The 3D Monolithic Volumetric Precast

EVOLUTION OF THE CONSTRUCTION INDUSTRY

S. J. Vijay, Chairman, Salmon Leap Associates India

Unlike other industries, the Construction Industry has been stagnant and slow to adopt new technologies and has never undergone a major transformation. As a result, productivity has stagnated over the years, or in some cases, even declined. The image below depicts the evolution of the Construction Industry


3D Monolithic

The construction industry is buoyed by predicted growth and expansion, however, it continues to underperform in four strategic areas: Productivity, Certainty in Delivery, Skills Shortage, and Data Transparency. Poor productivity and project uncertainty can be countered by introducing technology into construction. The right technology would ensure reduction in the project development cycle and reduction in labour.

Construction Industry Globally

Smaller but advanced countries like Singapore as well as larger but thinly populated continents like Australia have been developing and deploying construction technologies and methodologies for decades. These have been tried, tested and proven, and can be the solution to the challenges faced in housing for the billion+ Indians.

Construction of the built environment has continually been adopting “increasing levels of manufacturing” as the solution to address the challenges relating to:
  1. Speed of Construction
  2. Quality of Construction
  3. Reduction in Wastage
  4. Productivity in Construction
  5. Dwindling number of Construction Workers/ Labourers
  6. Health Safety and Environment Issues of Construction
  7. Efficiency of Resources in Construction
The chart below summarizes the decades long path from material-based construction to the current manufacturing of buildings as modules, assembling them into pre-finished transportable Volumetric Modules for installation as Built Environment.

Indian Construction Industry

The surging construction activity in Infrastructure and Buildings coupled with rapidly diminishing labour pool has already pushed the leading players to adopt mechanized and precast methods of construction, be it for bridges or flyovers or metros or even roads, canals, waterlines, airports, seaports et al.

Formwork-based cast-insitu construction while accelerating the speed of building has also increased demand of skilled labour, and safety issues of handling the formwork at increasing height by the multitude of workers.

In July 2017, the Prime Minister of India also directed the use of 3D Technology to speed up housing construction in India. India needs the highest number of houses of possibly at the lowest price point and also in the shortest timeframe.

India has increasingly been adopting different levels of machine-driven construction. The cast-insitu construction using conventional and newer formworks is being replaced by offsite manufacturing / precast of the elements of the built environment as 2D or planar elements. As shown in the diagram above, India by doing this would still be stuck in Stage 3 of the construction evolution.

Stage 3 of construction should be by manufacturing the houses not as components, not as just 2D elements but as modules that deliver a room or more from each precast as 3-Dimensional Monolithic Modular Volumetric Precast. Construction Methods Currently Prevalent in India

Indian construction activity has increasingly been moving away from conventional column, beam, slab-based construction to formwork-based cast insitu shear wall construction during the past decade. The newer types of skills required to efficiently execute the formwork-based construction be it with MIVAN or with ALUFORM or with JUMPFORM or with TUNNEL FORM have all been struggling to cope with the rapidly diminishing quantity of construction workers and more so by the miniscule of fitters and formwork handling workforce.

3D Monolithic

2D Precast

A spurt in Affordable and other Social Housing requirements have led to the developers establishing their own 2D Precast Panel Production facilities as captive plants in Delhi, NCR, Bangalore and a few other cities.

Third Party manufacturers of 2D Precast Panels in the offsite factories are transporting a multitude of panels to building sites and erecting them with equipment and a large number of installation crew in Bangalore, Hyderabad, Vizag, Gurgaon, Mumbai, Pune etc.

Most of these 2D plants are designed and configured to Precast Columns, Beams, Hollow Core or Solid Slabs and Wall Panels as disparate elements in the dimensions of Commercial, Retail and Institutional Buildings as well as Multi Level Car Parking facilities.

However, offsite production of 2D elements, their transportation to building sites, erecting them, aligning them for plum and level, jointing the multiple pieces to secure the targeted strength and shape, and sealing the numerous joints, etc, still pose significant and critical challenges when it comes to building apartments or individual houses. Because of the fragmented nature of manufacturing in the 2D Precast panels, the installation of services like plumbing, electrical wiring, air-conditioning etc. pose additional constraints and are not able to shrink the timelines of construction.

Grinding the misalignments between panels as well as treating the numerous joints between the columns, wall panels, slab panels and beams is also tedious and demands skilled workforce, expensive material like grouts and PU sealants, but still remain vulnerable to leakages and seepages since these are not made as monolithic.

3D Monolithic

3D Monolithic Modular Volumetric Precast

3D Modular Volumetric Precast (Onsite / Offsite) construction is an alternative to this current construction status-quo by promising transformative improvements in Time, Cost, Quality, Health and Safety. And most importantly, it offers predictability.

The 3D Monolithic Volumetric Precast eliminates the problems inherent in 2D Panel-based construction, and employs the least possible number of qualified engineers and trained technicians without leaving the construction to unskilled labour.

3D Monolithic Volumetric construction (also known as modular construction) involves production of three-dimensional modular units in controlled factory conditions prior to transportation to site. Modules can be brought to site either as a basic structure or with all internal and external finishes and services installed, and ready for assembly.

This unique method of construction offers the inherent benefits of concrete such as thermal mass, sound and fire resistance, as well as factory quality and accuracy, together with speed of erection on-site.

The 3D Volumetric Construction offers schedule benefits as most of the activities are undertaken away from the building site with minimal work at the building site. This enables taking some activities off the critical path and bringing certainty in the delivery of the project.

3DMVP Project

Key Advantages of Modular Construction
  • Achieves superior quality through factory-based quality control
  • Standardized design details for modular buildings simplify and reduce need for continued design inputs
  • Reduced site labour: erection and finishing teams that install and complete modular buildings involve less workers on site than conventional buildings or 2D Precast
  • Improved site productivity
  • Reduced wastage during manufacture and on-site installation
  • Greater reliability and quality as it is a monolithic structure with no, or minimal vertical joints
  • Greater certainty of completion on time and on budget
  • Modular construction sites have proved to be significantly safer than conventional construction methods.
3DMVP Process

3DMVP Project

This technology is unlike the conventional and 2D Precast methods and is cast complete with window and door frames, electrical and plumbing conduits already inlaid. A brief write-up of the process is illustrated below:
  • The modules casts five sides in a single pour, or a three- dimensional shape creating a pre-designed shaped room or multiple rooms.
  • The moulds are customizable during the modules’ design process. All openings - doors and windows, access points—piping and conduit and insulation are designed into the mould.
  • Building all the features into the mould’s design reduces project turnaround time and costs.
  • The openings for Windows, doors are so precise that they can be ordered straight from the drawings.
  • The first fix MEP is installed at the time of casting thus reducing the time and labour required for chasing the walls, fixing the conduits and plastering the walls.
  • This method is replicated and the modules are fitted together—side-by-side or atop of each other. This allows the roof of the first module to become the floor of the second module as they are vertically stacked, similar to Lego blocks or bricks. This ability to fit the modules together reduces construction time.
3DMVP Project

India’s first 3DMVP Project

The application of the 3DMVP technology was developed and optimized to meet the demands of Indian Market. In addition, recruitment and training of the Engineers in 3DMVP, its transportation and installation was undertaken. Armed with the above and with the personal presence and guidance of the technology owner from Australia, construction of a Pilot Building for Tata Housing was undertaken with 3DMVP.

A five-storey building with 20 apartments was manufactured and installed in 33 working days.

The images of the Casting, Transportation and Installation of the Tata’s Boisar Project is presented here:

NBM&CW November 2018

Click Here
To Know More / Contact The Manufacturer
Please provide your details we will contact you as soon as possible
Choose Title from the listPlease let us know your name.
Please let us know your Designation.
Invalid Input
Please let us know your email address.
Please let us know your City.
Please let us know your Contact Number.
Please brief your query.
Our other value-added services:

To receive updates through e-mail on Products, Technologies, equipment, please Select the Product Category(s) you are interested in and click Submit. This will help you not only to save time but also to get best quote for right products from many manufacturers of the same category; it helps you to evaluate and negotiate the best price.

Equipment & Machinery
Invalid Input
Building Products
Invalid Input

Challenges in Design & Construction of 4680m Elevated Viaduct at Pilkhuwa – A Case Study

The 4680m long elevated viaduct at Pilkhuwa is a part of package-3 of Delhi-Meerut Expressway Road project. It is passing through a very congested area with 24x7 heavy traffic and market on its both sides. The main challenges Read More ...

Mumbai Metro Line 2A Use of precast construction in urban infrastructure projects

Md. Adil SHAIKH, Mangesh SAWANT & Ajay TANK, Sr. Design Engineers at Spectrum Techno Consultants present the various aspects of planning, design and construction considered for this project keeping in view its complexity Read More ...

Design Intricacies of Precast Concrete Structures for Multi-Storied Residential Towers

With Precast, we can envision a cost-effective, fast-track, safe and sustainable future for the construction of high-rise structures. Nidhi Gupta & Ahilan R. Design and Engineering team, Starworth Infrastructure & Construction Ltd., Bengaluru Read More ...

Echo Precast - Increased automation in production of prestressed hollow core slabs

With a multi-angle saw (MAS) from Echo Precast Engineering, Belgium, the Franconian building materials manufacturer Dennert is focusing on higher automation in the production of prestressed hollow core slabs Read More ...

Ecofriendly Paver Block

In the past few decades, the rapid process of industrialization and urbanization has increased the generation of waste material at huge rates and landfills are filling up faster than the exploration of new sites. Disposal of industrial Read More ...

DECAST Ltd, one of the largest precast companies in Canada, has invested in a self-stressing casting bed from Tecnocom in Italy

Tecnocom specializes in providing molds and casting beds for the precast industry and is a part of the PROGRESS GROUP of companies; which is a leading precast technology conglomerate worldwide. PROGRESS GROUP is represented Read More ...

Rethinking Repaving

As states continue to look at ways to efficiently repair roads, Indiana is testing a new product in an urban environment. Every commuter has experienced it at some point. Cruising along an interstate when you come to a grinding halt Read More ...

Architectural Precast Concrete

Concrete can easily replicate the high-end look of masonry, marble, cut stone and even exotic and sculpted motifs in both beauty and durability and the versatility of architectural precast concrete gives designers a freedom that is not Read More ...

Precast in Residential Construction

Urban population is growing at the rate faster than expected and hence the providing residential units is one of the most important challenges of the developing countries like India. The precast technology is spreading its wing from Read More ...

Aurobindo Realty & Infrastructure chooses Elematic to fast-track projects in Hyderabad

Aurobindo Realty & Infrastructure has adopted precast technology to speed-up construction processes and take advantage of the growth boom in Hyderabad, which is home to about seven million people, and is one of the fastest growing Read More ...

Sansiri invests in sophisticated battery mould technology by Tecnocom

Sansiri Public Co. Ltd, based in Bangkok, Thailand, has more than three decades of experience in the field of construction projects and real estate development and has successfully delivered hundreds of projects all over Thailand. It has gained Read More ...

Enhancing Buildability Using Precast Concrete Technology

Though precast construction is in use for almost 80 years, it continues to be the least understood construction method in developing countries. Only a limited number of countries in North America, Europe, Australia, Japan and some parts Read More ...

Greener, Faster and Sustainable Construction Practices Through Precast Solutions

It is very important for us to have a greener, faster and sustainable approach towards the construction of buildings and infrastructure in order to meet the ever-increasing demands of the construction industry. One such method Read More ...

Precast Segmental Lining for Underground Tunnels

India, which has been lagging behind other countries in metro rail development with the country’s first Metro commissioned in Kolkata in 1984 followed by New Delhi only during 2002, is now catching up with over 585km of operational lines Read More ...

Precast Construction to the Rescue

Precast construction meets the expectation of cost in building structures and has proven to be the most suitable technology for India. It is also the most effective when there is a large volume of construction that requires a balanced Read More ...

Offsite Manufacturing is the Future of Construction

Across the globe, Data Driven Design, Design for Manufacturing and Assembly (DFMA), Modular Construction, Offsite Manufacturing, Intelligent Buildings and Construction Software are gaining prominence as they enable faster construction Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week