Prof. Satish Chandra, Ph. D. Director, CSIR-Central Road Research Institute, Delhi
Two types of pavements are laid in India-rigid pavement and flexible pavement. In simple terms, a flexible pavement can be defined as a pavement layer comprising of a mixture of aggregates and bitumen, heated and mixed properly and then laid and compacted on a bed of granular layer. Rigid pavements on the other hand, are made from cement concrete or reinforced concrete slabs, laid over a low strength concrete layer (Dry lean concrete, DLC) or on a well compacted layer of aggregates or both.
Flexible Pavements

Flexible Pavement Cross-section
courtesy: www.theconstructor.org
Rigid Pavements

Rigid Pavement Cross-Section
courtesy: www.theconstructor.org

Difference between Flexible Pavements and Rigid Pavements
courtesy: www.theconstructor.org
Design Strategy
The design of pavement varies with soil conditions and the amount of traffic expected to be carried during its design life. Flexible pavements in India are designed based on California bearing ratio (CBR) of subgrade soil and expected number of cumulated axles (measured in million standard axles, msa) during the design life of the pavement. These pavements are designed for a period of 15 years. The method of design allows use of conventional as well as stabilized materials in any layer of the pavement, and thickness of each layer is taken from the templates given in Indian Roads Congress (IRC) design code.
Rigid pavements are designed for a period of 30-40 years and thickness design of rigid pavements are influenced by traffic loading, subgrade soil, moisture, and temperature differential. First, the thickness of rigid pavements is designed for fatigue failure. The computed thicknesses of the pavements are then checked for the critical combination of load stresses and temperature stresses.
Comparison
Flexible pavements and rigid pavements can be compared on different parameters. Here only two parameters are considered: cost of construction and carbon footprints.
Comparison Based on Cost
A typical section of two-lane road with 7.0 m carriageway and 1.5 m wide shoulders on either side is considered. A length of one kilometer is considered for computation of the cost. Two types of pavements were designed for different types of soil subgrade (CBR ranging from 2 percent to 10 percent) and design traffic (1 msa to 150 msa), and the cost of each layer is computed using Dehradun PWD schedule of rates. Therefore, a total of 90 pavements were designed and the costs of construction and maintenance were computed. The above ranges of soil and traffic values are assumed to cover almost all possible combinations of soil CBR and traffic loadings.

Table 1 gives the costs of flexible pavements in million Rupees designed for different combinations of soil CBR and traffic conditions. Equation 1 shows the relation between the cost of flexible pavements and the soil CBR and traffic loading.
Cost = -16.98 + 12.136 x CBR-0.3 + 15.476 x msa0.10 -----------------------------(1)
(R2 = 0.98)
The cost of Rigid Pavement is also computed and the total cost of construction and maintenance for different soil and traffic conditions is shown in Table 2. Eq. 2 relates cost with CBR and traffic.

Cost = 8.284 + 4.719 x cbr-0.9 + 20.83 x msa0.15 -----------------------------14
R2 = 0.95
The points of equal cost on the CBR vs msa graph are plotted in Figure 1. Rigid pavements are found to be economical in the upper portion of the graph and flexible pavements are economical in the lower portion of the graph. Mathematically:
if msa < 12.48 + 6.05 x CBR, flexible pavement will be economical;
if msa > 12.48 + 6.05 x CBR, rigid pavement will be economical;
if msa = 12.48 + 6.05 x CBR, both pavements will have the same cost.
Comparison Based on Carbon Foot print
Another comparison between flexible and rigid pavements could be in terms of carbon foot prints spent during construction. Road construction consumes energy in following five phases.
- Energy consumed in manufacturing of construction materials (Embodied Energy)
- Energy consumed in the site preparation (Pre Construction)
- Energy used in actual construction of roads (induced energy) and transport of material (gray energy) [Construction equipment, material transport and on site impact]
- Energy consumed during mainte- nance of road [Maintenance]
- Energy consumed in demolition phase as well as recycling of their parts

Chart 1:
Note: WMM = Wet Mix Macadam; DBM= Dense Bituminous Macadam; BC = Bituminous Concrete; DLC = Dry Lean Concrete; PQC = Pavement Quality Concrete
The green house gas emissions during construction of two types of pavements are shown in Chart 1. All calculations are made for one kilometer road length with 7.0 m wide carriageway.
As may be seen, in case of rigid pavement, the embodied energy constitutes almost 96 percent of total emission while in case of flexible pavement energy consumed during construction is also substantial. However, if emission only during the construction is considered without considering the embodied emission of materials like cement and steel bar, then rigid pavement has lower emission during construction process.
Concluding Remarks
Major highways constructed in the world are of bituminous surfacing. For example, 86 percent of rural highways and 78 percent of urban roads in the U.S. are of flexible type. Most of the runways in the world have flexible pavements, Autobahn in Germany is also with flexible pavement. However, the choice of type of a pavement is governed by the type of traffic and soil conditions. In case of areas where soil subgrade is weak (like clay) and drainage conditions are also difficult to maintain at desired level of performance (like in urban areas or in situations where road passes through habitation), rigid pavement can be a good choice. But when soil subgrade is of good quality and traffic is also not very heavy, flexible pavements can be more economical. The biggest advantage with flexible pavement is that they can be made in stages. The economic analysis done by an expert committee for the upcoming Nagpur – Mumbai Access controlled Expressway also indicated that if stage construction is adopted, then flexible pavement will be much cheaper than rigid pavement.