Use of Geosynthetic Material For Reinforced Earthwall Construction

Reinforced earth retaining wall is comparatively a new construction technique. Due to its simplicity, economy and faster pace of construction, several such retaining walls have been constructed all over the world and this technique has almost replaced the conventional reinforced concrete and gravity retaining walls. To reduce the congestion on National Highway-2 at the crossing of Kalindi Kunj near Sarita Vihar, New Delhi, a flyover was constructed along Badarpur-Ashram direction. The construction of approach road was carried out with reinforced retaining wall with friction polymeric ties (geosynthetic material) as reinforcement material. Instead of conventional earth, pond ash from the nearby Badarpur thermal power plant was used as backfill material. The paper discusses the properties of geosynthetic reinforcement ; backfill material, design details and the methodology adopted for construction of reinforced approach embankment. Conclusions have been drawn about the suitability of geosynthetic material as a reinforcement and pond ash as a backfill material for the retaining wall.

Vasant G Havanagi, Principal Scientist

Anil Kumar Sinha, Scientist and Sudhir Mathur, Chief Scientist and Head (GTE), Central Road Research Institute, New Delhi.

Introduction

Large scale infrastructural development is going on in the country under different programmes viz. National Highway Development Program (NHDP), State Road Development programmes etc. Road development activities are also going on for decongestion of urban areas in different states. In all these construction activities, to have smooth movement of traffic especially at intersections, flyovers are built along one feasible direction. The approaches of the flyovers have to be built by economical design and construction by suitable technique. Geosynthetics are relatively new road construction materials which have potential for such applications (Mandal JN ,1987, Elias, V.et.al 2001). PVC coated polyester geogrid was used for the construction of reinforced approach road of DND flyover connecting Delhi-Noida Road (Jimmy T. and Pawan T, 2008). Huabei Lie and Myoung-Soo Won (2009) advocated different parameters which have to be considered for economic design of geosynthetic reinforced soil retaining wall. Conventional earth is normally used as a backfill material. Pond ash which is a waste from thermal power plant has a potential for use as an alternative material for the backfill (Mathur etal., 2003, Yudbir and Honjo,Y.,1991, Martin,J.P, 1990, Digioia, A.M and Brendel, G.F,1998).

In the present study, vertical retaining walls are built along the approaches of a flyover using geosynthetic material as reinforcement. The technique known as ‘Reinforced earth technique’ which not only saves the costly available land but also helps to decongest the intersection area. The paper discusses the utility of geosynthetics in the form of ‘friction ties’ as a reinforcement material. Pond ash was also investigated for its suitability as a backfill material instead of conventional earth.

Salient Features of Reinforced Earth Wall

To avoid decongestion at the intersection point of Kalindi Kunj road and NH-2 at Sarita Vihar, New Delhi, it was decided to construct a flyover with two carriageways each having a width of 11.25 m, with 3 lanes on each side. It was also decided that approach road of this flyover will be constructed using reinforced retaining wall. For the purpose of reinforcement, polymeric strips i.e. friction ties (commercially known as KOLOTIES) were used. The salient features of the Sarita Vihar reinforced earth wall are given in Table 1. During construction, pond ash was used as a back fill material instead of the good earth due to economic considerations.

Materials Used in Reinforced Earth Wall

Pond ash was used as a backfill material instead of conventional earth as a backfill material. Geosynthetic friction ties were used as reinforcements. The properties of backfill material and reinfor- cements are briefly discussed below.

Backfill

Table - 1 Salient features of Reinforced Earth Wall
Length of Reinforced wall 105 m (Badarpur site)78 m (Delhi side)
Height 5 m (max.)
Width 22.5 m
Allowable bearing capacity of subsoil 170 kN/sq.m
Fill Material Pond Ash
Reinforcement Friction ties made of high tenacity polyester yarns (KOLOTIES)
Facing panel 180mm thick precast RCC panel

Pond ash was used as a back fill material for the construction of reinforced earth retaining wall and abutment as per British Standard BS 8006-1995 ‘Code of Practice for Strengthened/Reinforced Soils and Other Fills’. Pond ash was procured from the Badarpur thermal power plant, New Delhi and was investigated for its geotechnical characteristics in the laboratory. Pond ash is a non plastic coarse grained material. The angle value for angle of internal friction varied in the range of 32°-34°. Therefore, there is a possibility of development of interfacial friction between the backfill and the reinforcement. It has high coefficient of permeability (K in the range of 10-6 to 10–7 m/sec). The maximum dry density of pond ash when tested as per IS: 2720 (Part 8)-1983, was found to be in the range of 11kN/m3 to 13 kN/m3 and OMC in the range of 30 to 32%.

Reinforcing material

The reinforcing geosynthetic material that was used is called friction ties (commercially known as KOLOTIES). Two type of friction ties, having ultimate tensile strength of 50 Tones (designated as KT50) and 30 Tones (designated as KT30) were used. The friction ties are composed of high tenacity polyester yarns and can undergo deformation to the extent of 10 to 12% without failure.

Characterisation of Reinforcing Materials

The friction ties which were used as reinforcements were tested for their tensile strength, creep resistance, pull out strength, chemical, temperature, biological and installation resistance as per ASTM standards. The brief details of the same are given below:

Tensile strength

The ultimate tensile strength and per cent elongation was tested as per ASTM D 4595. The results are shown in Table 2.

Table 2 Tensile strength of friction ties
Property/Type KT30 KT50
Tensile Strength (kN/m) 35.0 56.6
Elongation (%) 10.4 11.2

Creep resistance

Long-term creep resistance was tested according to ASTM D 5262 at elevated temperature of 62°C and at relative humidity between 50 and 70%. Creep rupture curves covering 65,700 hrs were drawn and extrapolated to 100 years of design life. For Kolotie, 73% strength retention for 100 years design life was obtained, which roughly corresponds to partial creep factor of 1.35.

Pull out test

In order to determine the friction between pond ash and friction ties, pull out test (as per Japanese Civil Engineering Society Recommen- dations) was conducted and it was found that friction resistance of pond ash-Koloties was 31°.

Chemical resistance

In order to determine the resistance of Koloties against chemical reaction, the samples of ties were immersed in the chemical solution of HCL and NaOH of different pH value and at different temperatures based on recommendation of ASTM D 543. Comparison of tensile strength before and after immersion was made. The test was conducted as per ASTM D 5322. It was concluded from the test that the reduction in tensile strength at 23°C was below 5 percent for all solutions. However, reduction rate of tensile strength at 50°C was above 20% for strong alkali solution. The decrease in the strength properties was due to hydrolysis of polyester yarns by penetration of alkali solution. It is, therefore recommended that the long-term allowable design loads shall be decided after special consideration of chemical degradation when pH value is higher than 9 in soils.

High and low temperature resistance test

Friction ties are susceptible to high and low temperature conditions of the environment. Its behaviour needs to be predicted by conducting laboratory tests. The resistance of friction ties to high and low tempe- rature conditions was tested as per ASTM D 4594 & ASTM D 5322 and ASTM D 4594 respectively. It was observed that tensile strength of Koloties reduced in the range 2.43% - 3.5% and 12.6% - 15.1% respectively.

Biological resistance test

The friction ties are used with different types of filling materials having different biological charact- eristics. The resistance to biological degradation was determined by conducting laboratory tests. It was observed that tensile strength decre- ases by about 3.0%. Therefore, biological degradation may be neglected.

Installation resistance test

Friction ties are susceptible to damage during handling and compaction of backfill material. The susceptibility to damage is tested by conducting installation resistance test as per ASTM D5818.

a) External wall height 1m to 4.6 m
b) Batter of wall face 90°
c) Slope angle of soil surface 0
d) External traffic loads 24 kN/sq.m
e) Type of facia Precast RCC panels
f) Vertical spacing of reinforcement, Sv 0.575 m
g) Width of approach 25.50 m
h) Cohesion of the backfill material 0
i) Angle of internal friction of the backfill material 31°
j) Unit weight of backfill 11 kN/m2
k) Bearing capacity of subsoil 170 kN/m2
l) Partial factor for pull out resistance 1.3
m) Reinforcing Material Geosynthetic friction ties
n) Ultimate Tensile Strength of tie 50 kN/m2
o) Coefficient of friction between reinforcing material and fill 0.80
p) Width of reinforcing strip 0.09 m

Facing Panels

Facing panels of the Reinforced Earth Wall were made of panels of predetermined size. They were made of 180 mm thick precast RCC panels of M 35 grade concrete. The size of the facing panels was decided considering the weight, the total height to be covered, ease of handling and provision to provide at least one or two reinforcing elements.

Design Calculations For Reinforced Earth Retaining Wall

The input parameters, which were used for the design of reinforced wall were;

Partial factors

In order to design the reinforced earth wall, ultimate limit state principles as stated in BS 8006: 1995 were adopted. The ultimate limit states are associated with collapse or other similar form of structural failure. These states are attained for a specific mode of failure when disturbing forces equal or exceed restoring forces. Margins of safety, against attaining the limit state of collapse are provided by the use of partial material factors and partial load factors. Limit state design for reinforced earth employs four principal partial factors all of which assume prescribed numerical values of unity or greater. Disturbing forces are increased by multiplying by prescribed load factor to obtain design loads. Restoring forces are decreased by dividing the prescribed material factors to obtain design strengths. Two of these are load factors ff and ffc applied to dead loads, and factor fq applied to the live loads. The third principal material factor is denoted as fm and fms. The fourth factor fn accounts for the economic ramification of failure. This factor is employed in addition to material factor to produce reduced design strength. The values of various partial factors are used as per BS 8006:1995.

Symbol Description Value
ffs Partial load factor for safety 1.50
fq Partial load factor for traffic loading 1.30
fm Partial material factor 1.20
fms Partial material factor
fm11 x fm12 x fm21 x fm22
 
Where,
fm11 = A factor to cover the possible reductions in the capacity of the materials as a
whole compared with the characteristics value derived from the control test.
1.0
fm12 = Extrapolation of test data to take account of the confidence of the long term
capacity assessment.
1.0
fm21 = Susceptibility to damage to take account of damage during construction. 1.2
fm22 = Environment factor to take account of different rates of degradation 1.05
fn = Economic ramification factor 1.10
fmc = Material creep partial factor 1.35
Reinforced Earth Wall was designed considering the external and internal stability which have been explained below:

Internal stability

The internal stability deals with the design of reinforcement with regard to its length, cross-section against tension failure and ensuring that it has sufficient anchoring length into the backfill material. For the purpose of internal stability, the reinforcement has to be checked for tension failure and adequacy of anchoring length and stability of wedges inside the fill.

Check for tension failure

i) Rupture/long-term design strength

Td= Tult/( fmc × fm × fn)

Where fmc = material creep partial factor (1.35)

fm = fm11 × fm12 × fm21 × fm22

= 1.0 × 1.0 × 1.20 × 1.05 = 1.26

fn = 1.1

Td50 = 50 / (1.35 × 1.26 × 1.1) = 26.72 t

Td30 = 30 / (1.35 × 1.26 × 1.1) = 16.03 t

ii) Reinforcement length

The reinforcement length of the tie should be at least equal to 0.7H i.e. 0.7 x 4.6 = 3.22 m, however, from conservative consideration, a length of 4.6 m was adopted at a height of 4.6 m.

Force, Fz in a specific layer at depth Z can be calculated as

Fz = Kreq (ffs.g.Z + fq.Ws).Sv

Where,

Ws, External traffic load and Sv, Spacing between the reinforcement

Kreq = 0.32, the estimated value of Fz = 19.71 t

For Ultimate Limit State,

Fz ≤ Td i.e. 19.71 < 26.72, Hence safe

Similarly, iterations may be carried out for different lengths and heights to check the safety.

Check for adherence

Once the maximum value of T has been found, the designer should ensure all the ties/strips have an adequate anchoring length into the resisting zone to prevent pull out failure. Active and passive zones in reinforced earth portion are shown in Fig. 1.

The anchoring length Lej for the reinforcement at depth hj can be determined using the following formula

Where Pj is the total horizontal width of the top and bottom faces of the reinforcing element at the jth layer per meter run.

Tj Long-term design strength

µ Coefficient of friction between fill and reinforcing element.

ffs, ff, fp, fn Partial load factors as already explained.

abc’Adhesion coefficient between soil and reinforcement

c’ Cohesion of soil

fms Partial material factor applied to c’

Calculation for Lej

Lej can be calculated by equation

Lej = L - hjtan (45–Ø / 2)

Let us consider a height of 4.6 m, hJ – 4.6 m

Lej = 4.6 – 4.6tan (45 – 31/2) = 2.3, substituting all the values to get Pj

Pj ≥ 0.0879

But Pj = 0.09 + 0.09 = 0.18 m (Two-way friction)

Since 0.18 m > 0.0879 m

Therefore, adhesion criterion is satisfied.

Hence O.K., Similarly calculations for different heights may be carried out.

External stability

In external stability analysis, it is assumed that the Reinforced Earth Wall is an integral unit and behaves as a rigid gravity structure and conforms to the laws of applied mechanics. The external failure mechanism which was considered in the design are (a) Sliding (b) Overturning (c) Tilting/bearing failure and (d) Slip failure. Different externally applied forces on reinforced earth wall are shown in Fig. 2. The target factor of safety against sliding is 1.5, factor of safety against overturning is 2.0, factor of safety against bearing pressure is 1.0.

Check for safety against sliding

Factor of safety against sliding = Resisting force / Sliding force

Calculation of sliding force

Total design uniform surcharge/live loads(q) = 24 kN/m2

Friction coefficient µ = tan 31° = 0.6008

Reinforcement length, L = 4.6 m

Coefficient of lateral earth pressure Ka = 0.32

S1 = Sliding force due to live load = F1 x Ka , = Ka .q. H

= 0.320 × 24 × 4.6 = 35.328 kN

S2 = Sliding force due to self wt. of soil = 0.5 Ka.γ. H2

= 0.5 × 0.320 × 11 × 4.6 × 4.6 = 37.24 kN

Use of Geosynthetic Material For Reinforced Earthwall Construction Use of Geosynthetic Material For Reinforced Earthwall Construction
Figure 1: Determination of adherence capacity of reinforcement Figure 2: Externally applied forces on reinforced earth wall

Calculation of resisting force

W = Self weight of reinforced zone

= γ.H.L= 11 × 4.6 × 4.6 = 232.76 kN

F.Sslinding = Σ Resisting moment about toe / Σ Overturning moment about toe

(ii) Check for overturning

F.Soverturning = Σ Resisting moment about toe / Σ Overturning moment about toe

(iii) Check for bearing pressure

The typical bearing pressure imposed by a reinforced earth structure on the foundation strata, is shown in Fig.2. For design, bearing pressure is calculated as per Meyerhoff equation.

Where σv max is the factored bearing pressure acting on the base of the wall;

Rv is the resultant of all factored vertical load components (load factors as applicable to each load case)

L = Reinforcement length at the base of the wall

Where Mr and M0 are the resisting and overturning moments respectively

Vq = Surcharge load = q × L = 24 × 4.6 = 110.4 kN

W = Self weight of reinforced zone = γ.H.L= 11 × 4.6 × 4.6 = 232.76 kN

d = (535.35 - 138.35 / 232.6 ) 1.71

e = L/2 - d = 4.6/2 - 1.71 = 0.59

σv max = Rv / (L-2e)

σv max = 232.76 + 110.4 / (4.6-2×0.59) = 100.34 < 170 kN/m2Hence Safe

Similarly, calculations for different heights of backfill and length of reinforcement may be carried out.

Construction Methodology of Reinforced Earth Wall

The construction methodology adopted for reinforced earth wall construction has been briefly explained here.

Construction of foundation block

Use of Geosynthetic Material For Reinforced Earthwall Construction
Figure 3(a): Provision of geotextiles in the space between the facing panels (b) longitudinal drainage

For the construction of foundation for facia panels, a trench of appropriate size was excavated along the proposed line. The bottom 150 mm was concreted with PCC as a leveling pad. The width, depth and reinforcement details were worked out on the basis of loads likely to come on the foundation block.

Erection of facing panels and provision of longitudinal drainage

The facing panels were lifted by a crane and placed over the foundation block from one end. The gap between facia panels and foundation beam was filled with thermocol and closed by bitumen sealant. A drainage bay 300 mm inside (inverted filter) was provided behind the panels and was filled with well-graded material of size 20mm to 0.425 mm. The facing panels were initially set at a batter of approximately 2° to 3° inside from the vertical to take care of the likely outward movement of the facing panel either due to the backfill material at the back of the wall or due to the readjustment and elongation of reinforcing material. A strip of geotextile (Fig.3) was provided at every joint not only to stop the flow of back fill material from the joints but also to ensure the flow of percolated water. Drainage of the backfill is vital for maintaining the friction between reinforcement and the pond ash. Provision made for the drainage behind the reinforced earth wall is shown in Fig.3. Panels were also temporarily supported with the help of steel struts from outside to keep them in position till the pressure is fully taken up by the reinforcing layer.

Laying and compaction of backfill

The fill material (pond ash) was brought by trucks and unloaded at site. The ash was spread over the entire width of the approach embankment with the help of the dozer and tractor and then compacted using vibratory and static rollers as shown in the Fig. 4. However near the facing panel i.e. over a width of 1.5 m the pond ash was compacted using plate compactors (Fig.4). This was done to avoid heavy lateral pressures which may come on the facing panels and may result in the outward movement of the wall. Pond ash was compacted in layers of 100 mm thickness near the facing panel, however in the remaining area, compacted thickness was kept around 200 mm. The moisture content of pond ash laid for compaction varied from 25% to 30% and density achieved was in the range of 10 kN/m3 to 13 kN/m3.

Use of Geosynthetic Material For Reinforced Earthwall Construction
Figure 4: Compaction of Backfill (pond ash) with vibratory roller and plate vibrator

Laying of reinforcing material (Koloties)

Before the laying of Koloties, fill and filter material were compacted in layers to the level of the first layer of the frictional anchor. Koloties were then placed to the alignment as per the drawings in horizontal layers. It was looped between panel anchors and the outer fixing bar. In case of joints, at least 1 to 1.5 m overlap was provided. After laying Koloties were hand tightened to remove any slackness before placing the next layer of filler material (Pond ash). This sequence was repeated till desired height was reached. Top panels were covered by cast in-situ capping beam. Layers of friction ties are shown in Fig.5.

Use of Geosynthetic Material For Reinforced Earthwall Construction
Figure 5: Laying of friction ties

Construction of pavement crust

After the reinforced fill was constructed, a mixture of Yamuna sand and pond ash was laid above it for a depth of about 50 cm. This was done to improve the stability of the reinforced portion. Over this layer sub grade soil was laid compacted as per MORTH specifications. The pavement crust consisted of 300 mm thick granular sub-base, 250mm Wet Mix Macadam (WMM), 50mm Bitumin- ous Macadam (BM), 50mm Dense Bituminous Macadam (DBM) follo- wed by 40mm Bituminous concrete (BC). The construction of capping beam and crash barrier was done.

Conclusions

  • This reinforced earth technique is particularly advantageous in urban areas where land is scarce and land values are high. Reinforced earth enables construction of walls on the boundary of the area available without encroaching upon the adjacent land.
  • The technique is simple and easy to install. There are only three components i.e. facing panels, frictional anchors and soil/pond ash. With slight experience, construction can be carried out with a very fast pace of construction.
  • Pond ash could be used as an alternative to conventional earth as a backfill material.
  • Since there is very little transfer of load to the ground and system being flexible in nature, it can be used on soils with low bearing capacity.
  • The distinctive pre-formed facing units can be manufactured with a variety of attractive pattern and in different colours. This helps in improving aesthetics of the structure blending with the surrounding.
  • This type of wall being flexible is safer in earthquake prone areas as compared to conventional reinforced concrete retaining wall.

Acknowledgement

The paper is published with the kind permission of Director, CRRI. The authors acknowledge Sh.U.K.Guruvittal and Sh.Alok Ranjan, scientists of the division for their contribution during quality supervision of construction of flyover.

References

  • Digioia, A.M and Brendel, G.F,(1998) “Coal ash as structural fill”, International Conference - Pond ash Disposal & Utilisation, Organised by CBIP, New Delhi, Vol II, pp. 39-48.
  • Elias, V., Christopher, B. R., and Berg, R. R. (2001). “Mechanically stabilized earth walls and reinforced soil slopes—Design and construction guidelines.” Rep. No. FHWA-NHI-00-043, Federal Highway Administration (FHwA), Washington, D.C.
  • Huabei Lie amd Myoung-Soo Won(2009) “Long-term reinforce- ment load of geosynthetic –reinforced soil retaining walls” Journal of geotechnical and geo- environmental engg. Vol. 135 (7).
  • Jimmy Thomas and Pawan Tripthi (2008) “Geogrid reinforced soil walls with welded wire mesh facing to retain the approaches to a flyover.” International seminar on geosynthetics, Hyderabad, India. Published by international geosynthetics society and Central board of irrigation and power, New Delhi.
  • Mandal JN (1987). “Geotextiles in India” Journal of Geotextiles and Geomembrane, Vol. 6(4) pp 235-274.
  • Martin,J.P., Collins, R.A., Browning, S.J and Biehl, F.J., (1990) “Properties and Use of Pond Ashes for Embankments”, Journal of ASCE Energy Engineering, Vol. 116, No.2, pp. 71-86.
  • Mathur, S., Guruvittal, U.K., Havanagi, V. G., and Sinha, A.K, (2003). “Design and construction of reinforced approach embank- ment using pond ash”. Proceeding of 3rd International Conference – Fly ash Utilisation & Disposal, New Delhi, Vol. 1, pp VI 39- VI 45.
  • Yudbir and Honjo,Y.,(1991) “Applications of Geotechnical Engineering to Environmental Control,” Theme Lecture at 9th Asian Regional Conference on Soil Mechanics and Foundation Engineering, Bangkok,pp.431-469.
NBM&CW September 2011
Performance of Thin White Topping (TWT) Overlay for NH-848

Performance of Thin White Topping (TWT) Overlay for NH-848

Vikas V. Thakar, MD, Pavetech Consultants India, presents the uses and advantages of TWT as a cost-effective treatment and a sustainable solution for rehabilitating and strengthening of flexible pavements, as seen in the NH-848 Nashik

Read more ...

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

REJUPAVE Technology for High RAP Recycling of Bituminous Pavement

Satish Pandey, Principal Scientist at CSIR-CRRI, New-Delhi, and Associate Professor, Academy of Scientific and Innovative Research, gives a brief overview of Hot Mix recycling process using bio-oil based rejuvenator REJUPAVE to facilitate

Read more ...

Safety Challenges On Indian Roads

Safety Challenges On Indian Roads

S.K. Nirmal, Secretary General, Indian Roads Congress, Director General (Road Development) & Special Secretary (Retd), MoRTH, gives an overview of India’s road network, causes of road accidents, and the safety measures and policies required

Read more ...

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

Dynapac Machines Deployed on Prestigious Palkhi Marg Project in Maharashtra

The Palkhi Marg holds deep significance as a pathway of faith for devotees of Lord Vitthal. Every year, thousands of ‘warkaris’ embark on a spiritual journey to the temple town of Pandharpur in Maharashtra. With the vision to create a Bhakti Marg and ensure

Read more ...

Delhi Vadodara Expressway Package-1 An overview

Delhi Vadodara Expressway Package-1 An overview

The Delhi-Vadodara Expressway is a part of the most anxiously awaited Delhi-Mumbai Expressway - the foundation stone for which was laid on March 8th 2019. Also referred to as the Delhi-Mumbai Industrial Corridor, it is planned as part of the Bharatmala

Read more ...

Bonded Rigid Pavement - A New Edge Concrete Pavement

Bonded Rigid Pavement - A New Edge Concrete Pavement

The exponential growth of the highway infrastructure in the past two decades has increased demand for long-lasting, durable pavements. Rigid pavements are suitable for heavily trafficked areas and are found to be performing satisfactorily with minimum

Read more ...

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

BRO Builds ‘Zero Fatality Corridors’ in Arunachal Pradesh

Through its unwavering commitment to road safety, eco-conscious practices, and visionary solutions, the Border Roads Organisation is elevating the standard of road infrastructure development in India. In Arunachal Pradesh, its contributions

Read more ...

Engineering Measures for Pothole Prevention

Engineering Measures for Pothole Prevention

Roads, pavements, and other paved surfaces have depressions in them called potholes which are caused by a variety of conditions. They not only present a serious risk to traffic and pedestrians, but also necessitate expensive repairs by local governments and

Read more ...

Pavement Marking Essential For Road Safety

Pavement Marking Essential For Road Safety

Vivek Singh, Founder, BuildStreet delves into the significance of pavement marking, its objective, and importance, with a focus on Hot Applied Thermoplastic paint - the predominant choice for road markings in India, its technical aspects, application methodology

Read more ...

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

GAEPL Achieves Record Paving of 100 lane-km in 100 hours

Ghaziabad Aligarh Expressway Private Limited (GAEPL), under the guidance of Cube Highways, has set an example of speedy, safe, and sustainable road construction through research, integration of advanced technology, following best international practices

Read more ...

Indian Companies Delivering Projects Overseas

Indian Companies Delivering Projects Overseas

External affairs minister S. Jaishankar during his visit interacted with the workers and the senior staff, and lauded the role of Indian infra companies, saying that he was “impressed by their enthusiasm”. “Strong economics will complement shared values in taking

Read more ...

NHAI awards 6,003 km of highway projects in FY23

NHAI awards 6,003 km of highway projects in FY23

According to Motilal Oswal Financial Services, the infra project awarding activity picked up and gathered pace in Q4 of FY23, with NHAI awarding total projects of 6,003 km in FY23, much below its FY23 target of 6,500 km. The total value of projects awarded

Read more ...

Is the Indian Road Sector Navigating a Smooth Journey?

Is the Indian Road Sector Navigating a Smooth Journey?

This report covers the current state of the Indian Road Sector, performance of road projects under Hybrid Annuity Model, financial performance of major road developers, and the outlook for FY24. CareEdge Ratings analysed 235 HAM projects awarded between

Read more ...

Balanced Mix Design for Bituminous Mixes

Balanced Mix Design for Bituminous Mixes

As more than 90% of the roads in India have bituminous surfacing, a proper bituminous mix design also assumes significance for better performance of the bituminous roads. India is currently witnessing huge investments by the Indian Government towards

Read more ...

Sustainable Road Construction in Hilly Region

Sustainable Road Construction in Hilly Region

Siksha Swaroopa Kar, Principal Scientist, Amit Kumar, Technical Officer, Krishan, Technician, Flexible Pavement Division, CSIR-CRRI, New Delhi, discuss mechanized laying of cold bituminous layer, the mixer and paver that have been fabricated, and the effectiveness

Read more ...

Implementation of Road Maintenance Management System - Benefits & Technologies

Implementation of Road Maintenance Management System - Benefits & Technologies

The maintenance of road pavements is essential to ensure the safety, reliability, and sustainability of road networks. A road maintenance management system (RMMS) involves effective management of resources to optimize the life cycle of roads, reduce maintenance

Read more ...

Replacement of Steel Reinforcement with  Synthetic Fibre for Concrete Pavement & Floor

Replacement of Steel Reinforcement with Synthetic Fibre for Concrete Pavement & Floor

Manoj Didwania, Adani Total Gas Ltd, Dharamsinh Desai University (DDU-Nadiad), Cept University, presents a paper on the use of Macro Synthetic Reinforcement Fibre (MSRF) as full or partial replacement of Steel Reinforcement for Concrete Pavement

Read more ...

GTI® Reinforced Soil Slope System

GTI® Reinforced Soil Slope System

GTI® is involved in developing environmentally friendly construction products and systems, which are critical for achieving infrastructure growth in a sustainable manner. The company’s GTI® Sloping Fascia Unit and the new system GTI® Reinforced Soil Slopes

Read more ...

CRISIL: Debt to rise for road developers amid strong revenue growth

CRISIL: Debt to rise for road developers amid strong revenue growth

Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.