PM's Telebelt TB 105 at Work at the World Largest Embankment Dam

PM's Telebelt TB 105 at Work at the World Largest Embankment Dam
At the Jinsha River - a tributary of the Yangtze - the Xiluodu hydro-electric plant is currently being built with a purpose to generate electricity. At the same time, the plant will also fulfil other tasks like protection, from flod deposition of sediment, improvement in shipping conditions, and so on. It is expected that it would produce 57 to 64 billion kilowatt hours of energy every year, making the plant the third largest hydro-electric plant in the world.

A double-curved arch dam should dam up a storage lake of 12.67 billion m3. The absolute elevation of the dam crest is 610 m, the maximum height of the dam is 278 m and the overall length is 700 m. The total excavated material for this project amounts to 39.81 million m3 of which 25.61 million m3 is above-ground excavation and 14.20 million m3 is from the construction of tunnels. In total, 16.72 million m3 of concrete is required for this project and 6.60 million m3 of this is required just for the body of the wall. The concreting work started in 2008. It is expected that the first generator set will be installed in June 2012 and hopefully it would start generating energy from June 2013 and the entire project would be completed by 2015. The total capital of $7.36 billion has been invested so far in the Xiluodu hydro-electric plant.

The devices in the Xiluodu dam that are planned for flood water flow include seven overflow drainage openings at a size of 12.5 m x 13.5 m, below them eight outlets at a size of 6 m x 6.7 m and four exceptionally large overflow tunnels (with a diameter of up to 15 m) – two tunnels on the right embankment and two more on the left. The overflow capacity of the project amounts up to 49,923 m3/s. The power which is generated by the overflow is almost 100 million kilowatts and is therefore the highest in the world. The four overflow tunnels are the largest of their kind in the world and have a discharge rate of 16,000 m3/s, which is about a third of the entire outlet capacity of the plant.

The water quantity and flow rate place high demand on the concrete

These numbers are not just attributed to the size of the tunnel but also to the flow rate of the river, which is amongst the fastest in the world (up to 50 m/s). Since these four overflow tunnels were designed to cope with exceptionally large quantities of water at an extremely high flow rate, the concrete that is used here must be of outstanding quality. The difference between this concrete and a pumpable concrete mix lies mainly in the proportions of the individual concrete raw materials that are used. Pumpable concrete requires a relatively high flowability so that it can flow through the delivery line. This means that concrete raw materials such as cement and flyash are required in large quantities. However, cement creates a lot of hydration heat when setting the concrete, it means that the temperature and crack formations are difficult to control. The dissipation of the hydration heat may pose a problem, particularly with structures such as a dam.

Telebelt comes out ahead

Telebelt is a mobile belt conveyor that can continuously convey any kind of bulk materials and concrete and is unrestricted by the pumpability of the concrete. Telebelt is therefore the perfect solution for pouring high-quality mass concrete as it not only lessens cracks but also reduces the cost of the concrete.

The first Telebelt TB 105 delivered by Putzmeister has been used in the Three Gorges Dam project since 2000. To date, the number of operating hours is over 20,000 and the device continues to work properly - clear proof of the robustness and reliability of the Telebelt. Due to this experience, the company responsible for the Three Gorges project ordered two more Telebelts of the new type TB 110G for the team from SinoHydro Bureau 7. Since the machines are very convenient to operate and the boom can be gently and smoothly telescoped, swung, lifted and lowered, the two TB 110G devices are very popular on the construction site. The machine has evoked a positive response among the workers from SinoHydro Bureau 7: Concrete pouring has become child's play. However, if we look at the quantity of concrete that the Telebelt must continuously pour for each concreting - more than 1,000 m3 of concrete - it becomes clear just how hard the work is for the workers on the construction site.

Telebelt is in great demand across power plant construction site

PM's Telebelt TB 105 at Work at the World Largest Embankment Dam
PM's Telebelt TB 105 at Work at the World Largest Embankment Dam

The Xiluodu hydro-electric plant is a huge construction site. Several projects are going on simultan - eously and these are co-ordinated centrally. The individual construction teams work closely together. It is often the case that immediately after the concreting task is finished, the belt conveyor travels to the next site of the construction site. Due to high level of flexibility and mobility, the Telebelt is often used "on the front line". The TB 110G from Putzmeister was therefore not only used on the construction sites of SinoHydro Bureau 7 (in other words, to construct the overflow tunnels, the foundations of the cable crane structure and for above-ground concreting, etc.), but it also considerably helped the construction sites of Hydro Bureau 6 and Hydro Bureau14 (among others) when constructing the surge tank, the underwater outlet, the main transformer building etc. As a result, on one occasion, the Telebelt was used at five different construction sites within six days, during which it continuously placed 4,800 m3 of concrete for the overflow tunnel, the cable crane platform and the underwater outlet. The high level of efficiency demonstrated by the belt conveyor is another performance feature that is recognised on the construction site. For example, the TB 110G generally requires only 2.5 minutes to drain a mixer of 6 m3 for the work on the cable crane platform and, at a slightly higher speed, it requires only 1.8 minutes to drain the mixer. This extremely high machine output significantly contributes to completing the work within the scheduled time.

The longest river in Asia with the changing name

The 6,300 km long Chang Jiang (also known as the Yangtze - the "Long River") is the longest river in Asia and, after the Nile and the Amazon, is the third-longest river in the world. It originates as the Dri Chu (Tibetan "river of the female yak") from the Ganjajubu glacier at an altitude of 5,405 m and continues under the name of Jinsha Jiang - "Gold Sands River" - from north to south along the entire border between Sichuan and Tibet. In the Hengduan Mountains, it crosses the border between Sichuan and Yunnan. From the city of Shuifu, it flows under the name of Yangtze until it reaches the East China Sea to the north of Shanghai.

The dam should reduce sludge load

In the Red Basin, the Yangtze is fed by numerous tributaries that drain, for example, the eastern slopes of the Tibetan highlands. The tributaries feed the Yangtze with large quantities of sand, silt and clay - an annual quantity of approximately 680 million tons, which is as much as the Nile, the Mississippi and the Amazon together! This makes the "Long River" one of the most sediment-rich rivers in the world. Where it is damed - like at the huge Three Gorges Dam - the flow velocity of the water slowes down, sediment is stored in the reservoir and gradually silts up. The Xiluodu dam should counteract this. It is expected that the dam should reduce the quantity of sludge in the Yangtze by a third.

Mammoth producer of energy

PM's Telebelt TB 105 at Work at the World Largest Embankment Dam
Once completed, the Xiluodu hydro-electric plant will produce 12,600 MW of power. This means that, with regard to power plant capacity, it would be the second-largest hydro-electric plant in China after the Three Gorges project and the third-largest in the world. The China Yangtze Three Gorges Project Development Corp. is planning three more giant hydro-electric plants at the overflow of the Yangtze, namely Wudongde, Baihetan and Xiangjiaba. At 38.5 million kWh every year, their combined power generation should be double than that of the Three Gorges Project.

Special configuration: Arch dam

In valleys that are very high and narrow, the preferred dam to build is the arch dam. The wall forms a vertically and horizontally tensioned arch towards the side of the water. Due to the arch-shaped design that is directed against the flow of the river, the mass of water is distributed over a larger surface area and therefore puts less stress on each unit of area. Significantly, fewer materials are required to construct these dams that are required for other types of dams. However, the water pressure is diverted over the arch to the foundations in the mountain at the side. The attachment to the rock is therefore particularly important with this wall design.
Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
Gamzen equipment is offering a range of equipment that includes concrete batching plants, beach cleaning machines, and railway rail track machines. The company is also offering equipment on lease. “We have been in the CE industry since 51 years; we started by manufacturing

Read more ...

Sunbeam Infra Equipment-(A vertical of Sunbeam Generators Pvt.Ltd), which was took roots in late 2016 for manufacturing Transit Concrete mixers, has progressed to become a manufacturer of a comprehensive range of solutions. Along with generator sets, it offers concrete

Read more ...

ARGO 3500, 3.5 m³, self-loading concrete mixers suitable for railway permanent way works, construction of buildings, industrial projects, canal lining and concreting of roads. ARGO 3500 is designed with Dual Engine, the FIRST of its kind in CE Industry

Read more ...

Looking to have a sizeable business presence in the growing concrete self-loading mixer segment, KYB Conmat is promoting its 4.8, 2.8, 4.3, and 4 cum/hrconcrete self-loading mixers(CSLMs), which are BSIV compliant and ARAI approved. The KYB Conmat CSLM has

Read more ...

Schwing Stetter India unveiled 14 new products at Excon. An impressive highlight was the Boom Pump S47 - the longest product on display. The other products on display were

Read more ...

AJAX, which offers next-generation 360-degree concreting solutions, has launched products from its entire spectrum of concrete production, concrete placement, and concrete paving at Excon

Read more ...

Macons produces the highest quality concrete equipment for the construction of large civil projects. At Excon, the company presented its turnkey concrete batching and mixing plant solutions along with Socage range of products

Read more ...

At Excon, Columbia has displayed a special machine that allows dimension of varying thickness ranging from 25 – 250 mm enabling production of concrete tiles and pavers on a single machine. The increased height of the machine assists in casting

Read more ...

Schwing Stetter (India) recently organized a week-long event ‘Technovation 2022’ at its new global manufacturing hub in Cheyyar, Tamil Nadu. According to V.G. Sakthikumar, MD, Schwing Stetter (India), the key objective of the week-long event

Read more ...

With infra development gathering pace, demand for concrete producing, transporting and placing equipment is increasing, and driving equipment manufacturers to upgrade their products with innovative features, including digitization

Read more ...

AJAX, the world’s largest SLCM manufacturer, always has a ‘Customer First’ focus, so much so that when it comes up with a strategy for business advancement, it keeps the stakeholders’ interests in mind. The company’s aim

Read more ...

As an equipment manufacturing company committed to sustainable environment, ApolloCarmix Equipment Pvt. Ltd., has made all its ApolloCarmix mixers BS IV compliant. Its newly launched CEV Stage IV ApolloCarmix 4x4 concrete

Read more ...

Schwing Stetter India has unveiled its state-of-the-art Self-loading Mixer – SLM 4600. It will cater to higher output requirements of concrete batching, mixing and placing in the urban development Segment. It is being rolled

Read more ...

MACONS, a leading manufacturer and supplier of world-class equipment for use in India and for the global construction markets, has introduced its latest MST series of Self Loading Concrete Mixer

Read more ...

Sicoma Mixers India has successfully implemented TUV SUD ISO Procedures for the scope of Manufacture and Sale of Concrete Mixers and Spare Parts. The company is now ISO certified for

Read more ...

The fusion design of the transit mixer as loader, mobile batching plant, and mixer, has positioned it as a unique product that owes its popularity to projects requiring small to medium volumes of concrete

Read more ...

AJAX Engineering, the world’s largest manufacturer of SLCMs, is now expanding its footprint to meet the growing demand from diversified construction segments such as roads, railways, energy, and irrigation. It has

Read more ...

MACONS, a leading manufacturer and supplier of world-class equipment for use in India and for the global construction markets, has introduced its latest MST series of Self Loading Concrete Mixer ‘MST-4’ which is

Read more ...

After a successful stint in the road construction equipment industry, Saumil Shah, one of the promoters of Kaushik Group, has taken a decision to diversify into the concrete equipment manufacturing segment

Read more ...

Apollo Carmix Equipments Ltd (a joint venture arising from the union of Carmix and Apollo Concrete Solutions in 2014), is the only manufacturer of front-loading truck mixers and is responsible for the sale of

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.
Click here to subscribe.