Doka's recent work on the new Doha Orbital Highway shows how a combination of slick logistics and technical supervision help to make even the most challenging projects possible.

Photo: New Orbital Highway, Copyright: Doka
Project Facts
Project: New Orbital Highway and Truck Route – Package 2
Location: Doha, Qatar
Type of structure: Highway
Length: 47 km
Structure height: 18m
Overall length of bridge: 383m + 390m for Junction 3 structure
Longest span: 13,7m
Developer: Public Works
General Contractors: Ashghal QDVC, Bin Omran
Start of construction: May 2014
Systems used: Large-area formwork Top 50, Load-bearing tower Staxo 100 eco, Load-bearing tower d3
Services: Ready-to-use service
With both the national Vision 2030 and the FIFA World Cup 2022, Qatar isn't short of reasons to ensure its national infrastructure is delivered. Furthermore, to showcase itself as a sustainable and technologically advanced nation and with just four years remaining before the World Cup, virtually all projects are on a strict timetable.
When dealing with simultaneous infrastructure development on such a massive scale, the issue of traffic congestion can often lead to significant delays across multiple projects, potentially hindering essential deadlines, making the daily lives of commuters a living nightmare. Ashghal (Public Works Authority) came up with the solution of building a new orbital highway and truck route that would circumvent the capital, allowing construction equipment, personnel and material to reach their various sites directly, reducing disruption for Qatar's citizens and residents.

Having tendered the project in May 2014, the contract was awarded as a joint venture between QDVC and Bin Omran Trading & Contracting Company. The scope of the project involved connecting the Salwa Road to the North Relief Road with 47 km of highway including five dual lanes for light vehicles, two dual lanes for heavy goods and industrial vehicles, six viaducts, seventeen bridges, and underpasses. With a delivery date scheduled for 2018, the success of the project would require the exclusive involvement of companies that could work fast without cutting corners.
While working on some mega-projects in Qatar, including the Doha Metro, Doka was selected for the construction of the major bridges and viaducts, thanks to its reputation for technical ability, understanding the importance of safety, and its ability to deliver large quantities of formwork at short notice.

Fulfilling the project's safety requirements, Doka started from the beginning of the project. In the preparation phase, elements such as the shoring erection sequence, weight to be carried, integrated safety equipment on the material, access to the work area, and dismantling sequences were all carefully calibrated by Doka's engineers, providing a safe, productive, and cost-efficient solution to complete the project. Some of the value-added elements used by the Doka team included 3D modelling, screw jack extensions for each shoring towers made with AutoLISP, and wood boxes cut by CNC machines.
Speaking on behalf of the client, Baptiste Ravoire, methods manager for the JV, commented, "Doka Qatar's design team was highly professional and flexible to our requirements. We thoroughly appreciate the team's technical skills and its ability to solve different challenges encountered on the project. This project is particularly complex with tight contractual constraints, and with the support of Doka, we've been able to meet these requirements and ensure the intermediate milestones were met on time."
Doka is a world leader in developing, manufacturing and distributing formwork technology for use in all fields of the construction sector. With more than 160 sales and logistics facilities in over 70 countries, Doka has a high-performing distribution network which ensures that equipment and technical support are provided swiftly and professionally.