Basement Waterproofing

Project Details
Project : BVR Mall
Client : PVP Square
Consultant : Design Tree Service Consultants Pvt Ltd
Location : Vijayawada, AP
Solution for basement waterproofing : Fosroc Chemicals (I) Pvt ltd

Key Challenges at project site

Basement Waterproofing
BS Nagaraj
Project is designed for 3 basements approximately -12mt. Below ground level, water table is very high which demanded installation of 4 Pumps of 62 hp and 16 bore wells dewatering at the rate of 400lit/minute. Rainy season posed its own problem aggravating the site condition for project execution.
  • City is located in the costal belt and prone to cyclone attacks and the nightmare came true when cyclone "Thane" hit the city in December 2011.

  • Sandy soil substrate poses threat of differential settlement of raft foundation, and also possibility of collapse of benching done for basement excavation.

  • Retaining wall flushed with the secant piling posing unique challenge for installation of waterproofing system in the absence of working space.
Basement Waterproofing

Challenges for the selection of suitable waterproofing system

Consultants M/s Design Tree Service Consultants Pvt Ltd and the clients BVR Mall were keen on waterproofing solution which can address effectively the basement waterproofing requirements of the project.
  • They were looking for a right solution which can address the following issues:

  • Dewatering: Dewatering system shall be in place and continuous till they complete the raft concreting which demands for installation of perforated pipes and pressure relief valves which could be taken across through the membrane.

  • Easy cleaning: During power failure, rains & cyclones lot of slush can deposit on the waterproofing membrane, collapse of benching can deposit sand on the membrane.

  • Differential settlement: Sandy soil substrate can lead to differential settlement of the foundation below raft.

  • Time and cost Saving: Protection screed on the Waterproofing membrane and re-profiling of secant piles surface using shotcreting should not be mandatory since this activity demands additional time and cost.

  • Easy and rapid Installation of waterproofing system: Waterproofing should be a parallel activity and go along with concreting rather than an independent activity for saving time.

  • Positive side waterproofing: Waterproofing for retaining wall shall be installed from positive side in the absence of working space.
Basement Waterproofing

Fosroc Innovative & Engineered Solutions: Proofex Engage system

After detail discussions and study of project requirement, Fosroc was rock solid confident of providing right solutions to this basement waterproofing.
  • Fosroc key success was routed by addressing solution to the issues as below.

Grade Slab

Fully bonded system with mechanical bond to poured concrete with non-tracking property, unique mesh provides water tightness for every square mm of concrete, membrane stay in place in case of differential settlement of raft foundation.
  • Thickness of the membrane is minimum 4mm, enabled direct placing of re-bars on the membrane without protection screed saving time and cost of protection screed.

  • Easy and rapid installation of the membrane just by unrolling the membrane of 1.27mt X 30mt and overlapping using selvedge inbuilt with the membrane, waterproofing goes along with concreting.

  • Pre-applied system enabled installation with minimum surface preparation even on wet condition.

  • Mechanical bond, no limitation like difficulty or improper removing release film from membrane which affects chemical bond with concrete and possibility of bond failure due to dust, sand and slush due to rains or flooding. Sand and slush shall be cleaned using air and water jet.

  • Simple and effective joint detailing for pressure releasing valves piercing through the membrane made easy using standard accessories.
Basement Waterproofing

Retaining wall

In absence of working space, membrane fixed to the sacrificial shuttering provided on the secant pile for achieving positive side waterproofing, eliminated the demand for re-profiling of secant piles with shortcreting, reused ply was used for re-profiling of the secant piles.

Basement Waterproofing

NBMCW February 2012

Click Here
To Know More / Contact The Manufacturer
Please provide your details we will contact you as soon as possible
Please let us know your name.
Invalid Input
Please let us know your Designation.
Invalid Input
Please let us know your City.
Please let us know your State.
Please let us know your Country.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.

Simulating oversize and heavy vehicle manoeuvres using AutoTURN® from Transoft Solutions

Narrow mountain roads, steep hills and challenging ‘S’ curves are just part of the landscape in the ‘toe’ of Southern Italy, where wind farms are becoming a common part of the countryside. With green technology like wind Read More ...

Atlas Copco XA316 and XAT266 portable air compressors for Mumbai underground metro line

Atlas Copco portable air compressors have been deployed for the first underground metro line in Mumbai, and they are not just under the supervision of Mumbai Metro Rail Corporation Limited (MMRCL) but also under Read More ...

Indira Paryavaran Bhawan - First On-site Zero Net Energy Building of India

A zero-energy or a net zero building is a building with zero net energy consumption from outside source, which means that the total amount of energy used by the building on an annual basis is almost equal to Read More ...

Making of a Green Data Centre

Data centres make up 3% of global energy consumption. The main reason behind data centres being major energy guzzlers is the IT processing power, which has increased substantially to meet the growing Read More ...

Apollo ValueTec Plant Gives Competitive Edge to Rana Builders

Dhaka-based Rana Builders (Pvt.) Ltd. specialises in construction of roads, bridges and buildings. When purchasing a new asphalt-mixing plant, it wanted a product that would help meet its objective of on-time delivery Read More ...

BHAI concrete batch mix plant working at Asia’s largest waste-water treatment plant

Delhi Jal Board is setting up a 318 MLD (70 MGD) wastewater treatment plant at GT Karnal Road on the outskirts of Delhi. The ₹414.78 crore project, said to be the largest in Asia, is being constructed by EPC contractor-Larsen & Toubro Read More ...

The Fast Lane to Growth

When the National Highways Authority of India (NHAI) last widened the Vijayawada-Chilakaluripet Highway in the early 2000s, the country was at the beginning of its exponential economic growth. Since then, the nation’s GDP Read More ...

Insitu Investigation of Cinder Mound For Building Construction - A Case Study

Cinder is a waste generated as coal residues from the blast furnace of thermal power plant. It was accumulated over a long periods near railway station, Jamshedpur, Jharkhand, India. This dumping Read More ...

SoilTech Mk. III - 3rd Generation nano-polymer stabilization

Golfshire is a super-premium residential project in Bangalore, comprising luxury villas, a 18-hole PGA standard golf course, a large convention centre with seating capacity of 5000, and a 5-star hotel. The project is Read More ...

Especially Designed Rope Suspended Platform for Dam & Silo Projects

New Age Construction Equipment Engineering Company is one of the leading manufacturers of construction equipment like Rope Suspended Working Platforms (Gondolas/ Cradles), Bar Bending Machines Read More ...

New Age Offers Customized Solutions with Higher Productivity & Safety

As a leading manufacturer of construction equipment, we believe in superior performance, higher productivity & safety, faster execution and timely completion of projects,” says Mr. Jayesh Vadukiya Read More ...

Rehabilitation of National Highway at Tripura-Assam

The National Highway NH-44 is a major road artery for the North-East. The stretch of this highway leading to the border of Assam and Tripura (two states in the north-east of India), is the only land-link between Read More ...

Wirtgen Milling & Recycling Machines give Excellent result at NH-2

Wirtgen most compact and versatile machines W2000 and WR240 have been used for milling and cold in situ recycling works by contractor Soma during the road rehabiliation of Varansi-Aurangabad section Read More ...

KYB-Conmat's Advanced Mechanization Parallel Lower Ganga Canal Lining Project

Tougher norms for quality & safety in the industry have pushed contractors & developers towards advanced mechanization for their projects to deliver quality results in set timelines. It has also Read More ...

3D Design Software Helps Engineers Prove Their Clients’ New “Home” is Ready for Work

Transoft VLMK
Whether it’s moving across town or across the country, there are always boxes to pack and trucks to fill. But what if the core of your business IS trucks and you didn’t have a choice about moving? That’s exactly Read More ...

Comparative Study of Basalt And Carbon FRP Bonded Steel Beams and its Finite Element Modelling

Finite Element Modelling
The use of Fibre Reinforced Polymer (FRP) sheets to strengthen the steel structures has become an attractive option which may ensure confident retrofitting of existing steel structures. Conventional strengthening Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week