Anuj Dayal, Executive Director-Corp Comm, DMRC

Delhi Metro’s Underground Revolution

The Delhi Metro’s underground construction in its third phase of expansion cannot be considered anything short of a revolution. Close to 80 kilometres of underground tunnels have been laid beneath the city in the last five years without causing any disruption to the din and bustle of the daily life above.

The sheer enormity of the task can be gauged from the fact that, the total length of the underground corridors in Delhi Metro’s Phase-3 is more than the total underground sections built by DMRC in both Phases 1 and 2, making it one of the most challenging construction phases for the organization.

Combining the first two phases, Delhi Metro has a total of 31 underground stations, while Phase-3 alone has 35 underground stations. The total length of the underground corridors in the first two phases was 48.06 kilometres and Phase-3 alone has underground corridors of 54 kilometres. The first phase of Delhi Metro’s construction had 13.17 kilometres of underground Metro lines while the second phase had 34.89 kilometres.

The decision to construct more underground corridors was taken to ensure that the construction work caused minimum inconvenience to the people. By constructing so many underground stretches, DMRC has also avoided causing any damage to the existing infrastructure such as flyovers and roads.

For the first time in the history of Delhi Metro’s construction, four different tunneling stretches in Phase-3 have passed below existing underground Metro stretches in the city. These four underground stretches are:
  • Tunnel between Sarojini Nagar to INA on the Majlis Park – Shiv Vihar corridor below the underground section of the Samaypur Badli – HUDA City Centre line at INA.
  • Tunnel between Indira Gandhi Domestic Airport (T1D) to Vasant Vihar on the Janak Puri West – Botanical Garden corridor below the underground section of the Airport Express Link near the Indira Gandhi International Airport (Domestic terminals).
  • Tunnel between Mandi House to ITO on the Escorts Mujesar – Kashmere Gate Corridor below the underground section of the NOIDA – Dwarka corridor (Blue Line) at Mandi House.
  • Tunnel between Hauz Khas and Panchsheel Park on the Janakpuri West – Botanical Garden corridor below the already operational HUDA City Centre – Samaypur Badli section at Hauz Khas.
Details of underground stretches (in a nutshell):
Phase 3 54 kilometres
Corridors Underground length (in kms.) Underground stations
Majlis Park – Shiv Vihar 19.117 12
Janakpuri West – Kalindi Kunj 23.807 15
Central Secretariat -Kashmere Gate 9.370 7
Dwarka – Najafgarh 1.541 1

Phase 1 and 2

Undergound length (in kms.)

Underground Stations

Phase 1

13.17

13

Phase 2

34.89

18


Tunneling Process

Tunneling Process

Most of the tunneling was done using Tunnel Boring Machines. A record 30 TBMs were pressed into service to complete the work. It is indeed rare to come across the use of so many TBMs within one urban centre anywhere in the world. In Phase 2, 14 TBMs had been used but this time the number had to be more than doubled.

There were also stretches where it was not possible to use TBMs. For example, at Kalkaji Mandir, the New Austrian Tunneling Method (NATM) was used to carry out tunneling work for a stretch of 176 metres.

The tunnel between Kalkaji Mandir and NSIC Okhla passes below piers 135 and 136 of the operational violet line and the distance between the two piers was 28 mtrs. It would have been impossible to construct twin tunnels within such a short space. Therefore, a decision was taken to construct a single tube twin tunnel through which both the tracks will pass using the NATM technology. In another stretch at Kashmere Gate, NATM was used for a stretch of a 12 metre long tunnel.

Monitoring during tunneling work

DMRC has always laid great stress on ensuring that its construction activities cause minimum inconvenience to the general public. During the tunneling work of Phase-3, detailed instrumentation was done at various locations to monitor the condition of buildings and other structures above.

In areas such as Old Delhi, stretches where the tunnels were passing below already operational Metro tunnels or beneath flyovers and bridges, DMRC’s engineers had to be very careful. Various equipment for monitoring the movement of the TBMs were installed such as settlement markers, inclinometers, bi-reflex targets etc. Exhaustive building condition surveys were also conducted at all major locations for the same.

DMRC Tunneling Process

Mass Spring Systems (MSS)

A decision was also taken to install Mass Spring Systems in the tunnels to mitigate vibrations generated from tunnels during the passing of trains. Mass Spring System (MSS) is the solution which helps mitigate vibrations generated by the passing trains at the source itself.

MSS elastically separates the tracks slabs in the tunnels or on the viaducts from the supporting structure. The material used for isolation is a microcellular Polyurethane Elastomer (e.g.- Sylomer from Getzner- Austria). Use of MSS helps in minimizing the transmission of vibrations (structure-borne noise) to the surrounding establishments in the vicinity of tracks. In addition, MSS also effectively reduces the development of audible secondary airborne noise caused by the vibration of buildings and other infrastructure components.

Mass Spring Systems (MSS)

Social Outreach:

Wherever the Delhi Metro carried out construction work, it engaged with the people through numerous Community Interaction Programmes. In these programmes, DMRC’s detailed construction plans were discussed with the residents of the area and all possibilities of road diversions, temporary or permanent displacements etc were deliberated upon. With such initiatives, DMRC could win the trust of the people and progress smoothly with its construction work.

Conclusion

Underground construction has its challenges irrespective of where it is carried out. However, if the construction takes place in a city with close to 20 million people, the challenges simply multiply. Constructing over 50 kilometres of underground lines in Delhi was a major challenge with innumerable buildings and structures in precarious conditions. However, DMRC’s engineers showed great commitment and presence of mind in ensuring that the work could be completed without any major hindrance.
Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
Equipment with cutting edge technologies is making tunneling smoother at RVNL’s mega railway project and helping contractors overcome geological complexities. Sandvik’s DT 821 C and DT 922i advanced automatic

Read more ...

The Metro-Rail segment in India is growing at a frantic pace with positive long-term prospects, supported by the impetus provided by the government by way of business-friendly policies and financial support. Use of advanced

Read more ...

Lucknow Metro has achieved the distinction of becoming the fastest built metro rail project in the country - both in terms of completion of construction work and execution. On 25th November 2013, LMRCL

Read more ...

India received its first mode of modern transportation in 1853 when the first railway line was laid from Bombay to Thane to boost industrial activities and ensure easy accessibility to heavy raw materials. In the following

Read more ...

The growth of the tunnel construction in the country has been driven by a robust pipeline of projects and investments in setting up hydropower projects, developing urban mass rapid transit systems, improving road

Read more ...

Stoked by their debut success with the timely completion of Kajang Line’s underground section, Gamuda Engineering found themselves pitted once more against the unique challenges of tunnelling in Kuala Lumpur

Read more ...

A tunnelling project is a race against time and costs. Getting it right from the very beginning requires knowledge, skill and experience, as well as a proper range of equipment that fulfils the customer’s tunnelling

Read more ...

The Mumbai-Nagpur Expressway is delayed until 2022. In the meantime, a machine ‘GHH IS26’ with remarkable reliability has been specially flown in from the supplier and is in operation to help complete the project

Read more ...

The project, located at the riverside of the Moscow River, passes under heavy traffic and crowded buildings. It includes two sections of a total length of 2947m. One is from Maple Avenue Station to No.2 Working Shaft

Read more ...

Pull Force is the force that a truck or prime mover can exert onto a transporter or any type of trailer. It has been a subject of much controversy and misunderstandings as truck manufacturers and end-users often do not talk

Read more ...

The first Sandvik DT922i, a computer controlled fully automatic tunneling jumbo, has been introduced by Sandvik Mining and Rock Technology in India with a vision to achieve high levels of safety, productivity and

Read more ...

Horizontal Directional Drilling is a technology in pipe and utility installation that allows greater accuracy and flexibility in placement and ends the need for costly digging, large crews, road closures and other

Read more ...

Special knowledge is required for building tunnels and wind energy plants in order to implement demanding projects. The facilities and manufacturing processes required for such projects can be adjusted well in advance for

Read more ...

The Large Hadron Collider (LHC) at CERN is the biggest particle accelerator in the world – and growing. To equip the LHC for new, more ambitious experiments in the next decade, the accelerator is currently

Read more ...

The river has its source at over 3000 meters high in the snow-covered Andes. It reaches the Pacific Ocean after 250 km. On its way, it overcomes a considerable gradient and is, therefore, ideally suited to generate electricity

Read more ...

Tan Shunhui, Chairman, CREG, discusses the competitive advantages of the company’s tunneling equipment and solutions, emerging opportunities in developing countries, factors driving its growth and success across

Read more ...

15-meter mega Slurry TBM rolled off the assembly line at CRCHI. The excavation diameter of the equipment is 15.01 m, its total length is about 130 m, total weight is about 4300 t, installed power is about 9755 kW, rated

Read more ...

Being the longest water delivery line in the history of Jilin province, transferring water from Songhua River into Central Jilin Province will transfer the largest capacity of water and cover the largest areas. The water diversion

Read more ...

Amit Kaul, BASF India Limited (Construction Chemicals Division), India, tells about the innovative tunnel lining system and related design aspects, and also describes the main advantages of this lining system in comparison

Read more ...

Underground infrastructures are an integral part of modern cities as they serve to counter problems of surface congestion and environmental degradation. The problems of ground vibrations, vibration induced noise and ground

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.