Power Plant Construction

Power Plant Construction Holistic Measures to Counteract Quality Deviations in Components

Hans Christian Schröder, Power Station Sector Manager at TÜV SÜD Industrie Service Moscow

Practical experiences show increasing quality deviations in delivered power plant components. Especially for components for the new generation of power plants with steam temperatures of up to 700 degrees, old integrity checks are to be complemented by holistic system considerations.

Power Plant Construction Holistic Measures to Counteract Quality Deviations in Components
Globalised, deregulated markets increased competitive and cost pressure in power plant construction. Despite the increasing technical requirements on components, in regards to their resistance to increasing operating pressures and temperatures, they are expected to be as cheap as possible. Many contracts are awarded abroad under special conditions. The manufacturers of components are not always able to meet the requirements agreed upon. Quality deviations in delivered components such as boilers, turbines and generators often occur. In order to maintain a high level of safety for thermal power plants, the tester has to go from being purely an inspector to being an all-out operations analyst.

Systemic Approach

Modern power plants are subject to higher operational stress and have lower operating reserves. For power plant construction, the components' integrity is tested and periodically reviewed by the manufacturer on the basis of the existing rules and standards. However, the components will function reliably in later plant operation, only when the quality requirements are aligned with the specific conditions of the future plant operation in advance. In some cases, we also take warranty or guarantee measurements. Important points to be taken into consideration in addition to the process and plant design are the structural design and future operational stress. How is the power plant operated? What strategies are provided for its maintenance and repair?

Components for 700-degree power plants

Power Plant Construction Holistic Measures to Counteract Quality Deviations in Components
With increased operating temperatures, coal plants are expected to continue to attain higher efficiencies of over 50%. In order to drive up the required temperatures of up to 700 degrees, new high temperature material concepts are needed. The use of, for example, nickel-alloyed steels places special demands on the manufacturing, construction, further processing and testing of components. At temperatures above 6000C, the material changes are more difficult to recognize and can only be detected using advanced testing methods. In addition, for example, the service life of welds and basic materials is shortened. So far, there are still no reliable creep strain measurements for new materials and components over a longer period of operation.

Testing of High-temperature components

Special test runs are to provide information on the behaviour of high-temperature materials and components in operation. In this regard, the large-scale power plant in Germany started a research and development project in 2008, during which the operational integrity of components at 725 degrees are to be tested. The first results are expected in the coming years. But it is certain now that the new materials and components are much more sensitive to additional loads during operation. During the test run, the specific quality requirements for the components will be accurately designated.

New Testing Requirements

For the testing of high-temperature power plant components, various influencing factors must be determined: the resistance of the new materials, the applied manufacturing and processing methods (welding) as well as the operational load. Because of the special material properties, the application of conventional testing methods such as ambulatory Metallography (for example fabric prints) should be limited. A holistic testing concept is oriented on the factors influencing the service life of a component and ensures that it is not determined according to the tolerance level specified in the component's design. The actual testing activity no longer serves to detect defects. Rather, the plausibility of the overall design is evaluated in the context of operational stress and determination of the remaining service life.

Hitherto traditional testing according to current regulatory requirements is ad hoc and reflects only the current state of a power plant. A forecast of the long-term behaviour of systems and their components is in this way virtually impossible. In a prognostic activity, however, lies the key to minimising costs by more accurate data on the actual condition of components. From this, the remaining service life can be derived. The „gAte4optimisation" concept of TÜV SÜD make such a forecast possible based on an integral consideration of components, and appropriate non-destructive testing methods such an advanced eddy current testing, ultrasound testing with ultra modern equipment such as phased array or a simplified procedure for measuring local creep strain (TCR – TÜV-Creep-Replica).

Risk Oriented Implementation

Power Plant Construction Holistic Measures to Counteract Quality Deviations in Components
For economic reasons, the quality requirements of individual components can be matched to their safety relevance in the overall system; without having to sacrifice security. Based on national and international standards and regulations well-thought-out power plant concepts can also cut costs of related components. To this end, planners should clarify with operators in advance what specific product quality is actually required for the respective components. The second step is to assess, which suppliers can fulfill the defined quality requirements.

Certification is not in Itself a Guarantee

Certification of companies, for example with DIN EN ISO 9001, provides no guarantee for the contractually agreed quality of their products. For example, the DIN EN ISO 9000 does not certify the product quality, but primarily the organizational processes of a company. For the quality management of power plant components, it is critical how quality requirements, cost efficiency, system availability and risks of downtime are conciliated in the future and in the long-term.

Conclusion

Quality deviations in components require holistic solution strategies to enable a high level of operational integrity. The integrated approach also allows a risk oriented implementation of the component requirements, which cuts costs. To assess the quality of components exactly, the component design, manufacturing technologies, and planned maintenance strategies as well as the operation mode of the power plant and operational load have to all be incorporated. This is particularly true for components that are exposed to elevated operating parameters.

NBMCW July 2010

Click Here
To Know More / Contact The Manufacturer
Please provide your details we will contact you as soon as possible
Please let us know your name.
Invalid Input
Please let us know your Designation.
Invalid Input
Please let us know your City.
Please let us know your State.
Please let us know your Country.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.

Cranes in Full Force at - India's Major Road Project

The 135-km, 11,000 crores Eastern Peripheral Expressway-2 which was inaugurated recently by the Prime Minister, connects towns of UP and Haryana and act as an outer ring road for the capital. It is the country's Read More ...

Sany cranes deployed at Suzlon India's wind power project

Project developers are deploying new cranes and advanced transportation to enable faster and safer completion of their projects. Suzlon India's wind power project at Agar in Madhya Pradesh, is one such site Read More ...

Kochi Refinery Expansion

Kochi Refinery Project
The rapid progress of the second phase of Bharat Petroleum Corporation Limited's (BPCZ), Kochi refinery expansion is being backed by high standards of project management. Efficient planning Read More ...

Bhuj Plant –Another milestone in BKT history

BKT Bhuj Plant
Balkrishna Industries Limited (BKT), a leading manufacturer of Off-highway tires, has recently organized a press visit to its New Bhuj Plants - The Game Changer, which few years ago, was a barren desert with no water Read More ...

Demag All Terrain at Delhi Metro’s Critical Heavy Lift Task

Demag All Terrain Cranes
Delhi Metro Railway Corporation (DMRC) is undertaking a major construction of underground corridors and stations between Bhikaji Cama Place and Sarojini Nagar. The project, which is Read More ...

Casagrande XP Series Piling Rigs and TFC Cranes Work For Coal Berth Project at Vizag Port

Casagrande XP Series Piling Rigs
Casagrande piling rigs are working to set up a 7.36 million tons coal berth at Vizag Port. The berth which is instrumental towards adding the port capacity will handle imported thermal and coking coal for power and Read More ...

Teesta-III Hydro Power Project Mix Design and Application of HPC

Teesta Hydro Power Project
The Teesta-IIII hydroelectric project (1200MW) is a run of the river scheme located on Teesta River in the North District of state of Sikkim. The project comprises of 60m high concrete face Rock Fill dam (CFRD), with the two bays of chute Spillway on the Left Bank Read More ...

IOCL Paradip Refinery: An Engineering Marvel

IOCL Paradip Refinery
The fundamental approach in planning and designing an industrial project is to make it commercially viable across its lifecycle. The larger the capital investment is involved, the commensurate approach is to optimize and to control Read More ...

Tandem Girders Lifting by Express Equipment

Gujarat based crane rental major, Express Equipment Rental & Logistics Pvt. Ltd (EERL) has recently undertaken tandem lifting and shifting of precast concrete girders for flyover project on National Highway Read More ...

Engineering, planning, construction of Kochi & Dahej LNG Terminal

Setting up new generation liquefied natural gas terminals has its own set of engineering challenges as they continue to persist even post commissioning of the terminals. This has been evident with India's newly Read More ...

GIFT City

Artistically designed to serve as a paradigm for a classic city in terms of quality of life, infrastructure, ambience and also to be at or above par with globally benchmarked financial centers such as Shinjuku, Tokyo, Lujiazui, Shanghai Read More ...

Niagara Tunnel: An Engineering Marvel with No Parallels

Muscling its way through the rugged terrains of Niagara River, the Niagara Tunnel is now gushing in 500 cubic metres of water per second to the Sir Adam Beck Generating Station in Ontario, Canada. As high as a four storey building, the Read More ...

Bangalore International Airport Expansion Shaping Up

The expansion of Bangalore International Airport mainly involves the integration of existing structure with the upcoming one P. P. Basistha visited the site to take a stock of the activities being put to shape up Read More ...

Marina Bay Sands Singapore’s Architectural Icons

Marina Bay Sands is a 929,000 square meter (10 million square-feet), high-density and mixed-use integrated resort complex that brings together a 2,560-room hotel, a 120,000 square meter (1,292,000 square feet) Read More ...

SBH Shoring System for MBMC Sewerage Project

The Mira-Bhayandar Municipal Corporation (MBMC) awarded a contract to SPML Infra Ltd for underground sewerage in Mira-Bhayandar city in Thane, Maharashtra under JNNURM Read More ...

Kochi LNG Terminal: A Mega Project in the Making

Located along the shore of Arabian Sea and surrounded by lush greenery, Puthuvypeen SEZ in Kochi is a truly visual treat for visitors. But more so, it is the buzzing activity of construction workers and large number of Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week