Lucknow Metro - The Fastest Built Metro Rail Project

Lucknow Metro has achieved the distinction of becoming the fastest built metro rail project in the country - both in terms of completion of construction work and execution.

Lucknow Metro Map
On 25th November 2013, LMRCL (now UPMRCL) was incorporated as a Special Purpose Vehicle (SPV) under the Companies Act, 1956. While the construction of Phase-IA i.e. North-South Corridor’s Priority Section (Transport Nagar to Charbagh) was completed ahead of schedule, the balance section of the North-South corridor was also completed in a record time.

The construction of ‘Priority Section’ of phase-IA started on 27th September 2014 was completed in a record time of less than 3 years and the first trial runs were conducted on 01/12/2016. Metro train operations on this Priority Section, which was developed on an 8.5 km stretch, was flagged off on 05th September 2017. The balance section had 13 stations in which 9 were elevated and the remaining 4 were in the underground section.

The construction work for the balance section comprising 10.94 km of elevated and 3.45 km underground network (Chaudhary Charan Singh Airport to Munshipulia Metro Station) started on 20th October 2016 and was completed on 23rd February 2019, way ahead of the deadline set in April 2019.The complete stretch of the North-South corridor from CCS Airport to Munshipulia was inaugurated by the Hon’ble Prime Minister on 8th March 2019.
Shri. Kumar Keshav, MD, Uttar Pradesh Metro Rail Corporation Limited
The Lucknow Metro has achieved the distinction of being the fastest-ever executed metro project in the country, as the entire project has been completed in just four and half years. Other contemporary Metro projects in the country have not been able to match up with the speed of deliverance as shown by UPMRCL’s strength in project execution. The Lucknow Metro is indeed the pride of the city.

Shri. Kumar Keshav, MD, Uttar Pradesh Metro Rail Corporation Limited

Planning & Execution
With detailed planning and execution strategies, the project was completed in a record time of 4.5 years, the fastest in the country. Efficient project management has been the prime reason for the success of the project. Regular monitoring and stringent follow-ups ensured that every aspect of the construction activity was carried out with perfection. The project received unwavering support from the central and state governments. This has been a significant reason for the success of Lucknow Metro.

Taking a cue from the availability of traffic-free roads at night, it was decided that the majority of the on-site construction and erection would take place in the after-hours. This had a positive impact on the speed at which the work was completed.

Utility identification proved to be a challenge. The entire city had already been utilized for civic infrastructure facilities. The old city area had a high water level which created difficulties in underground construction. The roads in those areas were congested and traffic management became a core issue. Traffic diversion was a challenge because substitute routes were needed to ease the problems. The UPMRC team had to widen some footpaths, remove electrical poles, cables & also shift some water pipelines and sewer lines. With efficient management, it was ensured that the public did not face any trouble.
  • During the construction phase of underground section, 4.5 lakh tonnes of mud was removed to make tunnels. A total number of 2321 piles were erected during the construction phase which included 541 pile caps as well.
  • 21 different types and sizes of steel spans were constructed in this project like 60 m steel span (near Nishatganj flyover) and 45 m steel spans (one beside Hotel Clark Awadh and four in Indira Nagar, in proximity to HAL). Apart from this, the 541 piers, 262 pier caps and 39 cantilever pier caps were also erected successfully.
  • The most remarkable achievement was the erection of curved U-girders near IT intersection for the first time by Lucknow Metro Project team.
  • The erection of I-girders near the polytechnic intersection was also difficult due to traffic congestion in the area.
  • A total number of 634 U-girders were erected on the elevated stretch of the North-South corridor from KD Singh Stadium to Munshi Pulia. These U-girders are 27 m long and 4.1 m wide, weighing around 150 tonnes.
The major challenges like erection of 225 m long balanced cantilever span at Mawaiya railway crossing with operational Indian railways lines beneath, erection of 60 m special steel span at Awadh rotary, 177 m long balanced cantilever bridge on Gomti river and another 60 m special steel span at Nishatganj (constructed in just 5 days), were overcome by strategic planning and careful execution by the dedicated team of engineers under the fine leadership of Managing Director Shri Kumar Keshav.

UPMRCL worked in a dedicated and planned manner. They issued multiple contracts to avoid delay. Contractors were monitored effectively and provided assistance to help with the delivery of the work on time and as per budget. Most of the contracts were divided among various companies so that timely delivery of work could be ensured. The corporation ensured timely payments to the vendors to keep them motivated.

Despite the pace at which the construction took place, UPMRC ensured to keep the city’s values, ethnicity, culture, and environment intact. The same was achieved by adopting a blend of construction methodologies as per the geological profile of different areas to avoid making changes to the landscape. Pre-cast twin U-Girders, Underground stations constructed through Cut and Cover Methodology, Bridges erected by Push launching technology and balanced cantilever bridges stand tall as a fine example of this strategic mix.

UPMRC also made sure that the green cover of the city remains intact and more and more green practices were adopted during the construction phase. Around 410 trees were transplanted (pulled along with the roots and relocated elsewhere) and altered the route map’s design at certain places to save over 500 trees. UPMRC also took steps towards waste reduction and use of renewable resources (Solar panels installed at Transport Nagar).

To keep the city’s roads clean, a wheel washing plant was installed at construction sites and every loading-unloading vehicle that moved out of the construction site was made to pass through the wheel washing plant. Only after the dirt-packed wheels were washed and cleansed off the construction mud, the vehicles moved outside the construction site onto the city roads.

During the construction phase of Lucknow Metro, weekly media briefings were conducted at its administration office every Wednesday. The Managing Director along with the directors updated media on the development of the week and plans for the next week. This regular update left no space for speculations. Media queries were regularly answered and this proved helpful in avoiding the situation of crisis or misinformation amidst the public.

All important information, progress updates, challenges, milestones, success and achievements were strategically communicated to the media which helped UPMRC to gain trust and ensured public support through positive image building and news coverage. Public confidence was gradually built by instilling a sense of ownership towards their own Lucknow Metro.

Various awareness and stakeholders engagement activities were performed and partnerships were created with RWAs, Traders associations, NGOs and other stakeholders to engage in dialogue and seek solutions to any problem that arose. This ensured no roadblocks from people and associations.
60 Metrespecial Steelspan
Lucknow Metro - The Fastest Built Metro Rail Project

At Awadh Rotary, Lucknow Metro has launched a 60-meter special steel span bridge crossing the rotary over a statue in the middle of the rotary. This bridge which has been built at a height of approximately 13 meters above the ground connects both the ends of the Metro viaduct to provide a special seamless connectivity for Metro train operations.

The decision to erect a steel span was taken so that the statue beneath wasn’t affected and the beauty of the intersection wasn’t compromised. What’s interesting is that not a single day’s traffic was interrupted during this span’s erection.

First U Girder Erection in Between K.D. Singh Babu Stadium – Munshi Pulia Elevated Stretch
Lucknow Metro - The Fastest Built Metro Rail Project

27 metre long and 4.1 metre wide U-girder weighing around 150 tonnes was lifted through two cranes of 400 tonnes and 350 tonnes to fix over the viaduct.

Special Balanced Cantilever Span
Lucknow Metro - The Fastest Built Metro Rail Project

A special balanced cantilever span of 255 meters (central span 105 meters; end spans of 75 meters each) was one of the most challenging and critical tasks which was erected at a height of 21.5 meters above the ground level while passing over 12 functional Indian railway tracks at a height of 15.2 meters under extremely difficult situations. The task was completed without affecting Indian railways train operations beneath, even for a single day. It is one of the rarest feats achieved for any Metro project in the country.

Diaphragm Wall
Lucknow Metro - The Fastest Built Metro Rail Project

A total number of 130,120,122 diaphragm walls were installed in Hussainganj, Sachivalaya and Hazaratganj Metro Station. These walls were constructed in panels to a depth of about 22 meter using construction machinery like Hydraulic rig with inbuilt control mechanism and cranes. It also helps in safe and speedy construction work of the underground section.

Lucknow Metro - The Fastest Built Metro Rail Project

Lucknow Metro - The Fastest Built Metro Rail Project

Lucknow Metro - The Fastest Built Metro Rail Project

Sources

http://spsingla.com/?projects=balanced-cantilever-bridge-at-mawaiya-railway-crossing-on-north-south-corridor-of-lucknow-metro-at-lucknow
https://timesofindia.indiatimes.com/city/lucknow/lucknow-metro-completes-over-80-of-metros-gomti-bridges-civil-work/articleshow/65222418.cms
https://orissadiary.com/tata-projects-sets-new-benchmark-completes-first-part-metro-tunneling-lucknow-record-time/
https://www.nbmcw.com/articles-reports/building-construction-material/precast-construction/precast-segmental-lining-for-underground-tunnels.html
Project Pricing
A P MOLLER Group's acquisition of MARTIN BENCHER set to trigger pricing challenges for many project forwarders globally The process of forward integration by Major Shipping lines is slowly affecting many small and medium Forwarders. Many

Read more ...

Gati Shakti National Master Plan - Fast Tracking Infra Development
Gati Shakti is a digital backbone on which infrastructure projects planned by the government under the ₹110 trillion National Infrastructure Plan (NIP) will be implemented by 2025. It provides an institutional framework

Read more ...

Chardham Tunnel Project
Equipment with cutting edge technologies is making tunneling smoother at RVNL’s mega railway project and helping contractors overcome geological complexities. Sandvik’s DT 821 C and DT 922i advanced automatic

Read more ...

India’s Metro-Rail Industry Expanding Fast
The Metro-Rail segment in India is growing at a frantic pace with positive long-term prospects, supported by the impetus provided by the government by way of business-friendly policies and financial support. Use of advanced

Read more ...

Ropeways - Alternative Mobility Solution in Urban India
India received its first mode of modern transportation in 1853 when the first railway line was laid from Bombay to Thane to boost industrial activities and ensure easy accessibility to heavy raw materials. In the following

Read more ...

India’s Tunnelling Industry Opportunities & Challenges
The growth of the tunnel construction in the country has been driven by a robust pipeline of projects and investments in setting up hydropower projects, developing urban mass rapid transit systems, improving road

Read more ...

Klang Valley Mass Rapid Transit Putrajaya Line in Malaysia
Stoked by their debut success with the timely completion of Kajang Line’s underground section, Gamuda Engineering found themselves pitted once more against the unique challenges of tunnelling in Kuala Lumpur

Read more ...

Sandvik DT 821C Tunneling Jumbo Setting a New Standard in Speed & Precision
A tunnelling project is a race against time and costs. Getting it right from the very beginning requires knowledge, skill and experience, as well as a proper range of equipment that fulfils the customer’s tunnelling

Read more ...

German manufacturer GHH brings special Shotcreting Machine to help complete Mumbai Nagpur Expressway
The Mumbai-Nagpur Expressway is delayed until 2022. In the meantime, a machine ‘GHH IS26’ with remarkable reliability has been specially flown in from the supplier and is in operation to help complete the project

Read more ...

CRCHI’s EPB TBM ‘Victory’ Achieves New Records in Construction of Moscow Metro
The project, located at the riverside of the Moscow River, passes under heavy traffic and crowded buildings. It includes two sections of a total length of 2947m. One is from Maple Avenue Station to No.2 Working Shaft

Read more ...

Pull Force
Pull Force is the force that a truck or prime mover can exert onto a transporter or any type of trailer. It has been a subject of much controversy and misunderstandings as truck manufacturers and end-users often do not talk

Read more ...

Fully Automated Jumbo Revolutionizing Tunneling in India
The first Sandvik DT922i, a computer controlled fully automatic tunneling jumbo, has been introduced by Sandvik Mining and Rock Technology in India with a vision to achieve high levels of safety, productivity and

Read more ...

HDD Machines Best Suited for Gas, Cable, and Sewerage  Pipeline Projects
Horizontal Directional Drilling is a technology in pipe and utility installation that allows greater accuracy and flexibility in placement and ends the need for costly digging, large crews, road closures and other

Read more ...

Progress Maschinen & Automation: Reinforcing cages for tunnel construction and wind-energy solutions
Special knowledge is required for building tunnels and wind energy plants in order to implement demanding projects. The facilities and manufacturing processes required for such projects can be adjusted well in advance for

Read more ...

Tunnelling for Science - Special formworks from Doka for tunnel system at CERN
The Large Hadron Collider (LHC) at CERN is the biggest particle accelerator in the world – and growing. To equip the LHC for new, more ambitious experiments in the next decade, the accelerator is currently

Read more ...

Proven Technology in Use
The river has its source at over 3000 meters high in the snow-covered Andes. It reaches the Pacific Ocean after 250 km. On its way, it overcomes a considerable gradient and is, therefore, ideally suited to generate electricity

Read more ...

CREG: Distinctive Amongst Peers
Tan Shunhui, Chairman, CREG, discusses the competitive advantages of the company’s tunneling equipment and solutions, emerging opportunities in developing countries, factors driving its growth and success across

Read more ...

CRCHI TBM at work in Hangzhou Genshan East Road Crossing River Tunnel
15-meter mega Slurry TBM rolled off the assembly line at CRCHI. The excavation diameter of the equipment is 15.01 m, its total length is about 130 m, total weight is about 4300 t, installed power is about 9755 kW, rated

Read more ...

Open-type TBM produced by CRCHI creates a new record in China
Being the longest water delivery line in the history of Jilin province, transferring water from Songhua River into Central Jilin Province will transfer the largest capacity of water and cover the largest areas. The water diversion

Read more ...