase I providing capacity of 1.1 million TEUs and Phase II adding 0.9 million TEUs. The PPP investment will be arranged by the selected concessionaire. KPL will separately incur an estimated Rs 450 crore towards dredging.

The terminal is designed to handle container vessels of up to 24,346 TEUs and 400 metres in length. It is expected to improve KPL’s ability to accommodate larger mainline vessels and strengthen connectivity with international shipping routes.

The project aims to meet rising containerised export-import (EXIM) cargo demand from the Chennai–Ennore industrial region and the wider southern hinterland. Key cargo-generating sectors include automobiles and auto components, engineering goods, electronics, chemicals and other manufactured products.

KPL handled 49.08 million tonnes of cargo and 1,008 vessels in FY2025-26, including more than 7 lakh TEUs of container traffic. Its existing container terminal has an installed capacity of 0.8 million TEUs per annum and handled around 0.7 million TEUs during the year, representing approximately 88% utilisation.

India’s container traffic has grown at a compound annual growth rate (CAGR) of around 7% over the past five years, while KPL’s container traffic has grown at approximately 9.9%. The feasibility study projects continued growth in the south-eastern region, supporting the need for additional capacity.

The project will have a 40-year concession period, including a construction period of 48 months. Phase I is scheduled for completion within 24 months from the Date of Award of Concession, with commercial operations expected to begin in the 25th month. Phase II will be developed from the 25th to the 48th month, with full commercial operations commencing in the 49th month.

The concessionaire will be selected through a transparent global bidding process and recover its investment through user charges under the Concession Agreement and applicable tariff framework. The project proposal also provides for obtaining environmental and other necessary clearances before the bid due date.

The additional capacity is expected to strengthen KPL’s role as a container gateway on India’s East Coast, improve maritime logistics efficiency and support EXIM trade. The terminal’s deep draft is expected to facilitate direct calls by larger vessels and reduce dependence on foreign deep-water hub ports and associated feedering costs.

The project is expected to generate around 750 direct and indirect jobs during construction and approximately 800 jobs during the operational phase. It will support industries and manufacturers across Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and the adjoining hinterland.

The project is aligned with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047. No financial implication is envisaged for the Government of India for the PPP component, as the investment will be arranged by the selected concessionaire.

Kamarajar Port, formerly known as Ennore Port, is one of India’s 12 major ports and is wholly owned by Chennai Port Authority under the Ministry of Ports, Shipping and Waterways. During FY2025-26, the port recorded revenue of approximately Rs 1,280 crore and profit before tax of Rs 924 crore. Its cargo has grown at a CAGR of 13.64% over the past five years.