Successful from + 40° to - 40°

Sandvik underground drilling rigs used for the Chutak Hydroelectric Project

Two Sandvik underground drilling rigs are being used to cut the tunnels for the Chutak Hydroelectric Project, underconstruction in the trans-Himalayan mountain ranges of Jammu & Kashmir’s Kargil district in India. The project on Suru River, a tributary of Indus, is being undertaken by the National Hydroelectric Power (NHPC) and has been contracted to the Hindustan Construction Company (HCC) Limited. HCC is using two Sandvik Axera* jumbos in the project that are equipped with Sandvik HLX 5 Rock Drill. The project after completion will provide 44 MW (11 x 4) of electricity to the Kargil district. It is being built at a cost of $80 Million.

Overview of Project

The tunneling work involves cutting a 4.8 km long headrace tunnel (HRT) of 5.9m diameter (horseshoe), a 19m diameter and 59 m deep underground surge shaft, a 50m long tailrace tunnel with a diameter of 5.9m (horseshoe), a vertical pressure shaft of 2 x 4m diameter and 37m deep bifurcating into four 2.3m diameter penstocks, two intake tunnels of 4.5m diameter (horseshoe), and three D shape Adits of 6m diameter each. While Adit 1 is 86.62m long, Adit 2 is 240.28m long and Adit 3 is 292.03m long. The underground powerhouse cavern will be 83m long, 15.5m wide and 34.5m high while an underground transformer cavern will be 67m long, 12m wide and 10m high. The barrage is 47.5m length & 15m high above crest level. The rock being encountered in the Chutak project is mainly quartzite.

Difficult Terrain

The mountains in the Kargil region provide a tough challenge for such a hydroelectric project. The biggest challenge is the climate of the location which is a cold desert. The temperature at the project site — at an elevation of 2710m above the mean sea level (MSL)–varies from a high 42 degree Celsius in Peak summer to as low as 40 degrees Celsius below the freezing point in winter. This creates extreme conditions for both the man and the machine. Persons working at the site are found to be troubled by problems like high blood pressure and rapid heart beat and chest pain. The conditions get more difficult during the winter months. The machines too find it difficult to maintain a high level of efficiency under the freezing temperatures. Water lines and air lines freeze during the extreme cold conditions. These machines supplied have special heating systems for hydraulic, diesel and air flushing system for extremely low temperature. However, air flushing system does not solve this problem when the temperature dips to (-) 25 degree Celsius and the air tends to condense and the moisture freezes inside the water line. Also to prevent the fuel from freezing at this temperature, ATF is mixed with diesel in the proportion of 80:20.

Moreover, the site is cut-off by road from the rest of the country for almost six months during the year as the high passes are snowbound from November/December to May/ June. In winter, the only way to reach the site is by flying to Leh and travelling 235 km by road via the 13,780-feet high Fotula (la means mountain pass) to the site location. This demands adequate storage of food, spares, store material and fuel for approximately 6 months during winter. Another unique problem was faced when it was time to take the machines to the site at the beginning of the project. It was found that complete rigs could not be delivered as there was a transportation restriction. The Axera rig weighs 29 tonnes while nothing above 8 tonnes is allowed to be transported in this region due to difficult accessibility and restriction due to capacity of bridges in this region. So the rigs were taken apart completely leaving only the chassis, one in Mumbai and other in Jammu, and then delivered part by part to the site. They were then assembled by the Sandvik engineers on site in six days. Despite such obstacles, the work has continued without a break since its inception in September 2007.

High on Performance

The HCC is using two Axera 8 jumbos equipped with two drilling booms and one basket boom each, and utilising high-power HLX 5 hydraulic rock drills. The efficiency of the Sandvik jumbo is vouched for by HCC’s project manager Manmeet Singh. “The main advantage of Sandvik is its feed system as it has high reliability,” he said adding, “it also scores well as the water consumption is less compared to the other manufacturers, this is of great advantage in winters as less water is available due to ice everywhere.” Mr Singh said that the new drifter has resulted in less number of breakdowns. Saying that Sandvik is very handy in the difficult terrain and quite successfully coping with the extreme temperatures, Mr Singh added that he trusted the Sandvik as it provided him with the “assurance that it will go and complete the assigned work in the limited time that is available for it.” Sandvik’s reliability has also impressed the machine operator. “It is very easy working with the Sandvik and I do not feel tired as I used to be earlier,” he said. “I can see the drilling booms from the operating cabin itself and can adjust their required positions without getting off,” he said. Mr Manmeet Singh said that they are running to a 50-month schedule and their contract is due for completion in November 2010. “We are working well ahead of schedule and are aiming at finishing the project by 10 months in advance,” he said. Sandvik has deputed one engineer on site to take care of the two machines round the clock, achieving 95 percent machine performance that is extremely high under such difficult conditions. “We are drilling 90 to 100 holes of 45 mm diameter and 4,000mm per cycle, using V-cut drilling pattern,” said Sandvik’s on-site engineer Anshuman Verma. Tunnelling work is being assessed in excavation cycles with drilling, blasting, excavating and supporting constituting one cycle. Working on a 24-hour basis, the tunnelling is progressing at the rate of approximately three cycles every two days on average, with an average 3250–3500 mm advance being achieved per cycle. As far as rock bolting is concerned, the machines have been drilling holes ranging from 3m to 12m with diameters ranging from 45mm to 105mm. They were done using Sandvik R32 64mm string.

Sandvik underground drilling rigs used for the Chutak Hydroelectric Project

NBMCW January 2009

Cranes in Full Force at - India's Major Road Project

The 135-km, 11,000 crores Eastern Peripheral Expressway-2 which was inaugurated recently by the Prime Minister, connects towns of UP and Haryana and act as an outer ring road for the capital. It is the country's Read More ...

Sany cranes deployed at Suzlon India's wind power project

Project developers are deploying new cranes and advanced transportation to enable faster and safer completion of their projects. Suzlon India's wind power project at Agar in Madhya Pradesh, is one such site Read More ...

Kochi Refinery Expansion

Kochi Refinery Project
The rapid progress of the second phase of Bharat Petroleum Corporation Limited's (BPCZ), Kochi refinery expansion is being backed by high standards of project management. Efficient planning Read More ...

Bhuj Plant –Another milestone in BKT history

BKT Bhuj Plant
Balkrishna Industries Limited (BKT), a leading manufacturer of Off-highway tires, has recently organized a press visit to its New Bhuj Plants - The Game Changer, which few years ago, was a barren desert with no water Read More ...

Demag All Terrain at Delhi Metro’s Critical Heavy Lift Task

Demag All Terrain Cranes
Delhi Metro Railway Corporation (DMRC) is undertaking a major construction of underground corridors and stations between Bhikaji Cama Place and Sarojini Nagar. The project, which is Read More ...

Casagrande XP Series Piling Rigs and TFC Cranes Work For Coal Berth Project at Vizag Port

Casagrande XP Series Piling Rigs
Casagrande piling rigs are working to set up a 7.36 million tons coal berth at Vizag Port. The berth which is instrumental towards adding the port capacity will handle imported thermal and coking coal for power and Read More ...

Teesta-III Hydro Power Project Mix Design and Application of HPC

Teesta Hydro Power Project
The Teesta-IIII hydroelectric project (1200MW) is a run of the river scheme located on Teesta River in the North District of state of Sikkim. The project comprises of 60m high concrete face Rock Fill dam (CFRD), with the two bays of chute Spillway on the Left Bank Read More ...

IOCL Paradip Refinery: An Engineering Marvel

IOCL Paradip Refinery
The fundamental approach in planning and designing an industrial project is to make it commercially viable across its lifecycle. The larger the capital investment is involved, the commensurate approach is to optimize and to control Read More ...

Tandem Girders Lifting by Express Equipment

Gujarat based crane rental major, Express Equipment Rental & Logistics Pvt. Ltd (EERL) has recently undertaken tandem lifting and shifting of precast concrete girders for flyover project on National Highway Read More ...

Engineering, planning, construction of Kochi & Dahej LNG Terminal

Setting up new generation liquefied natural gas terminals has its own set of engineering challenges as they continue to persist even post commissioning of the terminals. This has been evident with India's newly Read More ...

GIFT City

Artistically designed to serve as a paradigm for a classic city in terms of quality of life, infrastructure, ambience and also to be at or above par with globally benchmarked financial centers such as Shinjuku, Tokyo, Lujiazui, Shanghai Read More ...

Niagara Tunnel: An Engineering Marvel with No Parallels

Muscling its way through the rugged terrains of Niagara River, the Niagara Tunnel is now gushing in 500 cubic metres of water per second to the Sir Adam Beck Generating Station in Ontario, Canada. As high as a four storey building, the Read More ...

Bangalore International Airport Expansion Shaping Up

The expansion of Bangalore International Airport mainly involves the integration of existing structure with the upcoming one P. P. Basistha visited the site to take a stock of the activities being put to shape up Read More ...

Marina Bay Sands Singapore’s Architectural Icons

Marina Bay Sands is a 929,000 square meter (10 million square-feet), high-density and mixed-use integrated resort complex that brings together a 2,560-room hotel, a 120,000 square meter (1,292,000 square feet) Read More ...

SBH Shoring System for MBMC Sewerage Project

The Mira-Bhayandar Municipal Corporation (MBMC) awarded a contract to SPML Infra Ltd for underground sewerage in Mira-Bhayandar city in Thane, Maharashtra under JNNURM Read More ...

Kochi LNG Terminal: A Mega Project in the Making

Located along the shore of Arabian Sea and surrounded by lush greenery, Puthuvypeen SEZ in Kochi is a truly visual treat for visitors. But more so, it is the buzzing activity of construction workers and large number of Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week