In Saudi Arabia, L&T’s PT&D business has secured orders in the 380 kV transmission and substation segments. The projects are aimed at augmenting transmission capacity and supporting renewable energy evacuation, strengthening the country’s power transmission network and enabling greater integration of renewable energy into the grid.
In the United Arab Emirates, the business has won an order for the construction of 132/11 kV substations along with associated cabling works.
In India, L&T has secured an order from a leading private sector developer to establish a transmission system in Visakhapatnam. The project includes the construction of transmission lines and substations.
Joji Sebastian, Executive Vice President & Head – PT&D, L&T, said, “These order wins demonstrate the breadth of PT&D’s engineering and execution capabilities and the ability to deliver complex power infrastructure solutions across geographies. With the growing demand for grid strengthening, renewable energy integration and associated infrastructure, we are leveraging our technology, project execution expertise and global presence to deliver value for our esteemed clients.”
PT&D is a leading EPC player in the field of power transmission and distribution. It offers integrated solutions and end-to-end services ranging from design, manufacture, supply, installation and commissioning of Transmission Lines, Substations, Underground Cable Networks, Distribution Networks, Power Quality Improvement projects and Infrastructure Electrification projects.