Dr. Rajeev Goel, Dr. SK Sharma, Central Road Research Institute, New Delhi
Er. Naveen Kumar, Resident Engineer, UP PWD, Rai Barely &
Er Parvez Ahmad, Assistant Engineer, UP PWD, Ghazipur

Introduction

A grade-separator was to be constructed at the Polytechnic crossing in Lucknow city on National Highway-24A. The construction work was started in May 2002 which was scheduled to be completed within three years. Before the completion of the work, the contract was terminated and the leftover work was awarded to another contractor. Two spans of Inner carriageway and one span of Outer carriageway were completed by the previous Contractor. The soffit slab and the web portion of the Outer span P2-P3 was cast-in-situ by the previous contractor while, the deck was to be cast by the new contractor. As the box girder was designed for single stage prestressing (i.e. Prestressing only after the casting of soffit slab, web and deck slab), therefore this span could not be prestressed earlier and remained supported on the shuttering for about two years. As soon as the work of prestressing was started, end anchorage blocks started caving, one after another. The work was immediately stopped and the problem was referred to CRRI. CRRI conducted detailed inspections/investigations for the structural integrity of this span P2-P3 on outer carriageway. Based on test results and visual inspection, scheme of its rehabilitation was prepared. Post rehabilitation assessment of the bridge was also carried out by CRRI and results are presented in this paper.

Details of Grade Separator

The grade separator was on a curve and has two independent carriageways namely 'Inner carriageway' and 'Outer carriageway'. Each carriageway has 4 spans of single cell box-girder shape (consisting of soffit slab, web and deck slab, each of 35 m length and simply supported over a pair of pot bearings on each support.) Each box girder was to be prestressed with 18 Nos. of prestressing tendons. Fig.1 shows the location plan of the grade separator. Longitudinal section of span P2-P3 is shown in Fig.2.

Location Plan of Grade Separator
Figure 1: Location Plan of Grade Separator

Typical Longitudinal Section of Box-Girder Span
Figure 2: Typical Longitudinal Section of Box-Girder Span

Field Investigations

During field investigations, it was noticed that out of 18 numbers of prestressing cables, 5 prestressing cables (four in soffit slab and one in web) are yet to be stressed in span P2-P3. It was observed that this span was still resting on the staging. Honeycombing, spalling of concrete and exposure of steel reinforcement were observed in the soffit slab near the junctions of end-diaphragm walls and inclined web and in the vicinity of bearings (refer Fig.3). Application of epoxy mortar and grout nipples in the affected areas was also noticed. Shuttering plates under the entire area of soffit slab except near end-diaphragm walls were still at place. Due to this reason, the concrete of soffit slab behind these shuttering plates could not be inspected.

Views of Distressed Span P2-P3 on Outer Carriageway
Figure 3: Views of Distressed Span P2-P3 on Outer Carriageway

Following non-destructive investigations on span P2-P3 were carried out to evaluate the quality of in-situ concrete in the vicinity of end diaphragms:
  • Schmidt Rebound Hammer test for estimating the compressive strength of concrete.
    This is a premium article available exclusively for our subscribers.
    If you are already a subscriber, please Login
    If not, subscribe now and get access to well researched articles & reports on infrastructure construction, equipment & machinery, innovations & technology, project reports, case studies, and more. All this by simply paying just ₹200/- for a month of complete portal access, or a discounted rate of ₹1000/- for a full year of access.
GAEPL Achieves Record Paving of 100 lane-km in 100 hours
Ghaziabad Aligarh Expressway Private Limited (GAEPL), under the guidance of Cube Highways, has set an example of speedy, safe, and sustainable road construction through research, integration of advanced technology, following best international practices

Read more ...

Indian Companies Delivering Projects Overseas
External affairs minister S. Jaishankar during his visit interacted with the workers and the senior staff, and lauded the role of Indian infra companies, saying that he was “impressed by their enthusiasm”. “Strong economics will complement shared values in taking

Read more ...

NHAI awards 6,003 km of highway projects in FY23
According to Motilal Oswal Financial Services, the infra project awarding activity picked up and gathered pace in Q4 of FY23, with NHAI awarding total projects of 6,003 km in FY23, much below its FY23 target of 6,500 km. The total value of projects awarded

Read more ...

Is the Indian Road Sector Navigating a Smooth Journey?
This report covers the current state of the Indian Road Sector, performance of road projects under Hybrid Annuity Model, financial performance of major road developers, and the outlook for FY24. CareEdge Ratings analysed 235 HAM projects awarded between

Read more ...

Balanced Mix Design for Bituminous Mixes
As more than 90% of the roads in India have bituminous surfacing, a proper bituminous mix design also assumes significance for better performance of the bituminous roads. India is currently witnessing huge investments by the Indian Government towards

Read more ...

Sustainable Road Construction in Hilly Region
Siksha Swaroopa Kar, Principal Scientist, Amit Kumar, Technical Officer, Krishan, Technician, Flexible Pavement Division, CSIR-CRRI, New Delhi, discuss mechanized laying of cold bituminous layer, the mixer and paver that have been fabricated, and the effectiveness

Read more ...

Implementation of Road Maintenance Management System - Benefits & Technologies
The maintenance of road pavements is essential to ensure the safety, reliability, and sustainability of road networks. A road maintenance management system (RMMS) involves effective management of resources to optimize the life cycle of roads, reduce maintenance

Read more ...

Replacement of Steel Reinforcement with  Synthetic Fibre for Concrete Pavement & Floor
Manoj Didwania, Adani Total Gas Ltd, Dharamsinh Desai University (DDU-Nadiad), Cept University, presents a paper on the use of Macro Synthetic Reinforcement Fibre (MSRF) as full or partial replacement of Steel Reinforcement for Concrete Pavement

Read more ...

GTI® Reinforced Soil Slope System
GTI® is involved in developing environmentally friendly construction products and systems, which are critical for achieving infrastructure growth in a sustainable manner. The company’s GTI® Sloping Fascia Unit and the new system GTI® Reinforced Soil Slopes

Read more ...

CRISIL: Debt to rise for road developers amid strong revenue growth
Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

Indian Toll Roads to witness moderation in growth to high single digits in FY2024 after a stellar 17-20% growth in FY2023: ICRA
WPI for December 2022 is significantly lower at 5.0% against WPI of 14.27% in December 2021. ICRA Ratings expects the toll road projects growth to moderate to high single digit in FY2024 after a 17-20% growth witnessed in FY2023 with moderation in the

Read more ...

Road Over Umling-La Pass at 19,024 Feet
Construction of World’s Highest Motorable Road Chismule – Demchok In Eastern Ladakh Using Non-Frost Susceptible Sub-Base. Union Territory of Ladakh is located at approx 11,000 feet above Mean Sea Level (MSL). The area experiences extreme cold

Read more ...

BRO Uses Eco-Friendly Steel Slag For Road Construction
Steel slag, a by-product of steel making, is produced during the separation of the molten steel from impurities in steelmaking furnaces. This process generates slag as a molten liquid melt and is a complex solution of silicates and oxides that solidifies

Read more ...

Potholes to become history breakthrough by Zydex
Vadodara-based Zydex Industries has developed a new technology in road construction that enables roads to resist cracking under heavy traffic loads and cyclic weather variations. The speciality chemicals company has been at the forefront of R&D and implementation

Read more ...

Expected Increase in M&A and Refinancing Activity for HAM Projects in India: ICRA
According to the ratings agency ICRA, there is expected to be an increase in mergers and acquisitions (M&A) and refinancing activity in highway asset management (HAM) projects in the upcoming quarters. Approximately 105 HAM projects, with a total bid project

Read more ...

Prestressed Precast Concrete Pavement (PPCP)TM
PPCP Technology can help build roads of good quality, which are highly durable, can be built quickly, and do not require extensive maintenance. The construction industry is primarily concerned with two issues: construction quality control and the speed

Read more ...

More Efficient Road with iROADS Asset Management
iROADS Asset Management System enables significant optimization of road maintenance costs while ensuring a well-maintained road network and road assets. India has the second largest road network in the world comprising national

Read more ...

Upgradation of PMGSY Road Using Full Depth Reclamation Process in the State of Nagaland
Rapid growth in industrial development and economy in last two decades has demanded upgradation of the existing road network in the country. Though there is a huge road network in the country, it is still inadequate to meet accessibility and mobility requirements

Read more ...

Erosion Control for Green Highway Construction
Namrata Bichewar, Regional Manager - Maharashtra, Gabion Technologies India Pvt Ltd, discusses the company’s contribution in constructing green highways using Bio-Engineering Erosion Control methods and solutions. The government plans to construct 26 green expressways

Read more ...

Stone Matrix Asphalt is enabling durable and maintenance-free roads in India
A Stone Matrix Asphalt (SMA) pavement laid at Parimal Underpass in Ahmedabad Municipal Corporation has completed 7 years. The underpass, which used to get submerged under almost 2m depth of water due to waterlogging in the monsoons every year

Read more ...