Dam Rehabilitation With Cutoff Wall for Seepage Control

Christopher Burke, Ph.D., P.E., Mark Lukasik, P.E., and George Murphy, P.E., P.G., Tectonic Engineering Consultants, Geologists & Land Surveyors

As storm damage becomes more severe and has occurred more frequently in recent years, addressing the needs to repair essential infrastructure and dam rehabilitation is also becoming more common. However, deep foundation experts and others may find themselves working with restraints on the repair of essential infrastructure due to funding and environmental compliance requirements.

the historic Upper Candor DamRehabilitated Upper Candor Dam in spring 2019

As an example, the historic Upper Candor Dam, located in the Southern Tier Region of New York State, was damaged during extreme flooding associated with Tropical Storm Lee. The 2011 flooding resulted in a significant increase in uncontrolled seepage under, around and through the dam. If not remediated, dam failure was possible due to the progressive loss of soil along the seepage paths (piping), a loss that accelerates as the flow paths widen and allow for greater velocities.

Assessing the potential for failure and evaluating rehabilitation alternatives was difficult as there were no record documents depicting the internal structure of the dam and its foundation. The challenge was how to rehabilitate a dam without adversely impacting the existing, unknown and unpredictable structure. As outlined in this article, implementation of sheet piles was chosen to mitigate the risk while reducing the likelihood of seepage to prestorm magnitudes, and making the dam safe from pipingrelated failure.

Dam History

the historic Upper Candor DamMay 2012 discharge over the dam’s preconstruction crest
The run-of-the-river dam is 280 ft (85 m) long, 8 ft (2.5 m) high, and maintains a 55-acre-ft (68,000 m3) storage volume. The dam is believed to have been constructed in the early 19th century as a timber-clad, pile- supported or rock-filled wood crib structure to supply water to power adjacent millworks located along the Catatonk Creek in the Town of Candor, Tioga County, New York.

The dam was later fully encapsulated with a timber pile-supported continuous concrete spillway, an upstream concrete apron and a downstream splash apron comprised of large stone slabs. Prior to the storm, the Town of Candor had occasionally noted small, telltale whirlpools in the upstream water surface and sporadic loss of streambed in proximity to the crest. The dam was last repaired in 1997 to patch those precursor events and to replace portions of the concrete that encapsulated the older structure and served as the spillway.

Restoring the dam’s subsurface stability would clearly promote downstream safety, but so would removal of the dam. Catatonk Creek has a very shallow gradient of 5 ft/mi (0.95 m/km). Uncontrolled loss (or elective decommissioning) would have altered over 1,500 upstream meters (0.06 mi2 [141,640 m2]) of river habitat that had established over more than 100 years.

This habitat was already subject to protective seasonal work limitations, and New York State Department of Environmental Conservation (NYSDEC) further requested studies of three species of freshwater mussels and the inclusion of a fish passage. The Federal Emergency Management Agency (FEMA) ultimately declined to fund a fish passage, so that element was removed. With dam removal presenting a broad, dramatic and adverse impact to the area, preservation of the dam structure and the environment upstream became the principal goal.

Structural Investigation

the historic Upper Candor DamWater pouring through, below and downstream of the structure’s damaged dry face
A visual investigation was performed in June 2012 to thoroughly document the condition of the dam and assess the degree to which the storm had destabilized the structure. Boils were observed within portions of the splash apron, undermining the stones, and significant seepage emanated from riprap that lined the sides of the river bank immediately downstream of the spillway. Seepage was also documented from cracks within the concrete cladding of the spillway itself.

To evaluate appropriate and cost-effective means of remediating the dam, a subsurface investigation consisting of test holes and borings was performed through the concrete cladding above the spillway to identify the composition of the dam and the underlying soils. Although a clay core had reportedly existed, this condition was not observed. Substantial voids were encountered within the upper zone of the dam. The soils consisted of bedded river deposits (gravelly sand and sandy gravel) with a localized deep zone of clay-dominated soils. Cobbles were noted at depth, and numerous cobbles and boulders were observed at the surface.

The state of the structure was thus confirmed to be unpredictable, and remediation was required. The storm was declared a federal disaster in September 2011, and the town applied for funding through FEMA. FEMA ultimately agreed the storm had dramatically exacerbated the seepage and destabilized the dam, but was only willing to fund the repairs required to mitigate seepage.

Remediation Approach

the historic Upper Candor Dam
Since the internal structure of the dam could not be reliably ascertained for direct improvement, stabilizing the dam indirectly through seepage control was deemed the best approach. Tectonic Engineering Consultants, Geologists & Land Surveyors selected a sheet pile cutoff wall as a cost-effective and environmentally sensitive means of controlling seepage from beneath, through and around the dam. Aesthetically, this approach also considered that the dam is very visible to both the Village and Town of Candor residents. The sheet piling selected to control seepage would not alter the exposed structure or change the dam’s observable profile. Alternative methods, which commonly consist of mineral and/or chemical grouts, were eliminated as they can be difficult to control and the materials can become lost to the environment.

Key parameters in the design of the sheet pile cutoffs were the required depth and lateral extents of the piling. As the investigation did not identify the presence of a continuous, low permeability soil layer in which to embed the sheet piling, the design was based on the combination of identifying the point of diminishing return on the installation cost and ensuring that seepage was reduced to a safe magnitude where global stability returned.

the historic Upper Candor DamInstalling downstream sheet pile cutoff wall
Key to this premise was changing the hydraulic gradient: the difference in design water elevation from the upstream side of the dam to the downstream side of the dam, divided by the distance the water must travel to reach the downstream side. By forcing a longer flow path, the hydraulic gradient was decreased and the seepage would be reduced. A heavy PZ27 steel sheet pile was selected for the cutoff due to anticipated difficult driving resulting from coarse gravel, cobbles and possibly boulders, and the potential for joint interlock damage. The 10 ft (3 m) gap along the riverbed between the upstream sheet piling and the existing dam structure was resolved by first saw cutting a uniform edge to the upstream concrete cladding and casting a concrete apron extension as infill.

The NYSDEC commonly requires a detailed dam stability analysis when approving work permits. The previous repair work documents from 1997 were reviewed, but no recollection or record of interior conditions was found. To develop an analysis sufficient to grant a construction permit warranted knowledge of the dam interior. Subsurface testing within the dam was limited, however, and could only be completed to the threshold where a permit did not have to be granted by the NYSDEC to complete said testing. A separate NYSDEC permit to allow destructive testing sufficient to confirm the reputed complex, heterogeneous interior was impractical to obtain. The team was thus presented with a catch-22 scenario: an invasive investigation permit would require a stability analysis that could not be prepared without the subsurface investigation. This investigation permit would have further required constructing an expensive cofferdam upstream in addition to the selective demolition and reconstruction costs associated with the investigation.

the historic Upper Candor DamCompleted south crest sheet piling and apron extension
To resolve the impasse, an extended and extensive permit consultation was completed between the engineer and the NYSDEC to reach a new approach: address stability using limited field investigation results, external geometry, computational seepage analysis and an analysis that the seepage control structure would avoid imparting stress on the dam.

Analyses were performed to evaluate the impact of soil and water load transfer from the sheet pile seepage control to the existing dam structure. These analyses were performed using the computer program PYWall (by Ensoft), which incorporates the finite difference method. The load transferred to the existing dam was evaluated by adding a line load at the top of the sheet piling in the upstream direction of such magnitude to initiate upstream displacement of the sheet pile, knowing the load transferred to the dam would be less than this magnitude. The analyses showed that load transferred to the dam would be less than 5 lb/ft (7.44 kg/m) width of dam, a magnitude the dam was anticipated to safely tolerate. Therefore, the new upstream seepage structure was not a threat to the stability of the existing dam structure.

A finite element analysis was required to model the complexities of the seepage around the structure. The analysis and design were performed using the Midas Information Technology software package NTS GX. Due to the variable soil conditions, and consequently, the variable soil permeability represented beneath and around the dam, the analyses were performed using an assumed average permeability of the encountered soils. Analyses for below-dam seepage were performed with a two-dimensional model for sheet piles driven to depths ranging from 15 to 30 ft (4.6 to 9.1 m) below the top of the upstream concrete cladding at 5 ft (1.5 m) increments. Analyses for around-dam seepage were performed using a three-dimensional model with a similar approach, with sheet piling being extended laterally to a distance of up to 30 ft (9.1 m) beyond the abutments at 10 ft (3 m) increments.

the historic Upper Candor DamCompletion of dam seepage control, without causing a visual impact
For the case of under-dam seepage, the relative impact of each sheet pile depth increment in decreasing flow was evaluated in terms of the percentage reduction in flow from that modeled for the preexisting conditions, while assuming that the existing dam structure was impermeable for simplification. The analyses showed that sheet piling installed to depths of 15, 20, 25 and 30 ft (4.6, 6.1, 7.6 and 9.1 m) would result in under-dam seepage reductions of 40, 54, 62 and 67%, respectively. As modeling for existing flow conditions did not address that there are likely shallow, isolated zones that have experienced piping — and therefore are likely to be significantly more pervious than the surrounding soils — it was expected that the calculated percentage decreases in under-dam flow for the shallower cutoff depths are conservative. Specifically, it was estimated that the 15 ft (4.6 m) long sheet pile cutoffs would likely result in a minimum 50% reduction in underdam seepage.

Another consideration in selecting the sheet pile length was awareness of coarse gravel and cobbles existing within the alluvial soils, and of boulders that were observed to exist at least at the surface. The longer the sheet piling, the greater the chance of encountering these oversized materials that might damage the sheet pile interlock and render the cutoff ineffective. Fifteen foot (4.6 m) cutoffs were selected to minimize the possibility of damaging the interlocks. The estimated 50% seepage decrease was considered to be in line with prestorm event magnitudes, and to reduce the seepage magnitude at the dam to a level that could be considered safe against a piping-related breach.

The around-dam seepage case was evaluated for the cases of no lateral cutoff, and then for the noted 10, 20 and 30 ft (3, 6.1 and 9.1 m) wide lateral cutoffs. The bottom elevation of the sheet piles was maintained from that of the under-dam seepage analyses. The analyses showed that a 10 ft (3 m) lateral extension resulted in an approximately 23% reduction in around-dam seepage, and that a 20 ft (6.1 m) lateral extension would result in an approximately 58% reduction in around-dam seepage. The case of a 30 ft (9.1 m) lateral extension showed a comparatively minor decrease in around-dam seepage from that of the intermediate length lateral cutoff case. Based on the analyses, extending the seepage cutoffs 20 ft (6.1 m) laterally beyond the dam structure was selected. Due to conservative simplifications made in the model, this was anticipated to decrease around-the-dam seepage volume well in excess of 60%. This was determined to be a seepage volume that was both safe against the development of piping-induced dam breaches and to be defendable as a magnitude similar to that anticipated to have existed prior to Tropical Storm Lee.

Dam Rehabilitation

the historic Upper Candor DamConstruction of south cofferdam, upstream
Rehabilitating the dam to reduce seepage could only be accomplished by ensuring the sheet piles were installed to the specified depth with joints that were tight. The contractor elected to install the sheet piles using a Hercules Machinery Corporation Movax SP-100 Sonic SideGrip Vibratory Pile Driver mounted on a Caterpillar 330D L Hydraulic Excavator. Deneef Swellseal, manufactured by GCP Applied Technologies, was used to prevent water seepage through the sheet pile interlocks. Other than encountering remnants of the razed millworks, which were removed, installation encountered no obstructions and conformed to the specifications.

Constructing a cofferdam for a 122 mi2 (316 km2) watershed to permit two-stage construction presented a risk to the construction timeline. Provisions were included in the contract to halt work and remove in-stream temporary facilities should a large storm occur upstream. Portadams were utilized, which are able to be installed and removed in a very short amount of time. Sure enough, a state of emergency declaration was made in September 2018, during Stage 1 of the project; this resulted in a 2-week delay in project completion. The portadams were able to be lowered and obstructions removed from the flow path prior to the storm event, with no loss of constructed improvements as a result.

Conclusion

the historic Upper Candor DamHigh water through the construction site, August 2018
Since FEMA funds were restricted to damage caused by flooding associated with the Tropical Storm Lee event, rehabilitation costs for the Upper Candor Dam unrelated to storm damage had to be minimized. The FEMA-funded implementation consisted of sheet pile seepage control to restore stability, to reduce seepage to prestorm magnitudes, and to make the dam safe from pipingrelated failure, which achieved that goal. After work completion in May 2019, the dam has returned to use for recreational purposes and remains an important asset to the Town of Candor. The solution successfully mitigated the risk of the unknown variability of the existing condition and enabled completion under budget. The appearance of the dam remained unchanged as well.

After the final upstream sheeting was locked into place on the south abutment, the downstream south apron work was completed without local dewatering. In May 2019 when the final vegetative establishment inspection was performed, a dramatic reduction in seepage was evident and judged to have significantly outperformed modelled targets.

Acknowledgements

Continuous dialogue between all stakeholders was vital to project success. Besides FEMA, this included the New York State Department of Homeland Security and Emergency Services, Department of Environmental Conservation, and Department of Transportation, municipalities of Town of Candor (owner), and Village of Candor, adjacent landowners (required for temporary easements so construction materials and equipment could reach the dam), construction contractor R. DeVincentis Construction, and design and support professionals.

Christopher Burke, Ph.D., P.E., P.M.P., is manager of geotechnical services at Tectonic. He has over 24 years of geotechnical engineering experience, including management of site investigations, engineering evaluations, and geotechnical reports for the design and construction of buildings, roads, earth dams and more.

Mark Lukasik, P.E., is vice president and manager of civil engineering at Tectonic, with over 24 years of civil engineering experience, and oversees the preparation, coordination, management and presentation of capital designs for state, county and municipal clients, focusing on water resource transportation and land planning projects.

George Murphy, P.E., P.G., is engineering manager and senior geotechnical engineer at Tectonic. He has over 29 years of engineering, geology and geotechnical experience. Well versed in rock mechanics, Murphy has conducted numerous investigations and prepared designs for remediation for a variety of geologic hazards.
NBM&CW - February 2024
Enhancing Durability: Review of Rehabilitated/Retrofitted Structures

Enhancing Durability: Review of Rehabilitated/Retrofitted Structures

The word durability is a critical aspect that ensures the longevity and safety of structures. As existing structures age or face new challenges, rehabilitation/retrofitting becomes vital to enhance their durability. While rehabilit

Read more ...

Retrofitting of Rehabilitated Bridge Piers

Retrofitting of Rehabilitated Bridge Piers

Prof. Anjan Dutta, Prof. S.K. Deb, and Monjusha Sarmah (Research Scholar) Civil Engng. Deptt, IIT Guwahati, in this research paper investigate the rehabilitation of severely damaged bridge pier models by reinforced concrete jacketing

Read more ...

Retrofit Strategies for Tilted Multi-Storied RCC Buildings

Retrofit Strategies for Tilted Multi-Storied RCC Buildings

Devjit Acharjee and Debasish Bandyopadhyay, Department of Construction Engineering, Jadavpur University present a research on practical applications for assessing seismic vulnerability and optimising different retrofit strategies for existing

Read more ...

Retrofitting Structures of Historic & Heritage Importance

Retrofitting Structures of Historic & Heritage Importance

The definition of historic and heritage structures may vary from country to country and from culture to culture. But the need for the existence of these assets of historic values is nowhere denied, rather they are worth preserving.

Read more ...

Repair & Maintenance Techniques for RCC Building Facades

Repair & Maintenance Techniques for RCC Building Facades

Selection ideologies, materials, and methods for defect remediation in Concrete Buildings. The building façade or the envelope is the primary line of defense against water entering the living spaces. A typical building envelop today

Read more ...

Master Your Space with HomeSure TileEx Tile Adhesives

Master Your Space with HomeSure TileEx Tile Adhesives

In an innovative landscape, HomeSure is establishing a new benchmark for tile installation, presenting a solution that outperforms traditional cement in every aspect. Born out of extensive research and development, HomeSure leads with

Read more ...

Fabric Reinforced Cementitious Matrix: Structural Strengthening Systems

Fabric Reinforced Cementitious Matrix: Structural Strengthening Systems

The need for structural strengthening in aging infrastructures is rapidly escalating across various sectors, encompassing buildings, industrial structures, bridges, dams, ports, and other important structures. This demand extends

Read more ...

Assess Build Chem: Long-Lasting Solutions for Basement Waterproofing

Assess Build Chem: Long-Lasting Solutions for Basement Waterproofing

Assess Build Chem provides effective and long-lasting protection for buildings with its innovative products and solutions for deep/large basement waterproofing. Basement waterproofing is a crucial aspect of building construction, especially in

Read more ...

JOGANI Reinforcement: Alkali Resistant ARACC Coated Waterproofing Mesh

JOGANI Reinforcement: Alkali Resistant ARACC Coated Waterproofing Mesh

Jogani Impex is considered an industry leader in providing international grade Alkali Resistant ARACC Coated waterproofing mesh, which enhances the waterproofing systems and solutions in all types of buildings and structures, while saving money

Read more ...

Assess Build Chem’s Deep & Large Basement Waterproofing Solutions

Assess Build Chem’s Deep & Large Basement Waterproofing Solutions

Assess Build Chem, a leading provider of construction chemicals, is ensuring long-term protection of buildings with its innovative waterproofing solutions that include a 5-step waterproofing method for deep and large basements. Sunny Surlaker, Head

Read more ...

Agrani: Waterproofing, Retrofitting, Civil Work & Interior Fit Outs

Agrani: Waterproofing, Retrofitting, Civil Work & Interior Fit Outs

By adhering to the highest industry standards, Agrani Group has gained a reputation for delivering solutions waterproofing, retrofitting, civil work & interior fit outs that surpass client expectations, avers Ramendra Bahadur Sinha

Read more ...

FAIRMATE's FAIRFLO CRYSTALLINE: Waterproofing Admixture for Concrete

FAIRMATE's FAIRFLO CRYSTALLINE: Waterproofing Admixture for Concrete

FAIRMATE is catering to the Speciality Construction Chemical Industry by manufacturing a complete range of construction chemicals like FAIRFLO CRYSTALLINE - Waterproofing Admixture for Concrete, along with cost-effective solutions and world-class

Read more ...

Nippon Paint India: Paints, Construction Chemicals & Waterproofing

Nippon Paint India: Paints, Construction Chemicals & Waterproofing

In line with its global vision, Nippon Paint India is expanding its portfolio beyond the paint and coatings product range; it will now offer products and solutions under the broad categories: Dry mix, Repair and Maintenance, Construction Chemicals, and

Read more ...

Alkali-Aggregate Reaction in Concrete Structures & Preventive Measures

Alkali-Aggregate Reaction in Concrete Structures & Preventive Measures

When the alkali of cement reacts with the reactive constituents of aggregates, the reaction is deleterious though very slow, and the distress is exhibited when the volume inside the concrete is increased due to the formation of alkali-silica gel, causing the

Read more ...

Retrofitting for buildings: Enhance structure lifespan & efficiency

Retrofitting for buildings: Enhance structure lifespan & efficiency

Despite understanding the potential of retrofitting and its distinct and far-reaching advantages in making existing buildings green and sustainable, retrofitting continues to be undertaken on a very limited scale; hence, it needs to be promoted and made mandatory

Read more ...

Cause of Distress of an Old Building Through Advanced Analysis

Cause of Distress of an Old Building Through Advanced Analysis

The technical service life of a reinforced concrete building is the time in service when structural safety is unacceptable due to either material degradation or exceeding the load carrying capacity, or both. In which case, the repair strategy may be adopted

Read more ...

Value Engineering with MCI®-2019 Water Repellent for Concrete Repair

Value Engineering with MCI®-2019 Water Repellent for Concrete Repair

True value engineering saves money without reducing service life or affecting the quality of construction or materials. Ideally, it adds value to the project. MCI®-2019 Water Repellent is one such value engineering solution that can extend

Read more ...

Agrani Milestone Use Carbon Fiber Laminates to Strengthen Slab

Agrani Milestone Use Carbon Fiber Laminates to Strengthen Slab

Ramendra Bahadur Sinha, Managing Director, Agrani Milestone, explains the remedial measures and challenges faced during slab strengthening of a deflected slab at IIT. NBCC India Limited undertook the strengthening of a deflected slab at a G+2 storey IIT building

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.