Simulating oversize and heavy vehicle manoeuvres using AutoTURN® from Transoft Solutions.

Use AutoTURN® to design infrastructure adjustments to safely operate trucks transporting wind turbine components.

By Er. Alessio Gori - collaborator at POLITECNICA INGEGNERIA ED ARCHITETTURA SOC. COOP. (Infrastructure division - Head Office Firenze)

mezzo eccezionale

Narrow mountain roads, steep hills and challenging ‘S’ curves are just part of the landscape in the ‘toe’ of Southern Italy, where wind farms are becoming a common part of the countryside. With green technology like wind farms gaining popularity as generators of clean, efficient energy sources, technology and engineering are coming together to make these projects as safe and cost effective as possible.

In Reggio Calabria, the ENEL Green Power project proposed 2 wind farms development to be constructed in two areas: Piani di Lopa with 14 wind turbines rated output 0.85 MW and Campi S.Antonio with 25 wind turbines rated output 0.85 MW, within the boundaries of the three southern Italian municipalities of Bagaladi, Montebello Jonico and Motta San Giovanni.

The Aspromonte region infrastructure network has a limited number of paved roads. They are mostly classified as "mountain roads", both for the geometric road characteristics and for horizontal curves of low radii. The location of Piani di Lopa and Campi S.Antonio wind farm sites, which experts say are excellent for the wind and the rated power output, means engineers must study and plan the routes carefully prior to the transportation stage of the wind turbines components.

Special Software Required

Due to those conditions, the use of specialized software simulating oversize vehicle paths is important for evaluating how the transportation of wind turbine components along the provincial roads might be achieved. Two routes in particular, Strade Proviciale (SP) 3 and 107, from Reggio Calabria harbour to the project sites presented challenges to the engineers.

The objective of the path simulation along the provincial roads SP 3 and SP 107 was to verify the a priori conditions of the existing infrastructures. The actual tests have been set aside because they would have affected the road traffic and delayed the project schedule. Moreover, it has been possible to identify possible adjustments to the existing infrastructure in order to safely operate the oversize vehicles. Local engineering professionals were called in to inspect the overall topography of the route to assess any challenges. They measured the topography and the most critical curves along the route. They also tested the vehicle swept path of an oversized vehicle with an unloaded trailer.

The aspects listed below are potential issues in the traditional approach, which is suitable for short routes and/or simple studies:
  • The route length (40km)
  • The number of potentially critical points (about 150);
  • The presence of bridges, with geometry shown to be unsuitable for oversize vehicle paths.
AutoTURN, developed by Canadian software developer Transoft Solutions and distributed by One Team S.r.l in Italy was selected as the software for the simulation. The software allowed ENEL Green Power to perform vehicle swept path analysis and simulate the driving conditions of the area.

AutoTURN® includes a large selection of predefined vehicles, organized in international libraries and the software performs the simulation of "elementary" manoeuvres as well as of "simple" vehicles, trucks and special vehicles. The last ones are mainly common in Australian and North American regions (called "road train", combination of truck and 2 or more trailers). With the possibility of customizing the AutoTURN® library, defining the "vehicle type" and "ad-hoc" simulation profiles have been fundamental design aspects.

The oversize vehicle geometry and the steering characteristics of each component have been reproduced in a plan and meets the guidelines regulating the automatic steering of rear axles of the semi-trailers in relation to the front truck axles (Fig.4). Through a range of speeds, from 5km/h to 20km/h, each iteration showed the swept path of the simulated vehicle matching the swept path of the field test vehicle accurately. (Fig.5)

Definizione veicolo - Tipologico veicolo Autoturn

Choosing the Vehicles, Simulating the Route with AutoTURN

montaggio
Fig2 - montaggio
Melca Transporti worked with ENEL Green Power to conduct the path simulations. The inspection process designed by the two companies helped identify critical points along the route and the company made adjustments to ensure the equipment could be transported safely. After this process, the companies used an unloaded vehicle to successfully test the path and the convoys drove the route safely without delays or issues.

The vehicle type was selected by determining the characteristics of the three basic components that have to be transported from the production site to the building site. The basic components are:
  • fibreglass blade : length 26m, height 2.50 m
  • single section tower: width 3.60m, height 3.60m, length 25m
  • nacelle (to be installed at the top of the generator): width 2.50 m, height 3.00m, length 7.00m, weight 40 tonnes
The components are assembled with a mobile crane (Fig.2)

Wind turbine components are transported to the project site with wheeled vehicles, classified as "oversize transport vehicle", pursuant to Nuovo Codice della Strada (the new Highway Code). In accordance with the indications of the wind turbine producers, two "vehicle types" have been defined:
  1. Semi-trailer truck transporting a metal structure containing 3 "blade" components;
  2. Semi-trailer truck transporting the tower sections (Fig.3): the evaluated section is the critical one for its geometry; it is where the nacelle sits on the trailer. The nacelle also houses the rotational movement of the 3 fibreglass blades.
Figure 3
Figure - 3

The two "vehicle types" definition has been fundamental because type 1 has optimized the dimensions related to the length of the freight while the type 2 has shown the issues related to the semi-trailer truck width. The vehicle manoeuvre was conducted on both types of vehicles concurrently. The analysis was based on the hypothesis of keeping general traffic on the Piani di Lopa roads separate from the lower speed semi-trailer traffic. In order to ensure the safety margin between the simulation and the real path, the semi-trailer truck with steering axles have been taken into account. However, they have been not provided with a remote control of the steering angle of each axle. The decision to not include this variable in the path simulation is related to a larger flexibility in the vehicle selection for the company responsible for the transport execution.

Simulations and other editing operations are managed within the CAD-based program and this kind of versatility is built into the software. Customization of design attributes is an integral part of the software allowing simultaneous visualization of multiple vehicle combinations including:
  1. The precise position of the truck and semi-trailers during the manoeuvre;
  2. The convoy path with distinct single paths of rear and front wheels;
  3. The vehicle clearance, including the trailer ground clearance.
After topographic measurements were made, the 40 km delivery route from Reggio Calabria to the project site has been performed, revealing several adjustment points. (Fig.6, 7)

intervento tornante / Confronto interventi

The articulated vehicle simulation was performed with AutoTURN® and the path manoeuvres have been defined and designed, preventing errors in path modelling due to possible design inexperience with the semi-trailer truck. Without the aid of AutoTURN®, the path analysis would have been performed qualitatively, deducing the vehicle clearance from the turn radius values and then overlapping the oversize vehicle swept paths to the topographic measurements.

This qualitative approach doesn't consider system analysis; in fact in the typical "S" road curve case, the use of the geometric method would mislead the engineers because it doesn't correctly analyse single critical points in relation to the project plan. The close distance between two "S"-curves suggests a behaviour which is difficult to define with "swept path" analysis. In AutoTURN® this problem is avoided because the design path is built into the software’s vehicle libraries for the exact vehicle type being studied.

At a later stage of the two vehicle types path simulation, the required adjustments to the existing infrastructure were identified including, about 100 small scale "ad-hoc" projects, like: bedrock excavation to widen the road, pile bulkhead structures ( Fig.8) creating manoeuvring space, removal and replacement of direction signs and safety barriers and removing trees. From an economic standpoint, it is important to identify any conflicts along the route (Fig.9), including lighting and telephone wiring. AutoTURN allows the planning to take place ahead of time, speeding up the permit stage and allowing for repositioning or replacement of any obstacles along the way.

intervento con paratia di micropali / Intervento ponte

The oversize convoy path along 40 km route, with more than 100 adjustment points, has not found issues or conflcits with any obstacles along the path geometry (Fig.10, 11), showing the reliability of AutoTURN® for projects of this kind.

particolare manovre su ponte
Fig.10 - particolare manovre su ponte

transito mezzo
Fig.11 - transito mezzo
Project Pricing

Project Pricing

A P MOLLER Group's acquisition of MARTIN BENCHER set to trigger pricing challenges for many project forwarders globally The process of forward integration by Major Shipping lines is slowly affecting many small and medium Forwarders. Many

Read more ...

Gati Shakti National Master Plan - Fast Tracking Infra Development

Gati Shakti National Master Plan - Fast Tracking Infra Development

Gati Shakti is a digital backbone on which infrastructure projects planned by the government under the ₹110 trillion National Infrastructure Plan (NIP) will be implemented by 2025. It provides an institutional framework

Read more ...

Chardham Tunnel Project

Chardham Tunnel Project

Equipment with cutting edge technologies is making tunneling smoother at RVNL’s mega railway project and helping contractors overcome geological complexities. Sandvik’s DT 821 C and DT 922i advanced automatic

Read more ...

India’s Metro-Rail Industry Expanding Fast

India’s Metro-Rail Industry Expanding Fast

The Metro-Rail segment in India is growing at a frantic pace with positive long-term prospects, supported by the impetus provided by the government by way of business-friendly policies and financial support. Use of advanced

Read more ...

Lucknow Metro - The Fastest Built Metro Rail Project

Lucknow Metro - The Fastest Built Metro Rail Project

Lucknow Metro has achieved the distinction of becoming the fastest built metro rail project in the country - both in terms of completion of construction work and execution. On 25th November 2013, LMRCL

Read more ...

Ropeways - Alternative Mobility Solution in Urban India

Ropeways - Alternative Mobility Solution in Urban India

India received its first mode of modern transportation in 1853 when the first railway line was laid from Bombay to Thane to boost industrial activities and ensure easy accessibility to heavy raw materials. In the following

Read more ...

India’s Tunnelling Industry Opportunities & Challenges

India’s Tunnelling Industry Opportunities & Challenges

The growth of the tunnel construction in the country has been driven by a robust pipeline of projects and investments in setting up hydropower projects, developing urban mass rapid transit systems, improving road

Read more ...

Klang Valley Mass Rapid Transit Putrajaya Line in Malaysia

Klang Valley Mass Rapid Transit Putrajaya Line in Malaysia

Stoked by their debut success with the timely completion of Kajang Line’s underground section, Gamuda Engineering found themselves pitted once more against the unique challenges of tunnelling in Kuala Lumpur

Read more ...

Sandvik DT 821C Tunneling Jumbo Setting a New Standard in Speed & Precision

Sandvik DT 821C Tunneling Jumbo Setting a New Standard in Speed & Precision

A tunnelling project is a race against time and costs. Getting it right from the very beginning requires knowledge, skill and experience, as well as a proper range of equipment that fulfils the customer’s tunnelling

Read more ...

German manufacturer GHH brings special Shotcreting Machine to help complete Mumbai Nagpur Expressway

German manufacturer GHH brings special Shotcreting Machine to help complete Mumbai Nagpur Expressway

The Mumbai-Nagpur Expressway is delayed until 2022. In the meantime, a machine ‘GHH IS26’ with remarkable reliability has been specially flown in from the supplier and is in operation to help complete the project

Read more ...

CRCHI’s EPB TBM ‘Victory’ Achieves New Records in Construction of Moscow Metro

CRCHI’s EPB TBM ‘Victory’ Achieves New Records in Construction of Moscow Metro

The project, located at the riverside of the Moscow River, passes under heavy traffic and crowded buildings. It includes two sections of a total length of 2947m. One is from Maple Avenue Station to No.2 Working Shaft

Read more ...

Pull Force

Pull Force

Pull Force is the force that a truck or prime mover can exert onto a transporter or any type of trailer. It has been a subject of much controversy and misunderstandings as truck manufacturers and end-users often do not talk

Read more ...

Fully Automated Jumbo Revolutionizing Tunneling in India

Fully Automated Jumbo Revolutionizing Tunneling in India

The first Sandvik DT922i, a computer controlled fully automatic tunneling jumbo, has been introduced by Sandvik Mining and Rock Technology in India with a vision to achieve high levels of safety, productivity and

Read more ...

HDD Machines Best Suited for Gas, Cable, and Sewerage  Pipeline Projects

HDD Machines Best Suited for Gas, Cable, and Sewerage Pipeline Projects

Horizontal Directional Drilling is a technology in pipe and utility installation that allows greater accuracy and flexibility in placement and ends the need for costly digging, large crews, road closures and other

Read more ...

Progress Maschinen & Automation: Reinforcing cages for tunnel construction and wind-energy solutions

Progress Maschinen & Automation: Reinforcing cages for tunnel construction and wind-energy solutions

Special knowledge is required for building tunnels and wind energy plants in order to implement demanding projects. The facilities and manufacturing processes required for such projects can be adjusted well in advance for

Read more ...

Tunnelling for Science - Special formworks from Doka for tunnel system at CERN

Tunnelling for Science - Special formworks from Doka for tunnel system at CERN

The Large Hadron Collider (LHC) at CERN is the biggest particle accelerator in the world – and growing. To equip the LHC for new, more ambitious experiments in the next decade, the accelerator is currently

Read more ...

Proven Technology in Use

Proven Technology in Use

The river has its source at over 3000 meters high in the snow-covered Andes. It reaches the Pacific Ocean after 250 km. On its way, it overcomes a considerable gradient and is, therefore, ideally suited to generate electricity

Read more ...

CREG: Distinctive Amongst Peers

CREG: Distinctive Amongst Peers

Tan Shunhui, Chairman, CREG, discusses the competitive advantages of the company’s tunneling equipment and solutions, emerging opportunities in developing countries, factors driving its growth and success across

Read more ...

CRCHI TBM at work in Hangzhou Genshan East Road Crossing River Tunnel

CRCHI TBM at work in Hangzhou Genshan East Road Crossing River Tunnel

15-meter mega Slurry TBM rolled off the assembly line at CRCHI. The excavation diameter of the equipment is 15.01 m, its total length is about 130 m, total weight is about 4300 t, installed power is about 9755 kW, rated

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.