Waterproofing of Sanjay Lake Laxmi Bai Nagar, New Delhi.

    M M Gupta, Director, JBM Engineers Pvt. ltd., H P Singh, S.E., NDMC

    Sanjay Lake was constructed 30 years ago and was main attraction of the residents of this area. Structurally, It consist of two circular pools at the two ends connected with rectangular cross section channel running from East to West, East having average depth of four feet. Wall is of brick masonary and Floor is of Cement Concrete. Water for Lake is underground water supplied from Pump house. Due to heavy leakage from this lake, the use of this lake was discontinued several times since its construction. All the efforts to stop leakage failed as the water used to drain of leaving the lake dry. The kota stone flooring over the cement concrete was done but to no avail. The higher authority of NDMC directed for technical investigation of lake and to suggest suitable measures for its gainful public utilization either lake or otherwise.

    Observation

    After the construction, its use was stopped due to abnormal loss of water on account of leakage and seepage. Despite all the remedial measures taken for retention of water, the level of water fell down very rapidly and in no time lake ran dry. To revive the lake, several treatment were carried out time to time, but no documents/ time to time efforts were complied collectively. Therefore, field investigation was the only course of action to find out the existing data and the following structural details were noticed from trial pit:

    Sanjay Park Lake

    Finding of visual examination and field investigation of the water body:
    • No expansion joints and construction joints in the concrete floor were found.
    • At number of places long cracks were visible.
    • The brick walls were painted with enamel paint after the Cement Plaster.
    • Cracks of size > 5mm present all over the bed floor longitudinally and transversely.
    • More than 5mm wide gap (about 1 metre to 2.5m) long at the joint of wall and bed were found at several locations.
    • Honey combing and damaged concrete floor were noticed.
    • Compacted earth base in the bottom.
    • 150 mm thick lean concrete over base.
    • 25mm thick cement mortar for fixing 20mm thick Kota stone over PCC.
    • 100 mm Cement Concrete (1:2:4) over Kota stone flooring.

    Proposal Considerations

    Waterproofing of Sanjay Lake
    After the study of field observations and discussions by the NDMC with the experts, consensus arrived that before applying the waterproofing impermeable layer on the wall and bed of the lake and the joint of wall and floor need to be structurally strengthened for avoiding leakage of the water.

    Reconstruction of lake with water-proofed RCC wall & proper joint with bed was a costly option and NDMC authorities were not inclined to accept such proposal, since earlier piece meals efforts had not yielded satisfactory results.

    Other option was to make the joint of wall and bed structurally strong enough and repairing of damaged portion of the concrete floor and injecting the cementious grounting polymer modified slurry to make concrete bed compact. The wide cracks has to be repaired and filled with flexible material. All micro and macro cracks should be strengthened by the polymer modified cementitious slurry with glass fiber mat, since water depth was not more than 4 ft.

    Crack Repair

    It was a big challenge to repair and to provide an appropriate waterproofing system which should not only be cost effective but long lasting also, so that lake can be revamped as an water body and for other social uses/ occasion.

    Crack Repair:
    Reasons of cracks were debated. Once it became evident that cracks developed due to unusual expansion and contraction of the structure on account of thermal variation, the choice of Polyurethane as a filling and sealing material for cracks was considered inescapable.

    Strengthening of Concrete Floor:
    For the portion of honey combing, damaged concrete floor etc., it was necessary to provide additional strengthening of joints of walls and floor and Honey combing in floor by grouting and injecting cementitious polymer material. Ferrocement for joints and wall was selected for structurally strengthening the wall and floor.

    Water-proofing of Water Body:
    Provision of suitable waterproofing system on both wall and floor of the lake was considered critical and incorporation of following features in the chosen waterproofing system became inevitable:
    • Environment friendly.
    • Abrasion and impact resistant.
    • Flexible to absorb expansion/contraction due to temperature variations
    • Long life and cost effective, Defect free with a guarantee of at least 10 years
    • Water resistant and non- reactive.
    After considering the above, following modus-operandi for repair and waterproofing of the lake was considered as under:
    • Cracks wider than 5 mm be further widened and filled/sealed using flexible material.
    • Macro/micro cracks to be covered by PMCC (Polymer modified cementitious Coating over sand witched glass mat.
    • Weak concrete floor to be strengthened by injecting polymer grout at pressure.
    • The joint of wall and floor to be provided with Ferro cement before water-proofing Treatment flexible.
    • Poly urethane based flexible and impermeable water-proofing system over the walls and floor as per section below:-
    Based on above guide lines following specifications for providing strengthening and water-proofing treatment on walls and floor of the lake were finalized and executed:-

    Strengthening Of Concrete Floor

    1. Repair to joints on floor by cutting V grooves using poly-crete R and cement mix in the ratio of 1:2.
    2. Two coats of PMCC using polycrete R or equivalent @ 0.25 kg per square metre and cement @ 0.50 kg per square meter per coat with embedment of glass mat.
    3. Two coats of polyurethane screed of polyeuro -1050 (I) by mixing part A, part B and part C (fine additive aggregate) in the ratio of 1:2:2 respectively.
    4. Top coat of neat polyurethane polyeuro 1050 1 admixed with colour pigment.
    5. Ferrocement strengthening screed comprising of layers of hot galvanized 22 gauge or woven wire mesh with 12 mm size mesh openings stretched and fixed to substrate with 100 mm over laps in both directions at a clear spacing of 4 mm and also maintaining a clear bottom cover of 4mm complete with plasticizer and polymeric sealant admixed in appropriate ratio.

      The ferrocement layer was vibrated using a special type of vibrator (orbital type)
    Execution and Completion of Work:
    The above work was executed by M/s JBM Engineer Pvt. Ltd. successfully in the year 2006 under the team of Shri H.P. Singh, Superintending Engineer (Civil) the then Executive Engineer (Civil) and consultant Sh. P.C. Sharma, Retd Head M.S. SERC Ghaziabad. After water testing for evaluation of lake, the same was opened to public and still working satisfactorily even after 8 years.

    Synopsis of the Work

    Client:- New Delhi Municipal Council, New Delhi.
    Agency:- M/s JBM Engineers Pvt. Ltd. Janak Puri, N. Delhi
    Date of Start:- 30.06.2006
    Date of Completion:- 04.12.2006
    Amount:- Rs. 48.00 Lacs
    Total area executed for water proofing:- 3837 M²

    The special gratitude to complete the above work was to Chairperson, NDMC and Chief Engineer (Civil) without their help and continuous guidance, the work would have not been completed.

    NBMCW April 2014

    CURRENTLY ONLINE
    We have 658 guests and no members online

    NBM&CW

    New Building Material & Construction World

    New Building Material & Construction World
    MGS Architecture

    Modern Green Structures & Architecture

    Modern Green Structures & Architecture
    L&ST

    Lifting & Specialized Transport

    Lifting & Specialized Transport
    II&TW

    Indian Infrastructure & Tenders Week

    Indian Infrastructure & Tenders Week