Prestressed Concrete in Building

Partha Pratim Roy, B. E. (Civil), M. E. (Structure), General Manager (Technical), ADAPT International Pvt. Ltd.

Prestressed Concrete

Prestressed concrete is a method for overcoming concrete's natural weakness in tension. Prestressing tendons (generally of high tensile steel cable or rods) are used which produces a compressive stress that offsets the tensile stress that the concrete compression member would otherwise experience due to self–weight and gravity loads. Traditional reinforced concrete is based on the use of steel reinforcement bars, rebar, and inside poured concrete.

Prestressing can be accomplished in two ways: pre-tensioned concrete and bonded or unbounded post-tensioned concrete.

Pre-tensioned Concrete

Pre-tensioned concrete is cast around already tensioned tendons. This method produces a good bond between the tendon and concrete, which both protects the tendon from corrosion and allows for direct transfer of tension. The cured concrete adheres and bonds to the bars and when the tension is released it is transferred to the concrete as compression by static friction.

However, it requires stout anchoring points between which the tendon is to be stretched and the tendons are usually in a straight line. Thus, most pretensioned concrete elements are prefabricated in a factory and must be transported to the construction site, which limits their size. Pre-tensioned elements may be balcony elements, lintels, floor slabs, beams or foundation piles. An innovative bridge construction method using pre-stressing is described in stressed ribbon bridge.

Bonded Post-Tensioned Concrete

Typical Layout of Bonded System
Bonded post-tensioned concrete is the descriptive term for a method of applying compression after pouring concrete and the curing process (in situ). The concrete is cast around a plastic, steel or aluminium curved duct, to follow the area where otherwise tension would occur in the concrete element. A set of tendons are fished through the duct and the concrete is poured.

Once the concrete has hardened, the tendons are tensioned by hydraulic jacks that react against the concrete member itself. When the tendons have stretched sufficiently, according to the design specifications (see Hooke's law), they are wedged in position and maintain tension after the jacks are removed, transferring pressure to the concrete.

The duct is then grouted to protect the tendons from corrosion. This method is commonly used to create monolithic slabs for house construction in locations where expansive soils (such as adobe clay) create problems for the typical perimeter foundation. All stresses from seasonal expansion and contraction of the underlying soil are taken into the entire tensioned slab, which supports the building without significant flexure.

Post-stressing is also used in the construction of various bridges, both after concrete is cured after support by falsework and by the assembly of prefabricated sections, as in the segmental bridge.The advantages of this system over unbonded post-tensioning are:
  1. Large reduction in traditional reinforcement requirements as tendons cannot destress in accidents.
  2. Tendons can easily be 'weaved' allowing a more efficient design approach.
  3. Higher ultimate strength due to bond generated between the strand and concrete.
  4. No long term issues with maintaining the integrity of the anchor/dead end.

Unbonded Post-Tensioned Concrete

Typical Layout of Unbounded System
Unbonded post-tensioned concrete differs from bonded post-tensioning by providing each individual cable permanent freedom of movement relative to the concrete. To achieve this, each individual tendon is coated with a grease (generally lithium based) and covered by a plastic sheathing formed in an extrusion process. The transfer of tension to the concrete is achieved by the steel cable acting against steel anchors embedded in the perimeter of the slab.

The main disadvantage over bonded post-tensioning is the fact that a cable can destress itself and burst out of the slab if damaged (such as during repair on the slab). The advantages of this system over bonded post-tensioning are:
  1. The ability to individually adjust cables based on poor field conditions, e.g., shifting a group of 4 cables around an opening by placing 2 to either side).
  2. The procedure of post-stress grouting is eliminated.
  3. The ability to de-stress the tendons before attempting repair work.

Post-Tensioning in Building Structures

Market Factors Favoring the Post-tensioning System

Followings are the market factors, which favor implementing Post-Tensioning system in Building structures:
Dubai Pearl Project
  • Longer spans
  • Unique designs: irregular shapes
  • Shorter construction cycles
  • Cost reduction
  • Shorter floor-to-floor heights
  • Superior structural performance

Direct Cost Reduction

Beach Tower, Sharjah, UAE

Direct Cost Comparision between RC and PT Systems

Cost structure of RC vs. PT Slabs
Post-tensioning offers direct cost reduction over conventionally reinforced slabs primarily by reducing concrete and rebar material quantities as well as rebar installation labor. Typically, savings between 10%–20% in direct cost are achieved.

Followings are the factors which contribute to direct cost reduction:
  • Less concrete material
  • Reduction in slab thickness reduces total building height and cost
  • Less rebar
  • Less labor cost for installation of material
  • Reduced material handling
  • Simplified formwork leads to less labor cost
  • Rapid reuse of formwork leads to less formwork on jobsite
As a rule, the break even mark between conventional and prestressed solutions is approx. 7m spans.

In a typical slab with spans over 7 meters, the net savings in material cost can range between 10%–20% of original RC alternative. A typical comparative cost structure is shown on the next page:

Material represents 60% of direct cost of a post-tensioning system. Cost structure of PT System is shown there.

Improved Construction Efficiency

Construction Cycle
Since post-tensioned slabs are designed to carry their own weight at time of stressing, they can significantly improve construction efficiency and deliver an additional 5%-10% of indirect savings.

Following factors contribute to improved construction efficiency:
  • Shorter construction cycles
  • Less material handling and impact on other trades
  • Simpler slab soffit–less beams and drop caps/panels
  • Quicker removal of shoring gives more access to lower slabs
Typical 5-Day Construction Cycle schedule for 800-1,000 m2 of slab is shown below. 3-day cycle is also achievable with early strength concrete and industrial formwork.

Superior Structural Performance

The prestressing in post-tensioned slabs takes optimal advantage of tendon, rebar and concrete properties to deliver an economical structural system.

Factors contributing to superior structural performance are listed here:
  • Use of high-strength materials
  • Deflection control
  • Longer spans are achieved
  • Crack control and water-tightness
  • Reduced floor-to-floor height
  • Lighter structure requires lighter lateral load resisting system
  • Economy in column and footing design
  • Reduced noise transmission compared to RC
  • Lower total cost of ownership (maintenance) compared to RC alternatives

Typical Quantities

Post-Tensioning and rebar rates vary greatly depending on span configuration and loading. Compared to other countries, PT projects in US are designed with less loading and lower PT and rebar rates.

Bonded System

Layout of Original Design

Layout of Alternate Design
US values (1 kN/m2 SDL & 2.5 kN/m2LL)
  • 3 – 4 kg/m2 of PT
  • 5 kg/m2 of Rebar
With higher loading (3 kN/m2SDL & 3 kN/m2LL)
  • 3.5 – 5 kg/m2of PT
  • 7 – 9 kg/m2of Rebar

Unbonded System

US values (1 kN/m2SDL & 2.5 kN/m2LL)
  • 3.75 kg/m2of PT
  • 6 kg/m2of Rebar

Case Study of Value Engineering

Legend Plaza, Dubai, UAE is designed using ADAPT-Floor Pro (www.adaptsoft.com). Salient features of this project are listed here:

Project Parameters

  • Gross Floor Area–Superstructure: 72,000 m2
  • Typical Floor Gross Area: 11,000 m2
  • Total Floors: 7
  • Typical Floor Slab Spans: 10 m max / 8 m avg.

Type and Location

  • Type of Structure: High-end Residential
  • Location: Dubai, UAE
  • Construction Date: Aug 2004 – Jan 2005

Project Team

  • Prime Structural Engineers: Adnan Saffarini
  • Contractor: SBG
  • Client: Private Investment
  • PT Supplier: Freyssinet Gulf
  • PT Value Engineers: ADAPT Corporation

Design Criteria

  • Design Code: BS-8110
  • Concrete Compressive Strength Fcu: 40 MPa
  • Reinforcement Yield stress:460MPa
  • Superimposed Dead Load: 6 kN/m2
  • Design Live Load: 2 kN/m2

Original Design

  • Original Floor System: Hourdy Slab System
  • Depth of Floor System: 380 mm
  • Boundary Beams: Yes

Alternative Design offered by Freyssinet & ADAPT

  • Post-tensioned Floor System: 2-way Flat Plate
  • Depth of Slab:220 mm
  • Boundary Beams: None

Benefits

  • 70 % less rebar
  • 13 % less concrete
  • Elimination of all Hourdy Blocks
  • Unified structural slab system
  • Beams & drop caps were deleted, simplifying slab installation
  • 25% less formwork
  • 3 months shorter construction program
  • 15% savings in site overhead and plant
Value engineering saved Contractor over 1 million US$.

References

  • Wikimedia Foundation, Inc., (http://en.wikipedia.org)
  • ADAPT Corporation (http://www.adaptsoft.com)
  • Interested readers can contact the author at This email address is being protected from spambots. You need JavaScript enabled to view it.
Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
The demand for structural strengthening of ageing structures is growing rapidly in buildings, industrial structures, infrastructure projects like bridges, dams, etc. Structural Strengthening also

Read more ...

Durability and strength are two most important criteria and requirements for the long-term performance of concrete structures against weathering action, chemical attack and abrasion. Any deficiency

Read more ...

Cement is a key binder component of concrete production in the building industry. It is a complex hydraulic binder, made up of four main clinker components; alite (Ca3SiO5), belite (Ca2SiO4)

Read more ...

FAIRMATE manufactures a complete range of construction chemicals and provides cost-effective solutions and world-class services to the Speciality Construction Chemicals Industry in alliance with leading

Read more ...

Corrosion of concrete is a major issue and many concrete structures on adverse environment have experienced unacceptable losses in terms of serviceability, ultimately requiring replacement

Read more ...

Cement is the most used industrial commodity required for development, but it is also responsible for high GHG emissions; so there is a need to create a balance between the nation’s growth and environment sustainability

Read more ...

Cement concrete is the most consumed materials on the earth next only to water. The ingredients used in preparing concrete are not sustainable. The ingredients are responsible for causing global warming. The most

Read more ...

India’s ready-mix concrete (RMC) market is projected to witness a 7-9% CAGR in the next five years. This growth is predominantly driven by the increased investments in the development of infrastructure throughout

Read more ...

Concrete, being a physical mixture of cement, aggregate (sand and crushed rocks), and water, is the key construction material across the world. There is now a huge demand for infrastructure which has increased concrete

Read more ...

There is a need for technologically advanced concrete admixtures for the ready-mix industry that meet industry codes and meet or exceed the demands of challenging construction applications and adverse placement conditions

Read more ...

High Performance Concrete (HPC) is seeing major applications in the field of civil engineering constructions such as long-span bridges, tunnels, high-rise buildings, huge complexes, highway pavements, and more, since

Read more ...

Concrete being the second largest consumed material after water needs attention towards sustainable construction with an increase in infrastructure. The world is moving towards innovative techniques and methodologies

Read more ...

Co-processing of waste in the cement industry is an advanced and innovative recovery process whereby energy is recovered, and the non-combustible part of the waste is reused as raw material.

Read more ...

Traditional masonry units are not sustainable and eco friendly due to consumption of fuel or cement. It is essential to find sustainable alternatives. This paper reports about preparation of geopolymer bricks, masonry

Read more ...

Geo-polymer mortar (GPM) is proven for its strength, durability and sustainability [2 & 3]; strength of GPM is a function of alkaline to binder ratio, and has an adverse effect on consistence properties of mortar

Read more ...

Comparison of Reinforced and Pre-Stressed Concrete Building Frames This article discusses pre-stressing of concrete to get lighter and slender beam sections for six different four storied concrete building frames of different spans/lengths by the application of post-tensioning

Read more ...

Ready mix concrete (RMC) is the first choice for projects requiring concrete. The term ‘ready mix’ is used to describe a process where concrete is pre-made at a plant and delivered in batches to job sites. It is a convenient

Read more ...

When we talk of Primers that are applied before the paint work, what comes to mind are the Acrylic Primers. However, since the last few years, White Cement-based Primers are gaining popularity amongst the construction

Read more ...

Chemistry is truly relevant for concrete because chemistry controls the life/durability of concrete. It explains why cement hardens and the interaction between cement and its environment. Dr. S.B.Hegde at Udaipur Cement Works

Read more ...

Concrete is considered the world’s most versatile, durable and reliable construction material, next only to water. It is the most consumed material requiring large quantity of cement, fine aggregates, course aggregates

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.