Practical Recommendations for Construction of Longitudinal Joints in Hot Mix Asphalt (HMA) Pavements

Rajib B. Mallick, Ralph White Family Distinguished Professor, Civil and Environmental Engineering, Worcester Polytechnic Institute (WPI), Massachusetts, USA, and Veeraragavan Amirthalingam, Professor, Department of Civil Engineering, IIT Madras

Hot Mix Asphalt (HMA) is made up of primarily mineral aggregates and asphalt binder that are heated and mixed in a plant at an elevated temperature (~ 150oC), placed with a paver at a lower but sufficiently high temperature (~ 140oC), and compacted with rollers before the temperature drops below a certain level, typically 90-100oC.

Compaction generally becomes very difficult to accomplish once the temperature of the mix drops below approximately 90oC because of increased stiffness. This change in stiffness is a result of the change in stiffness of the asphalt binder, which behaves as a viscous material at high temperatures, and a viscoelastic material for most other temperature regimes. A well-designed and constructed HMA pavement provides a durable, smooth and watertight surface at a relatively low cost.

HMA (also known as asphalt) pavements do not require the creation of joints as is generally the case for portland cement concrete (PCC) pavements. However, unless echelon paving is adopted, a longitudinal joint occurs in between adjacent paved lanes. In the first pass of the paver, the first lane is constructed. When the adjacent lane is placed, the first lane has cooled and is referred to as the cold side of the joint. The second lane is often referred to as the hot side of the joint. During compaction of the edge of the cold lane the pavement is not restrained, hence, a lower density (higher air voids) is anticipated close to the edge relative to the areas away from the edge. There is confinement when compacting the edge (hot side) of the adjacent lane since it is placed up against the cold joint. Because of the issues at the joint and on both sides of the joint, the density directly in the joint is almost always lower than the asphalt mixture away from the joint. A low-density joint area is an ‘Achilles heel’ for otherwise well-constructed pavements since it may allow the rapid ingress of water and debris into the pavement and may lead to subsequent disintegration and premature failure (Figure 1).

Typical problems in longitudinal joints in asphalt pavements – note the ingress of water and subsequent deterioration along the jointFigure 1. Typical problems in longitudinal joints in asphalt pavements – note the ingress of water and subsequent deterioration along the joint

In the absence of echelon paving, three major construction processes are recommended (see Ref 1-5) to achieve adequate density at the joints: butt joint, wedge joint, and cut (and remove) joint. There is also a recommendation for compacting the first 150 mm of the existing cold lane while compacting the adjacent hot lane (5, Figure 2). In the case of a wedge joint, during the paving of the hot lane, the heated material will cover the sloped joint that can be easily compacted. It is believed that the roller can increase the density of the joint while compacting the hot side and that the overlapping hot side material on the cold wedge of the joint would create a higher density area. From the traffic safety point of view, the wedge joint is a better option compared to a butt joint with a sharp vertical drop, especially when the hot side is not paved immediately after the cold side. This is especially safer for motorcycles. Other recommendations include heating the joint and/or, and tack coating/sealing the joint before paving the hot side (5).

Examples of techniques used for improving density at the joint (a) wedge joint; (b) rolling from the hot side with 150 mm overlap on the cold side; (c) rubberized asphalt tack coat application on a notched wedge joint; (d) cutting part of the cold jointFigure 2: Examples of techniques used for improving density at the joint (a) wedge joint; (b) rolling from the hot side with 150 mm overlap on the cold side; (c) rubberized asphalt tack coat application on a notched wedge joint; (d) cutting part of the cold joint

Field research studies conducted over the years with different configurations have yielded mixed results in terms of density and performance. For example, some studies have shown that the wedge joint is better (6) (Toepel, 2003), while some have indicated good performance with sealed joints (7). Concerns have been expressed regarding the ability to compact the sloped portion of the wedge joint. Effective design (vertical or wedge) and construction of longitudinal joints remain an ongoing topic of research because of two reasons. First, the failure of pavements at joints continues to be a major problem in HMA pavements, and second, a lack of modeling/simulation work that could provide a rational basis for joint construction methods. Most of the existing work is based on field or laboratory experiments (e.g., 8).

This article explores the temperature increase in the cold butt joint during the paving of the hot side. Is it high enough for effective compaction during the compaction of the hot side? Is the temperature increase greater for a wedge joint?

Modeling And Analysis
Thermal modeling was conducted with Mecway (9) software in the following manner:

Model joints for thermal analysis
  • Apply relevant material thermal properties, boundary, and thermal loading conditions
  • Simulate the transient thermal condition for a time period expected during construction
  • Analyze the variation of temperature with time at different areas of the joints
In finite element analysis, a numerical technique is utilized to represent the object as a combination of relatively simple shapes (elements) that are connected at nodes (mesh). The material properties are assigned to the different elements, and the loading and constraints are applied. The different elements are related to each other through physics-based laws, such as heat transfer principles in thermal analysis, where a single temperature can be assigned to each node. The model is solved, and the mesh can be refined as desired by checking the solution through several iterations.The heat flux is calculated across the mesh from the input initial boundary condition data, and the updated temperatures are output.

Both butt and wedge joints were modeled in this analysis. The model conditions included a wind speed of 16 kmph (4.5 m/s), mix laydown temperature of 140oC, and an ambient temperature (air and existing base) of 25oC. A 450 mm section of the pavement (with a thickness of 50 mm) was modeled with the hot side paving along a cold side joint, as shown in Figure 3. In the case of the wedge joint, the right side is the cold side, whereas the left side is the hot side. The loading conditions and restraints consisted of the initial temperature of the various sections, convection at the open edges, and no heat flux along the edges of the base/existing HMA. The last condition was specified because the thermal conductivity of HMA is very low (1.6 W/m/K), and the boundary for the no heat flux was made at a distance that is sufficiently away from the model sections where no change in temperature was noted during the transient thermal analysis. The convective heat transfer coefficient (H) was calculated from the following formula (10,11):

Equation

where,Taverage = average of the surface and air temperatures, ºC, U = wind speed in m/s, Tsurface = temperature of surface, oC or oK, and Tair = temperature of air, oC or oK.

Schematic of Finite Element model for transient thermal analysisFigure 3: Schematic of Finite Element model for transient thermal analysis

The thermal properties used in the model consisted of a thermal conductivity of 1.6 W/m/K, and a heat capacity of 1,200 J/kg/K (12). Thermal properties have been found to be insensitive to temperature within the range that has been used in this study. There is no difference in thermal properties between the different sections of the pavement.

Results
Figures 4 and 5 show the results of thermal analyses of the butt and the wedge joints, respectively. As the material of the hot lane is laid down at 140oC, the heat from the mix starts to warm up the joint. With time, the heat flows towards the cold lane, because of its relatively low temperature (25oC). Within a time of 30 minutes, the heat can be seen to penetrate to 50-60 mm of the joint (see point A in Figure 4). However, with time, due to the conduction and convection of heat (wind above the mix and the cold lane) the temperature decreases. As a result, only about 12.5 mm (see point B in Figure 4) of the joint is heated to a temperature > 90oC within the first 5 minutes of laydown. For the remaining heated area, the temperature reaches a maximum of approximately 78oC and then starts decreasing over time.

Butt Joint, Wedge Joint

Figure 4: Butt Joint: Temperature at selected times after the placement of the hot side HMA; Hot Side HMA laydown temperature, 140oC, ambient temperature and temperature of existing base and cold side, 25oC; wind speed, 4.5 m/s (10 miles per hour); Thickness of the surface layer is 50 mm

Figure 5: Wedge Joint: Temperature at selected times after the placement of the hot side HMA; Hot Side HMA laydown temperature, 140oC, ambient temperature and temperature of existing base and cold side, 25oC; wind speed, 4.5 m/s (10 miles per hour); Thickness of the new layer is 50 mm

In the case of the wedge joint, there is a greater penetration of heat into the joint because HMA is placed over the wedge allowing higher temperatures to go farther into the cold side. Approximately 188 mm of the joint is heated up by the mix in the hot lane (see point A in Figure 5). Out of this area, a significant part of it, approximately 150 mm (see point B) is heated to a temperature > 90oC. This is significant since the relatively high temperature enables effective compaction at the interface of the sloped joint during the compaction of the hot lane. From Figures 4 and 5 it can be inferred that rolling 150 mm into the joint while compacting the hot lane is more effective in the case of a wedge joint than in a butt joint.

The following conclusions and recommendations are made from this study:
  • In a butt joint, the placement of HMA in the hot lane cannot be expected to cause a rise in the temperature along the cold lane/joint area to a high enough level for effective roller compaction.
  • In a wedge joint, the placement of the HMA on the hot lane side can be expected to cause a rise in the temperature of the bottom part of the wedge from the cold lane side to a level that would allow effective compaction.
  • Therefore, a wedge configuration is recommended to obtain better density at the joint.
  • Modeling and analysis, especially for field conditions (range of temperature) should be conducted to develop practical guidelines for joint construction.
References
  1. Kandhal, P. S., and S. Rao. Evaluation of Longitudinal Joint Construction Techniques for Asphalt Pavements. Transportation Research Record 1469, TRB, National Research Council, Washington, DC, 1994.
  2. Kandhal, P. S., and R. B. Mallick. A Study of Longitudinal Joint Construction Techniques in HMA Pavements. Transportation Record 1543, TRB, National Research Council, Washington, DC, 1996.
  3. Brock, J. D., and T. Skinner. Longitudinal Joints: Problems & Solutions. NAPA Quality Improvement Series 121, December 1997.
  4. Kandhal, P. S., T. L. Ramirez, and P. M. Ingram. Evaluation of Eight Longitudinal Joint Construction Techniques for Asphalt Pavements in Pennsylvania. Transportation Research Record 1813, TRB, National Research Council, Washington, DC, 2002.
  5. Mallick, R. B., P. S. Kandhal, R. Ahlrich, and S. Parker. Improved Performance of Longitudinal Joints on Asphalt Airfield. Final report to Federal Aviation Administration (FAA), Project 04-05: Airfield Asphalt Pavement Technology Program (AAPTP), July 2007.
  6. Toepel, A. Evaluation o f T e c h n i q u e s for Asphaltic Pavement Longitudinal Joint Construction. Wisconsin DOT Final Report WI-08-03, November 2003.
  7. Daniel, J. S. and W. L. Real. Field Trial of an Infrared Joint Heater to Improve Longitudinal Joint Performance in New Hampshire. Presented at the Annual Meeting of the Transportation Research Board, Washington, DC. January 2006.
  8. Chen, J., B. Huang, Y. Li, and X. Shu. Laboratory Evaluation of Effects of Joint Heater on Longitudinal Joint. GeoShanghai International Conference 2010.
  9. Mecway Limited, Mecway, New Zealand, 2018.
  10. Dempsey, B. J. A Heat Transfer Model for Evaluating Frost Action and Temperature Related Effects in Multilayered pavement Systems. In Highway Research Record 342, HRB, National Research Council, Washington, DC, 1970, pp. 39-56.
  11. Solaimanian, M. and T. Kennedy. Predicting Maximum Pavement Surface Temperature Using Maximum Air Temperature and Hourly Solar Radiation. Transportation Research Record 1417, Transportation Research Board, Washington, DC, pp 1-11, 1993.
  12. Chen, B., L. Rockett, and R. B. Mallick. Laboratory Investigation of Temperature Profiles and Thermal Properties of Asphalt Pavements with Different Subsurface Layers. Journal of AAPT, Volume 77, 2008.
GAEPL Achieves Record Paving of 100 lane-km in 100 hours
Ghaziabad Aligarh Expressway Private Limited (GAEPL), under the guidance of Cube Highways, has set an example of speedy, safe, and sustainable road construction through research, integration of advanced technology, following best international practices

Read more ...

Indian Companies Delivering Projects Overseas
External affairs minister S. Jaishankar during his visit interacted with the workers and the senior staff, and lauded the role of Indian infra companies, saying that he was “impressed by their enthusiasm”. “Strong economics will complement shared values in taking

Read more ...

NHAI awards 6,003 km of highway projects in FY23
According to Motilal Oswal Financial Services, the infra project awarding activity picked up and gathered pace in Q4 of FY23, with NHAI awarding total projects of 6,003 km in FY23, much below its FY23 target of 6,500 km. The total value of projects awarded

Read more ...

Is the Indian Road Sector Navigating a Smooth Journey?
This report covers the current state of the Indian Road Sector, performance of road projects under Hybrid Annuity Model, financial performance of major road developers, and the outlook for FY24. CareEdge Ratings analysed 235 HAM projects awarded between

Read more ...

Balanced Mix Design for Bituminous Mixes
As more than 90% of the roads in India have bituminous surfacing, a proper bituminous mix design also assumes significance for better performance of the bituminous roads. India is currently witnessing huge investments by the Indian Government towards

Read more ...

Sustainable Road Construction in Hilly Region
Siksha Swaroopa Kar, Principal Scientist, Amit Kumar, Technical Officer, Krishan, Technician, Flexible Pavement Division, CSIR-CRRI, New Delhi, discuss mechanized laying of cold bituminous layer, the mixer and paver that have been fabricated, and the effectiveness

Read more ...

Implementation of Road Maintenance Management System - Benefits & Technologies
The maintenance of road pavements is essential to ensure the safety, reliability, and sustainability of road networks. A road maintenance management system (RMMS) involves effective management of resources to optimize the life cycle of roads, reduce maintenance

Read more ...

Replacement of Steel Reinforcement with  Synthetic Fibre for Concrete Pavement & Floor
Manoj Didwania, Adani Total Gas Ltd, Dharamsinh Desai University (DDU-Nadiad), Cept University, presents a paper on the use of Macro Synthetic Reinforcement Fibre (MSRF) as full or partial replacement of Steel Reinforcement for Concrete Pavement

Read more ...

GTI® Reinforced Soil Slope System
GTI® is involved in developing environmentally friendly construction products and systems, which are critical for achieving infrastructure growth in a sustainable manner. The company’s GTI® Sloping Fascia Unit and the new system GTI® Reinforced Soil Slopes

Read more ...

CRISIL: Debt to rise for road developers amid strong revenue growth
Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

Indian Toll Roads to witness moderation in growth to high single digits in FY2024 after a stellar 17-20% growth in FY2023: ICRA
WPI for December 2022 is significantly lower at 5.0% against WPI of 14.27% in December 2021. ICRA Ratings expects the toll road projects growth to moderate to high single digit in FY2024 after a 17-20% growth witnessed in FY2023 with moderation in the

Read more ...

Road Over Umling-La Pass at 19,024 Feet
Construction of World’s Highest Motorable Road Chismule – Demchok In Eastern Ladakh Using Non-Frost Susceptible Sub-Base. Union Territory of Ladakh is located at approx 11,000 feet above Mean Sea Level (MSL). The area experiences extreme cold

Read more ...

BRO Uses Eco-Friendly Steel Slag For Road Construction
Steel slag, a by-product of steel making, is produced during the separation of the molten steel from impurities in steelmaking furnaces. This process generates slag as a molten liquid melt and is a complex solution of silicates and oxides that solidifies

Read more ...

Potholes to become history breakthrough by Zydex
Vadodara-based Zydex Industries has developed a new technology in road construction that enables roads to resist cracking under heavy traffic loads and cyclic weather variations. The speciality chemicals company has been at the forefront of R&D and implementation

Read more ...

Expected Increase in M&A and Refinancing Activity for HAM Projects in India: ICRA
According to the ratings agency ICRA, there is expected to be an increase in mergers and acquisitions (M&A) and refinancing activity in highway asset management (HAM) projects in the upcoming quarters. Approximately 105 HAM projects, with a total bid project

Read more ...

Prestressed Precast Concrete Pavement (PPCP)TM
PPCP Technology can help build roads of good quality, which are highly durable, can be built quickly, and do not require extensive maintenance. The construction industry is primarily concerned with two issues: construction quality control and the speed

Read more ...

More Efficient Road with iROADS Asset Management
iROADS Asset Management System enables significant optimization of road maintenance costs while ensuring a well-maintained road network and road assets. India has the second largest road network in the world comprising national

Read more ...

Upgradation of PMGSY Road Using Full Depth Reclamation Process in the State of Nagaland
Rapid growth in industrial development and economy in last two decades has demanded upgradation of the existing road network in the country. Though there is a huge road network in the country, it is still inadequate to meet accessibility and mobility requirements

Read more ...

Erosion Control for Green Highway Construction
Namrata Bichewar, Regional Manager - Maharashtra, Gabion Technologies India Pvt Ltd, discusses the company’s contribution in constructing green highways using Bio-Engineering Erosion Control methods and solutions. The government plans to construct 26 green expressways

Read more ...

Stone Matrix Asphalt is enabling durable and maintenance-free roads in India
A Stone Matrix Asphalt (SMA) pavement laid at Parimal Underpass in Ahmedabad Municipal Corporation has completed 7 years. The underpass, which used to get submerged under almost 2m depth of water due to waterlogging in the monsoons every year

Read more ...