U-girder is a platform that is prepared and placed on top of the piers (pillars) of the viaduct, on which the metro track is laid. These girders are pre-casted or prefabricated in the casting yard and are then placed with a crane over the pillars at a fixed time (at night) due to safety reasons. A total of 196 u-girders will be used for the elevated stretch of the priority corridor between Taj East Gate & Fatehabad Road. In just 7 months since launching the project, Agra Metro Project team has completed 553 piles, 100 pile caps and 64 piers for the elevated section of the priority stretch of the 29.4 km long first corridor, which runs from Taj East Gate to Sikandara.