The 3D Monolithic Volumetric Precast

EVOLUTION OF THE CONSTRUCTION INDUSTRY

S. J. Vijay, Chairman, Salmon Leap Associates India

Unlike other industries, the Construction Industry has been stagnant and slow to adopt new technologies and has never undergone a major transformation. As a result, productivity has stagnated over the years, or in some cases, even declined. The image below depicts the evolution of the Construction Industry


3D Monolithic

The construction industry is buoyed by predicted growth and expansion, however, it continues to underperform in four strategic areas: Productivity, Certainty in Delivery, Skills Shortage, and Data Transparency. Poor productivity and project uncertainty can be countered by introducing technology into construction. The right technology would ensure reduction in the project development cycle and reduction in labour.

Construction Industry Globally

Smaller but advanced countries like Singapore as well as larger but thinly populated continents like Australia have been developing and deploying construction technologies and methodologies for decades. These have been tried, tested and proven, and can be the solution to the challenges faced in housing for the billion+ Indians.

Construction of the built environment has continually been adopting “increasing levels of manufacturing” as the solution to address the challenges relating to:
  1. Speed of Construction
  2. Quality of Construction
  3. Reduction in Wastage
  4. Productivity in Construction
  5. Dwindling number of Construction Workers/ Labourers
  6. Health Safety and Environment Issues of Construction
  7. Efficiency of Resources in Construction
The chart below summarizes the decades long path from material-based construction to the current manufacturing of buildings as modules, assembling them into pre-finished transportable Volumetric Modules for installation as Built Environment.

Indian Construction Industry

The surging construction activity in Infrastructure and Buildings coupled with rapidly diminishing labour pool has already pushed the leading players to adopt mechanized and precast methods of construction, be it for bridges or flyovers or metros or even roads, canals, waterlines, airports, seaports et al.

Formwork-based cast-insitu construction while accelerating the speed of building has also increased demand of skilled labour, and safety issues of handling the formwork at increasing height by the multitude of workers.

In July 2017, the Prime Minister of India also directed the use of 3D Technology to speed up housing construction in India. India needs the highest number of houses of possibly at the lowest price point and also in the shortest timeframe.

India has increasingly been adopting different levels of machine-driven construction. The cast-insitu construction using conventional and newer formworks is being replaced by offsite manufacturing / precast of the elements of the built environment as 2D or planar elements. As shown in the diagram above, India by doing this would still be stuck in Stage 3 of the construction evolution.

Stage 3 of construction should be by manufacturing the houses not as components, not as just 2D elements but as modules that deliver a room or more from each precast as 3-Dimensional Monolithic Modular Volumetric Precast. Construction Methods Currently Prevalent in India

Indian construction activity has increasingly been moving away from conventional column, beam, slab-based construction to formwork-based cast insitu shear wall construction during the past decade. The newer types of skills required to efficiently execute the formwork-based construction be it with MIVAN or with ALUFORM or with JUMPFORM or with TUNNEL FORM have all been struggling to cope with the rapidly diminishing quantity of construction workers and more so by the miniscule of fitters and formwork handling workforce.

3D Monolithic

2D Precast

A spurt in Affordable and other Social Housing requirements have led to the developers establishing their own 2D Precast Panel Production facilities as captive plants in Delhi, NCR, Bangalore and a few other cities.

Third Party manufacturers of 2D Precast Panels in the offsite factories are transporting a multitude of panels to building sites and erecting them with equipment and a large number of installation crew in Bangalore, Hyderabad, Vizag, Gurgaon, Mumbai, Pune etc.

Most of these 2D plants are designed and configured to Precast Columns, Beams, Hollow Core or Solid Slabs and Wall Panels as disparate elements in the dimensions of Commercial, Retail and Institutional Buildings as well as Multi Level Car Parking facilities.

However, offsite production of 2D elements, their transportation to building sites, erecting them, aligning them for plum and level, jointing the multiple pieces to secure the targeted strength and shape, and sealing the numerous joints, etc, still pose significant and critical challenges when it comes to building apartments or individual houses. Because of the fragmented nature of manufacturing in the 2D Precast panels, the installation of services like plumbing, electrical wiring, air-conditioning etc. pose additional constraints and are not able to shrink the timelines of construction.

Grinding the misalignments between panels as well as treating the numerous joints between the columns, wall panels, slab panels and beams is also tedious and demands skilled workforce, expensive material like grouts and PU sealants, but still remain vulnerable to leakages and seepages since these are not made as monolithic.

3D Monolithic

3D Monolithic Modular Volumetric Precast

3D Modular Volumetric Precast (Onsite / Offsite) construction is an alternative to this current construction status-quo by promising transformative improvements in Time, Cost, Quality, Health and Safety. And most importantly, it offers predictability.

The 3D Monolithic Volumetric Precast eliminates the problems inherent in 2D Panel-based construction, and employs the least possible number of qualified engineers and trained technicians without leaving the construction to unskilled labour.

3D Monolithic Volumetric construction (also known as modular construction) involves production of three-dimensional modular units in controlled factory conditions prior to transportation to site. Modules can be brought to site either as a basic structure or with all internal and external finishes and services installed, and ready for assembly.

This unique method of construction offers the inherent benefits of concrete such as thermal mass, sound and fire resistance, as well as factory quality and accuracy, together with speed of erection on-site.

The 3D Volumetric Construction offers schedule benefits as most of the activities are undertaken away from the building site with minimal work at the building site. This enables taking some activities off the critical path and bringing certainty in the delivery of the project.

3DMVP Project

Key Advantages of Modular Construction
  • Achieves superior quality through factory-based quality control
  • Standardized design details for modular buildings simplify and reduce need for continued design inputs
  • Reduced site labour: erection and finishing teams that install and complete modular buildings involve less workers on site than conventional buildings or 2D Precast
  • Improved site productivity
  • Reduced wastage during manufacture and on-site installation
  • Greater reliability and quality as it is a monolithic structure with no, or minimal vertical joints
  • Greater certainty of completion on time and on budget
  • Modular construction sites have proved to be significantly safer than conventional construction methods.
3DMVP Process

3DMVP Project

This technology is unlike the conventional and 2D Precast methods and is cast complete with window and door frames, electrical and plumbing conduits already inlaid. A brief write-up of the process is illustrated below:
  • The modules casts five sides in a single pour, or a three- dimensional shape creating a pre-designed shaped room or multiple rooms.
  • The moulds are customizable during the modules’ design process. All openings - doors and windows, access points—piping and conduit and insulation are designed into the mould.
  • Building all the features into the mould’s design reduces project turnaround time and costs.
  • The openings for Windows, doors are so precise that they can be ordered straight from the drawings.
  • The first fix MEP is installed at the time of casting thus reducing the time and labour required for chasing the walls, fixing the conduits and plastering the walls.
  • This method is replicated and the modules are fitted together—side-by-side or atop of each other. This allows the roof of the first module to become the floor of the second module as they are vertically stacked, similar to Lego blocks or bricks. This ability to fit the modules together reduces construction time.
3DMVP Project

India’s first 3DMVP Project

The application of the 3DMVP technology was developed and optimized to meet the demands of Indian Market. In addition, recruitment and training of the Engineers in 3DMVP, its transportation and installation was undertaken. Armed with the above and with the personal presence and guidance of the technology owner from Australia, construction of a Pilot Building for Tata Housing was undertaken with 3DMVP.

A five-storey building with 20 apartments was manufactured and installed in 33 working days.

The images of the Casting, Transportation and Installation of the Tata’s Boisar Project is presented here:

NBM&CW November 2018

Click Here
To Know More / Contact The Manufacturer
Please provide your details we will contact you as soon as possible
Please let us know your name.
Invalid Input
Please let us know your Designation.
Invalid Input
Please let us know your City.
Please let us know your State.
Please let us know your Country.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.

A Sight to See - Precast concrete enhances the beauty of the Academy Museum of Motion Pictures

It will soon be one of the most eye-catching structures in the country. The 300,000-square-foot Academy Museum of Motion Pictures, dedicated to the art and science of the film industry, will open in late 2019 in Los Angeles Read More ...

New Elematic Extruder E9

Elematic introduces an all-new flagship model 'the Extruder E9' to their Extruder family for hollow-core slab production. The new machine will offer high casting speed, 2nd generation automatic compaction control and sophisticated Read More ...

Precast Technology Enabling High-rise Construction at Lower Cost

Precast technology has many advantages such as speed, quality and cost over the traditional construction method - the reason why it is particularly suited for high-rise projects, says Petteri Laitinen, Vice President, Projects and Read More ...

Infrastructure Project in Kuwait – Tecnocom moulds form bridge girders at Nawaseeb Road

Infrastructural projects in Kuwait are still the focus of local government-backed investments. In order to improve connectivity, regional and global projects in the infra sector are viewed as a state priority Read More ...

Creating Space with Prefab

The Museum hosts examples of Baroque art ranging from painting, sculpture and fashion to architecture, music, theatre, literature and food. Fluted slabs white concrete with a bush-hammered finish forms the walls, while maintaining Read More ...

Indonesian Property Developer Sets New Construction Standards – New Precast Plant From EBAWE

With more than 1,600 ha. of real property and development potential for the next 12 years, PT Modernland Tbk. is one of the leading Indonesian property developers in Greater Jakarta. For the last three decades, the Read More ...

Elevated Corridors For - Metro & Road Connectivity

India has taken a giant leap in the field of construction over the past 15-20 years. And infrastructure development is feather to the cap. A large number of cities are constructing metro projects. Similarly, an average of Read More ...

Earthquake-Proof Construction

The Pacific Ring of Fire is a volcanic belt which rings the Pacific Ocean on three sides with a length of over 40,000 km. The friction of the tectonic plates makes this region a zone of frequent earthquakes, which, in Read More ...

German's latest Precast Concrete Technology in Indonesia

PT Modernland Realty Tbk, through its subsidiary PT Modern Panel Indonesia, one of the country’s leading material building producers, continues to develop innovative solutions for the development of the Read More ...

Precast Bridge: Banking on Precast

According to the 2017 Bridge Report by the American Road & Transportation Builders Association, more than 185 million vehicles cross nearly 56,000 structurally deficient bridges every day in the U.S. As such, deteriorating Read More ...

Precast Construction - Elematic Helps B. G. Shirke to Execute Mass Projects

It has been the dream of our founder- chairman, Padmashri B.G. Shirke, to industrialize the civil engineering construction in our country by manufacturing standardized precast components for building Read More ...

Precast Construction - Tecnocom of Progress Group supplies mould system for the longest road bridge in Colombia

The figures concerning the "Proyecto Cartagena-Barranquilla y circunvalar de la Prosperidad" are impressive. The new road link on the Caribbean coast in northern Colombia is 146 km long, half of it is designed with two dual Read More ...

Singapore promotes precast concrete elements

Straits Construction Group, one of the largest construction companies in Singapore, recently commissioned a plant for producing not just walls and floor panels, but also pre-stressed solid slabs and 3D kitchen Read More ...

Minimization of heat ingress using insulated Hollow Concrete Block wall in buildings

Heat transfer through concrete block wall into a building is determined and comparison has been made with insulated hollow concrete block. The paper deals with use of different type of thermal insulations Read More ...

Elematic’s great products, reliable service and world reputation persuaded BSBK to switch to precast

One of India’s best known construction company BSBK Group chose Elematic as its key partner for a large-scale government housing project, thanks to the Finnish company’s excellence in precast Read More ...

KEF Infra to Prefabricate KMCH’s New College Hospital in Coimbatore

KEF Infra, leaders of innovative, integrated offsite manufacturing and prefabrication in India, and Kovai Medical Center and Hospital Ltd. (KMCH), Tamil Nadu’s most trusted multi-speciality hospital Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week