Dr. Rajeev Goel, Dr. SK Sharma, Central Road Research Institute, New Delhi
Er. Naveen Kumar, Resident Engineer, UP PWD, Rai Barely &
Er Parvez Ahmad, Assistant Engineer, UP PWD, Ghazipur

Introduction

A grade-separator was to be constructed at the Polytechnic crossing in Lucknow city on National Highway-24A. The construction work was started in May 2002 which was scheduled to be completed within three years. Before the completion of the work, the contract was terminated and the leftover work was awarded to another contractor. Two spans of Inner carriageway and one span of Outer carriageway were completed by the previous Contractor. The soffit slab and the web portion of the Outer span P2-P3 was cast-in-situ by the previous contractor while, the deck was to be cast by the new contractor. As the box girder was designed for single stage prestressing (i.e. Prestressing only after the casting of soffit slab, web and deck slab), therefore this span could not be prestressed earlier and remained supported on the shuttering for about two years. As soon as the work of prestressing was started, end anchorage blocks started caving, one after another. The work was immediately stopped and the problem was referred to CRRI. CRRI conducted detailed inspections/investigations for the structural integrity of this span P2-P3 on outer carriageway. Based on test results and visual inspection, scheme of its rehabilitation was prepared. Post rehabilitation assessment of the bridge was also carried out by CRRI and results are presented in this paper.

Details of Grade Separator

The grade separator was on a curve and has two independent carriageways namely 'Inner carriageway' and 'Outer carriageway'. Each carriageway has 4 spans of single cell box-girder shape (consisting of soffit slab, web and deck slab, each of 35 m length and simply supported over a pair of pot bearings on each support.) Each box girder was to be prestressed with 18 Nos. of prestressing tendons. Fig.1 shows the location plan of the grade separator. Longitudinal section of span P2-P3 is shown in Fig.2.

Location Plan of Grade Separator
Figure 1: Location Plan of Grade Separator

Typical Longitudinal Section of Box-Girder Span
Figure 2: Typical Longitudinal Section of Box-Girder Span

Field Investigations

During field investigations, it was noticed that out of 18 numbers of prestressing cables, 5 prestressing cables (four in soffit slab and one in web) are yet to be stressed in span P2-P3. It was observed that this span was still resting on the staging. Honeycombing, spalling of concrete and exposure of steel reinforcement were observed in the soffit slab near the junctions of end-diaphragm walls and inclined web and in the vicinity of bearings (refer Fig.3). Application of epoxy mortar and grout nipples in the affected areas was also noticed. Shuttering plates under the entire area of soffit slab except near end-diaphragm walls were still at place. Due to this reason, the concrete of soffit slab behind these shuttering plates could not be inspected.

Views of Distressed Span P2-P3 on Outer Carriageway
Figure 3: Views of Distressed Span P2-P3 on Outer Carriageway

Following non-destructive investigations on span P2-P3 were carried out to evaluate the quality of in-situ concrete in the vicinity of end diaphragms:
  • Schmidt Rebound Hammer test for estimating the compressive strength of concrete.

    This section of the article is only available for our subscribers. Please click here to subscribe to a subscription plan to view this part of the article.

Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
There are many challenges being faced by the highway sector such as ensuring availability of construction materials and machinery, timely completion of projects, availability of trained human resources

Read more ...

Practical Recommendations for Construction of Longitudinal Joints in Hot Mix Asphalt (HMA) Pavements Rajib B. Mallick, Ralph White Family Distinguished Professor, Civil and Environmental Engineering, Worcester Polytechnic Institute (WPI), Massachusetts, USA, and Veeraragavan

Read more ...

Plant and Equipment Determine Quality of Road Construction Road Infrastructure projects are time constrained; early completion of project entitles rewards while delays attract penalties. The plants and equipment being used determines the quality of the road

Read more ...

New Road Technologies & Smart Roads The exponential increase in the number of vehicles on roads has led to multiple traffic problems and associated risks, traffic congestions, etc., yet the roads, despite being arteries of modern

Read more ...

Designing roads and highways efficiently with the right materials will help achieve optimum construction cost, lower maintenance, and reduce life cycle costs. Ash from coal-fired thermal power

Read more ...

Rodic Consultants has emerged as a leader in the infrastructure consulting space with state-of-the-art engineering solutions, and a proven track record of timely completion of projects across sectors

Read more ...

Readymade Kandhal Pothole Patching Mix was adopted as Indian Roads Congress (IRC) Standard Specification IRC: 116-2014 for Readymade Bituminous Pothole Patching Mix Using Cut-Back Bitumen. All concerned

Read more ...

The Bundelkhand Expressway is a 296-km long, 4-lane wide (expandable to 6 lanes) access-controlled expressway in the state of Uttar Pradesh. It will connect Gonda village in Chitrakoot district with Agra–Lucknow

Read more ...

This case study briefly discusses the planning, design and construction of Package 3 of the Purvanchal Expressway. Package-3 of the Purvanchal Expressway is a 41.7km long section of the 340.82km long

Read more ...

Since the 1980’s billions of dollars have been invested in developing methods to make pavement design and construction more sustainable through the re-use of existing resources. This includes insitu recycling and

Read more ...

India has the second largest road network in the world, spanning a total of 5.89 million km, transporting 64.5% of all goods in the country. Nearly 90% of India's total passenger traffic uses the road network to commute

Read more ...

India generates nearly 26,000 tonnes of plastic waste every day, making it the 15th biggest plastic polluter globally. Discarded plastic waste litter the country’s roads, rivers and also form huge mounds in garbage

Read more ...

According to Vipula Sharma, Director – Ratings, Brickwork Ratings, with the recent tweaking in the HAM model, the share of the projects awarded under HAM model is expected to increase. “Overall, there should be a

Read more ...

After creating a world record for laying Pavement Quality Concrete (PQC) for a four-lane highway of 2,580 meters length within 24 hours, NHAI has made yet another record by completing a single lane of the four-lane

Read more ...

Ashoka Buildcon, a leading highway player in India, has an impressive portfolio of 39 PPP projects, which is the largest in number in the country. With 40 years of experience in the core business of Highway Construction

Read more ...

Patel Infrastructure, an established construction, development, and maintenance service company and a NHAI contractor, has created a world record in the Infrastructure sector by laying Pavement Quality Concrete (PQC) for

Read more ...

Macro synthetic polymeric fibres have the potential to enhance the post cracking properties of hardened cement-based materials, besides bringing improvements in other properties such as durability. This article disseminates

Read more ...

High altitude areas which are subjected to heavy snowfall and frost action necessitate special consideration for design and construction of pavements. U.K.Guruvittal, Chief Scientist & Dr G Bharath, Scientist, CSIR-Central

Read more ...

Flexible pavements are the most common type of pavement systems in the country. In addition to being convenient to construct, they are also cost-effective and easy to maintain. These pavements constitute the surface

Read more ...

Roller Compacted Concrete is an innovative technology gaining popularity in the recent past due to some of the positive points like low cost of construction, speed in construction, and the possibility of using mineral

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.