Hydro Power Current Scenario in India

Risks, Impediments, Opportunities

Bhakra Nagal Dam Hydro Power

Sandeep Upadhyay
Sandeep Upadhyay, MD & CEO - Centrum Infrastructure Advisory Ltd
The first Hydel Power Station (HPS) implemented in India was Sidrapong one in Darjeeling (West Bengal) completed in 1897 and is still in operation. Hydropower technology is well-proven with efficiency rates which could go upto 90% depending on the design power. The depreciated Hydro Power Stations i.e. Pong on Beas River and Bhakra on Satluj River are currently selling power @ 18 and 28 paise/unit respectively. However, the advantages of longevity and cost of generation doesn't reflect in trends in India's energy mix which is dominated by thermal power (70% share). Hydro, with an installed capacity of 42,783 MW, has a share of around 14% in 2016 coming down from 46% in 1966. This clearly indicates that there is an over-dependence on thermal plants vis-à-vis hydro assets.

The plummeting share of hydro in the overall power portfolio is primarily attributable to the consistent non-achievement of targets. Out of 10,897 MW of target capacity addition as per 12th Plan, only 3811 MW has been achieved, which indicates that only one-third of the target was achieved during the first two-thirds of the period. The same trend was observed in the previous 11th Plan wherein only 40% of the target was met.

Challenges to the govt. and to the private players
As per the Central Electricity Authority Assessment (CEAA), the economically exploitable hydro power potential in terms of installed capacity as 148,701 MW, out of which 145,320 MW is from schemes having capacity above 25 MW. As on Mar'16, the hydro-electric schemes in operation account for only 31% and thus, the bulk of the potential (69% including the projects that are under development) remains to be developed. Globally, countries like Canada and Brazil had harnessed around 48-69% of the economically feasible potential back in 2009.

The Government of India has taken many policy initiatives for sustainable hydro-power development. In 2008, the government came out with a Hydro Policy with an objective to achieve the implementation of these projects. The centre and many states have initiated hydro projects through PPP to attract investors for the development of water resources in an environment-friendly manner and to generate revenue while ensuring project viability. Odisha adopted PPP policy in 2007, Arunachal Pradesh (2011), Uttarakhand (2012) and Andhra Pradesh & Gujarat had framed PPP policy. Many projects had been allotted under PPP, however, some of these projects have struggled in the past due to several reasons such as R&R issues, land acquisition problems, clearance and approval procedures, capability of developers, etc. These issues resulted in a declining share of hydropower in India's power mix by almost 32% in the last 50 years. For example, in Arunachal Pradesh, out of 120 MoUs (~40 GW) signed in last dacade, most of the projects are at a standstill. India added 1824 MW of large hydropower capacity in 2015, most of these projects have a troubled track record in one way or the other that include issues like land acquisition, R&R, and cost escalations.

Due to inherent risks associated with the sector, such as geological surprises, natural calamities, environmental & forest issues, and rehabilitation and resettlement issues apart from commercial risks and change of river basin during operation, many developers are averse to enter into the sector. The major commercial deterrents for the private developers are high capital cost and long payback period due to high gestation period which may also create issues in financing.

Solutions and policy framework need to be looked into
Though, PPP is most suitable for hydro-power projects as it solves budgetary constraints, ensures faster implementation of projects, and balances project risks, however, without monitoring of implementation, it may lead to disasters like one happened in Shree Maheshwar Hydel in Madhya Pradesh, which is still not operational though project implementation started in 1992. This calls for central government to setup a separate body in partnership with the state governments for active monitoring of the progress of Hydro projects and resolve the impediments by directly overseeing issues such as land acquisition, rehabilitation & resettlement of affected people, expediting environment and forest clearances, interstate disputes and law & order issues arise due to these projects.

The other issue related to Hydropower projects is financing and evacuation. Hydro Power projects are capital-intensive and financing them for long such as 20 years is really a challenge. Further, a number of hydropower projects are located in remote sites in states which do not have enough demand for electricity that presents geographical constraints in developing requisite transmission infrastructure for evacuation.

Opportunities for the private sector
Through the private route, only about 3100 MW has been commissioned contributing 7 percent of the total installed hydropower capacity signifying that there is minimal, participation of the private sector.

Private developers, today seek commendurate returns with respect to risks involved in the sector. The private developers today have avenues to invest in Solar Power and Wind Power where technology risk is minimal and these projects with the same capacity in Hydro can be implemented within a significantly lower time vis-a-vis what is required for implementation of Hydro power project. Further, solar and wind power projects today are comparatively lower capital intensive as compared to Hydro. In view of this, untill and unless the government promises effective intervention in laggard long-drawn clearance processes and takes responsibility in R&R, land acquisition, evacuation, law & order problems, and other disputes, the investor confidence which as of now has plummeted will not restore.

Conclusion

India has vast potential for hydro-power development. A major part of the unexploited potential exists in Himalayan and North Eastern regions. The hydro sector inherently poses few challenges primarily on account of risk associated with implementation that can be mitigated with timely involvement of government agencies to be made responsible for. The private developers will engage themselves only if they find compatible risk adjusted returns in the hydro sector. Thus, government has now two-fold work of removing the impediments and restoring the investor's interest in the sector and to create an enabling environment.

NBM&CW July 2016

Real Estate Industry in 2019

Post the revival of the Indian real estate sector through a series of initiatives by the government, the confidence of the homebuyers has increased with a clear understanding of the market. The developers have also witnessed Read More ...

Technology Transforming Indian Real Estate

One of the most potent and radical ground-breaking technologies set to transform property markets in current times is artificial intelligence (AI), which along with machine learning are reforming technology all Read More ...

Indian Construction Equipment Sector - Seeing Unprecedented Growth & Intelligentization

The Indian equipment sector is undergoing sweeping changes not just in terms of higher demand amid the government’s resolve to build world-class infrastructure, but also due to the digitalization and intelligentization Read More ...

Indian Real Estate Sector 2018 - New policies for Growth, Development & Transparency

India's Real Estate Sector is seeing a resurrection with the several structural changes initiated by the government in 2017. The Government has put housing on a high growth trajectory by offering tax and fiscal incentives to Read More ...

India's Booming Aviation Sector - Will Boost CE Industry

India has witnessed a six-fold increase in passengers over the past decade due to better connectivity and cheaper fares. Global consultancy and research firm Centre for Asia Pacific Aviation (CAPA) revealed in its recent report Read More ...

Diversifying for Growth

A trend that is being noticed in the last one year, is that of companies diversifying from their core business to the Infrastructure Sector, where they are seeing a good potential for expanding their business footprint. Prospective Read More ...

Infrastructure Creation in India – The Next Generation of Reforms

Infrastructure is the centre piece of India’s growth-story. The total outlay for infrastructure in the FY 2018-19 stands at ₹5.97 lakh crore, as compared to the ₹4.94 lakh crore for FY 2017-18, thereby making an increase of more Read More ...

Bharatmala to Boost Real Estate Activity

The government’s ₹7 lakh crore Bharatmala highway-building programme is expected to give a big boost to the Real Estate sector, besides raising demand for steel and cement and creating large-scale blue-collar Read More ...

RERA: Law of the Land?

It is nearly a year since the Indian realty entered a new paradigm with the on-set of nationwide implementation of the Real Estate (Regulation and Development) Act, 2016 (RERA). As the first anniversary of RERA draws Read More ...

2017: The Year of RERA – What is the current scenario?

The Real Estate Regulatory Act (RERA) which came into effect from 1st May 2017, was aimed at ensuring accountability, infusing transparency and bringing uniformity in practices in the real estate sector Read More ...

Real Estate 2018 Era of RERA, GST and REIT

The year 2017 has been the most eventful period for the Indian Real Estate sector with new regulations and policy changes, following demonetization, roll out of RERA, Benami Transaction Prohibition Read More ...

Miles and miles to go...For Indian cities to be truly smart!

The last few years have witnessed pragmatic policies to bring about an urban renaissance in the country through innovative initiatives in urban development. On the top of such initiatives is the government Read More ...

The big bang Highways construction plan

In a master stroke to bridge the physical infrastructure deficit in the road and highway sector, the government has unveiled its biggest ever plan involving Rs.6.92 lakh-crore to construct 83,877 km of roads Read More ...

New Age Technologies for Construction Industry

The construction industry is changing rapidly, and new materials and technologies are being introduced on a regular basis. Execution of construction projects and their timely delivery Read More ...

New age airports must be agile, smart, and sustainable, as well as revenue efficient

In September 2014, the Airports Authority of India (AAI) had announced that it would be building 50 low-cost, no-frills airports all over the country. This is in tandem with its Policy on Airports that clearly Read More ...

Poor demand to keep private power producers under stress in medium term

The irony couldn’t be starker: for a country where significant stretches remain untouched by electricity, leave alone enjoy uninterrupted power. Power producers are battling a glut. Recent years have seen Read More ...
NBM&CW

New Building Material & Construction World

New Building Material & Construction World
MGS Architecture

Modern Green Structures & Architecture

Modern Green Structures & Architecture
L&ST

Lifting & Specialized Transport

Lifting & Specialized Transport
II&TW

Indian Infrastructure & Tenders Week

Indian Infrastructure & Tenders Week