Robbins Slurry TBM ramps up for Mumbai Metro Line 3

First of Two Mixed Ground Machines will begin boring this autumn

Robbins Slurry TBM
Officials from Robbins, owner MMRC, contractor Dogus-Soma JV, and consultant Maple, celebrate the successful factory acceptance testing of a Slurry TBM bound for the Mumbai Metro on September 4, 2017.

Robbins Slurry TBM
(From L- R) Mr. DV Raju, Senior VP-SOMA, Mr. Kapil Bhati, MD-Robbins India, and Mr. Tamay Sayin, Project Manager-DSJV mark the occasion of the first Robbins TBM to be sent to India’s Mumbai Metro Line 3 project.
At a Glance

Project Location:
Mumbai, Maharashtra, India
No. of Machines: 2
Machine Type: Slurry TBM
TBM Diameter: 6.65 m (21.8 ft)
Tunnel Length: 2 x 3.5 km (2.2 mi)
Geology: Fresh to weathered basalt and breccia
Project Owner: Mumbai Metro Rail Corporation (MMRC)
Contractor: Dogus-Soma Joint Venture (DSJV)

The first of two Slurry TBMs, a rebuilt 6.65 m (21.8 ft) diameter machine, passed its factory acceptance on September 4, 2017 in Singapore. The machine, fitted with a Robbins cutterhead and outer shields, is destined for the Mumbai Metro Line 3 under contract UGC03 for the Dogus-Soma JV (DSJV), and will begin excavation in late 2017. The factory acceptance for a second 6.65 m (21.8 ft) diameter Slurry TBM will be conducted by the end of 2017.

Mr. DV Raju, Senior VP, SOMA
The on-time delivery of the first machine is just the beginning of a partnership that will span many years. “There are few companies in the international arena that are as professional as Robbins. Robbins has been very helpful to DSJV since the inception of the project, and will be our partners until the end of the contract. Its presence in India, including field service crews, will be a great help for us in the future,” said Mr. DV Raju, Senior VP, SOMA.

The two machines will excavate parallel 3.5 km (2.2 mi) long tunnels between Mumbai Central and Worli station sites, passing through three intermediate cut and cover stations on the way. Ground conditions consist of fresh to weathered basalt and breccia upto 100 MPa UCS with water pressures upto 3 bar.

Mr. Tamay Sayin, Project Manager for DSJV
The JV selected Slurry machines for their contract due to the challenging ground conditions expected. “I have worked with Slurry TBMs on similar geology, globally. Slurry TBMs have real power and will suit the hard rock geology of our Mumbai Metro contract 3. The water table and variable geology, especially basalt of higher hardness, can be easily tackled by Slurry TBMs,” said Mr. Tamay Sayin, Project Manager for DSJV.

The cutterheads of the machines are fitted with wear protection, wear detection bits, and Robbins 17-inch disc cutters for the conditions mentioned above. Grizzly bars will limit the size of boulders that can enter the cutterhead to 250 mm (9.8 in). The slurry systems include rock crushers as well as abrasion-resistant plating in high-wear areas.

Mr. Kapil Bhati, Managing Director, Robbins India
The two TBMs are the first of a total of four machines being provided by Robbins for the Mumbai Metro Line 3. Another two 6.65 m (21.8 ft) diameter Crossover XRE machines will bore parallel 2.8 km (1.7 mi) tunnels on a separate contract in 2018. “Mumbai Metro is one of the most prestigious metro works in the country, and Robbins’ involvement in providing suitable machines and associated services is an honor,” said Mr. Kapil Bhati, Managing Director, Robbins India.

The 33.5 km (20.8 mi) long Line 3 of Mumbai Metro being constructed by the Mumbai Metro Rail Corporation (MMRC) will consist 26 underground stations and one at-grade station that will reduce heavy traffic and rail congestion between Bandra and Churchgate areas of the city. A total of 17 TBMs are being procured to bore various sections of the tunnels, which will be excavated at average depths of 15 to 25 m below the city. The entire line is expected to be operational by 2021.

Robbins Slurry TBM
The Slurry machine is the first of four Robbins TBMs that will be supplied to Mumbai Metro, including two Crossover XRE machines to be supplied to another contract in 2018.
 

NBM&CW October 2017

Click Here
To Know More / Contact The Manufacturer
Please provide your details we will contact you as soon as possible
Please let us know your name.
Invalid Input
Please let us know your Designation.
Invalid Input
Please let us know your City.
Please let us know your State.
Please let us know your Country.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.

Characteristics & Categorization of Tunnel Fires & Their Mitigation

A fire that develops in a tunnel interacts with the ventilation airflow and generates complicated air flow patterns and turbulence in the vicinity. The heat generated warms up the surrounding air, and in case of a slope inside Read More ...

Injection Solutions for Underground Construction

Injection can be defined as the introduction of a material with pressure into the ground or a structure for waterproofing and for consolidating voids, cracks and porosity. Generally, the injection can be categorised as Pre Read More ...

Tunnel Renovation Redefined

During renovation of the Hasselborner Tunnel in Central Hesse, Germany, contractor Baresel used a method they hadn't tried before. Parts of the tunnel lining had to be removed and the areas were subsequently Read More ...

GHH adds Shotcreting Machine to its - Tunneling Equipment Solutions

GHH is offering state-of-the-art and proven IS26 Concrete Spraying (Shotcrete) machine in India. The machine is suitable for shotcreting application in medium and large sized tunnels with cross sections ranging Read More ...

Kishanganga Hydro Power project – A New Power House

Inaugurated by the Prime Minister of India, the Kishanganga Hydro Electric Power project is the first mega hydro power plant to be awarded as EPC to HCC by NHPC. Located at Bandipore in north Kashmir, the Read More ...

Tunneling to Prosperity: Solutions, Equipment and Technologies

India is one of the fastest growing markets for tunnel construction due to various infrastructure development projects underway across the country. Tunnels are required for hydroelectric power projects, for improving road Read More ...

CREG: Tunneling Specialist

China-based China Railway Engineering Equipment Group Co., Ltd (CREG) is a subsidiary of the public- listed China Railway Engineering Corporation (CREC), a Fortune 500 company and a key state-owned company under Read More ...

Intermodality & Last Mile Connectivity - Creating Smart Walkable Spaces

Urban congestion needs to be addressed by encouraging high quality and innovative energy-efficient public transport integrating it with other forms of paratransit, ensuring last mile connectivity; working on Read More ...

Ashram Metro Station - An Engineering Masterpiece

One of the main challenges of constructing a station in the Delhi Metro Network, especially in a busy and densely populated area, is designing it according to the ambience and the limited space allocated. Constructing Read More ...

Transit Oriented Development - Challenges and Proposed Regulatory Framework

Transit Oriented Development (TOD) complements the concept of new urbanism. Compact, mixed-use communities are the answer to suburban problems. Due to the dynamic nature and multiplicity of underlying Read More ...

Simulating oversize and heavy vehicle manoeuvres using AutoTURN® from Transoft Solutions.

Use AutoTURN® to design infrastructure adjustments to safely operate trucks transporting wind turbine components. By Er. Alessio Gori - collaborator at POLITECNICA INGEGNERIA ED ARCHITETTURA SOC. COOP. Read More ...

Urgent Course Correction Imperative for Indian Railways

Railways’ freight and passenger businesses over the 5-year period, i.e., 2014-15 to 2018-19 (budgeted) indicate a flat growth. The number of total passenger journeys would record a CAGR of 0.22%, passenger kilometres Read More ...

Meeting Emerging Urban Transport Challenges

The Ministry of Housing and Urban Affairs has envisaged growth of urban transport along with a low carbon footprint through seamless implementation of a New Metro Rail Policy, announced last year Read More ...

Tunnelling Through the Ages

History has seen the evolution of tunnelling starting with cave formation, for water management, underground transportation, mineral extraction and for warfare purposes. The oldest reference of a tunnel was Read More ...

Afcons uses Robbins EPB TBM to Complete Third Bore for Chennai Metro Project

Contractor Afcons Infrastructure Ltd used a 6.65 m (21.8 ft) diameter Robbins EPB TBM to bore through in Chennai Metro, making it the contractor's third tunnel to be bored by the machine for the project. The three Read More ...

Tunnelling Technologies & product support keep pace with construction complexities

Advanced technologies, mechani- sation of equipment with heightened safety features, and timely service and technical support to end-users can help the construction industry deal with construction complexities Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week