Project Summary

Feasibility and Detailed Project Report for 4/6 Laning of Hyderabad-Vijayawadaand Vijayawada-Machilipatnam Under NHDP Phase III

Organization: Scott Wilson Kirkpatrick India Pvt Ltd.

BE Awards Category: Civil Road Infrastructure

Location: India

Project Objective: Widening India’s NH-9 from Hyderabad to Machilipatnam, including evaluation of multiple bypass options for eight sections of roadway.

Bentley Products

MXROAD V8 XM Edition

India’s NH-9 highway runs from Hyderabad, the capital city of state of Andhra Pradesh, to Machilipatnam, a port on the Bay of Bengal. As part of its National Highways Development Project, an ambitious four-phase program to upgrade about 25,000 kilometers of key national highways, the National Highways Authority of India (NHAI) plans to expand this road from two to four or six lanes and examine alternative alignments at certain towns to alleviate congestion.

The expansion will employ a buildoperate- transfer model, under which the government carries out preliminary work such as land acquisition and utility removal before turning the construction and operation over to a private concessionaire. Scott Wilson Kirkpatrick India Pvt Ltd (SWK India) was contracted by NHAI to prepare a feasibility study and detailed project report for the NH-9 expansion.

The project was split into two segments: the stretch from Hyderabad to Vijayawada and the stretch from Vijayawada to Machilipatnam. Highway construction is scheduled to start and finish by March 2010. The total length of the road is approximately 121 kilometers and the project cost is estimated to be $190 million.

Project Requirements

NH-9 runs mainly across a plain, with rolling terrain in some stretches. It passes through four major towns and many small villages along its route. The project itself includes 21 bridges, 197 culverts, and one railway crossing. The project is a partially controlled access road, so SWK India took this into consideration when planning the service roads and road safety, as well as the types of intersections, flyovers, and underpasses required.

As part of its work, SWK India examined the technical, economic, and financial viability of upgrading the two sections of NH-9 to a four–or six–lane divided highway. As the existing road was in good condition, the design called for the building of a new two-lane highway on one side of the existing road, with a median separating the two. Adopting this approach meant full utilization of the already acquired right of-way and reduction of time spent in securing additional land. However, the existing right-of-way proved to be minimal, so a large amount of private land had to be acquired. SWK India identified the additional land needed, generated the coordinate data, and staked the areas out on the ground before verifying and transferring the data back onto revenue maps used to contact landowners.

The project report provided designs for the highway, pavement (with options for flexible or rigid pavement), overlay, bridges, cross-drainage structures, grade-separated structures, and service roads. SWK India calculated quantities for many items and generated detailed working drawings as well as cost estimates. Other reports produced included the analyses of economic viability and environmental and social feasibility (with action plans as appropriate), as well as all documents needed for the bidding process.

NHAI also required SWK India to include the kind of financial returns that could be generated through tolls and other revenues. It would use these to help attract private businesses to build and operate its new roads. During the process, SWK India found that while the stretch from Vijayawada to Vuyyuru was likely to have sufficient traffic for a build-operate-transfer operator to recover its costs, the stretch from Vuyyuru to Machilipatnam did not. Having this data meant NHAI was able to seek assurances from the Andhra Pradesh state government over the planned development of Machilipatnam as a deepwater port facility, thereby increasing the amount of goods transported on that stretch of roadway.

Design in the Fast Lane

Initial topographic surveys took three to four months to complete, and during this process SWK India was able to fix preliminary alignments. Once the survey data was available, the firm could check them against field conditions using MXROAD and complete the detailed engineering of 121 kilometers of roadway.

NHAI identified eight locations where bypasses could relieve congestion near towns. For each bypass location, SWK India prepared several alternative alignments before running a cost/benefit analysis on each. The bypass for the towns of Kodad and Pamaru proved to be particularly challenging, as the alignments had to be routed to minimize interference with agricultural fields, cart paths, field channels, and a major canal surrounding the towns.

There were also situations in which a bypass had already been proposed and the land-acquisition process completed. In these cases, SWK India fixed the road alignment according to earlier plans using non-digital details provided by NHAI.

In total, SWK India ended up designing nearly 200 kilometers of road because of the multiple alignment options required. For each case, SWK India used revenue maps to determine the extent of land acquisition already completed as well as the new land required along the centerline of the planned route.

Finally, the road designs were evaluated for safety by outside experts. SWK India was able to create 3D visualizations of the project in order to convey sight distances and their suitability for the surrounding terrain along the road.

Venkat Sheela, principal engineer for SWK India, noted the robustness of MXROAD, including the ability to output the coordinates of utilities that needed to be moved, trees that needed to be cut, and structures that required complete removal. The software, he said, enabled an integrated workflow that extended from processing the survey data all the way through to preparing land-acquisition plans, relocating utilities, and generating quantity takeoffs. SWK India has used.

MXROAD for 12 years, and Mr. Venkat believes that it is “the right kind of software for such a complex project.” He added that the functionality of MXROAD helped the firm cut design time. The engineers prepared input files to create roadway edges, apply camber and superelevation as well as create verges, shoulders, lay-bys, median openings, junctions, and earthwork styles. Managing the different phases of engineering design on a single platform helped ensure a consistent and uniform design product, even extending to small details such as linetypes and styles. The coordinated workflow ensured that different departments were always working on the current version of the design.
CRISIL: Debt to rise for road developers amid strong revenue growth
Sizeable equity commitments in under-construction projects and rising working capital requirement will increase the debt burden of road developers, though revenue growth will also be high in the next two fiscals driven by strong awarding and execution

Read more ...

Indian Toll Roads to witness moderation in growth to high single digits in FY2024 after a stellar 17-20% growth in FY2023: ICRA
WPI for December 2022 is significantly lower at 5.0% against WPI of 14.27% in December 2021. ICRA Ratings expects the toll road projects growth to moderate to high single digit in FY2024 after a 17-20% growth witnessed in FY2023 with moderation in the

Read more ...

Road Over Umling-La Pass at 19,024 Feet
Construction of World’s Highest Motorable Road Chismule – Demchok In Eastern Ladakh Using Non-Frost Susceptible Sub-Base. Union Territory of Ladakh is located at approx 11,000 feet above Mean Sea Level (MSL). The area experiences extreme cold

Read more ...

BRO Uses Eco-Friendly Steel Slag For Road Construction
Steel slag, a by-product of steel making, is produced during the separation of the molten steel from impurities in steelmaking furnaces. This process generates slag as a molten liquid melt and is a complex solution of silicates and oxides that solidifies

Read more ...

Potholes to become history breakthrough by Zydex
Vadodara-based Zydex Industries has developed a new technology in road construction that enables roads to resist cracking under heavy traffic loads and cyclic weather variations. The speciality chemicals company has been at the forefront of R&D and implementation

Read more ...

Expected Increase in M&A and Refinancing Activity for HAM Projects in India: ICRA
According to the ratings agency ICRA, there is expected to be an increase in mergers and acquisitions (M&A) and refinancing activity in highway asset management (HAM) projects in the upcoming quarters. Approximately 105 HAM projects, with a total bid project

Read more ...

Prestressed Precast Concrete Pavement (PPCP)TM
PPCP Technology can help build roads of good quality, which are highly durable, can be built quickly, and do not require extensive maintenance. The construction industry is primarily concerned with two issues: construction quality control and the speed

Read more ...

More Efficient Road with iROADS Asset Management
iROADS Asset Management System enables significant optimization of road maintenance costs while ensuring a well-maintained road network and road assets. India has the second largest road network in the world comprising national

Read more ...

Upgradation of PMGSY Road Using Full Depth Reclamation Process in the State of Nagaland
Rapid growth in industrial development and economy in last two decades has demanded upgradation of the existing road network in the country. Though there is a huge road network in the country, it is still inadequate to meet accessibility and mobility requirements

Read more ...

Erosion Control for Green Highway Construction
Namrata Bichewar, Regional Manager - Maharashtra, Gabion Technologies India Pvt Ltd, discusses the company’s contribution in constructing green highways using Bio-Engineering Erosion Control methods and solutions. The government plans to construct 26 green expressways

Read more ...

Stone Matrix Asphalt is enabling durable and maintenance-free roads in India
A Stone Matrix Asphalt (SMA) pavement laid at Parimal Underpass in Ahmedabad Municipal Corporation has completed 7 years. The underpass, which used to get submerged under almost 2m depth of water due to waterlogging in the monsoons every year

Read more ...

Effect of Climate Change on Flexible Pavements
Dr. Abhishek Mittal, Principal Scientist, CSIR-CRRI New Delhi, discusses the effects of changes in temperature due to climate change on pavements with respect to their material, design, construction, and maintenance. A long-term shift in temperature and weather

Read more ...

Latest Technologies and Mechanization for Sustainable Road Construction & Maintenance of Pavements
Massive road development work for huge road network of the country’s national assets is essential for overall development of the country. However, major road development projects consume a huge quantity of soil and crushed aggregates. The consumption of these materials

Read more ...

AEW’s Dr. Road: Doing Away with Potholes Instantly
Following the launch of AEW’s road repair machine ‘Dr. Road’ by Shri Nitin Gadkari, Minister for Road Transport & Highways, Shatish Panchal, Director, AEW Group, informs that the company is geared up to promote the machine to State PWDs and CPWDs

Read more ...

Paving-Grade Asphalt Binders
Evaluating the Quality of Asphalt Binders and Plant Produced Asphalt Mixes through Recovered Asphalt Testing and other Mix Properties, Amma Wakefield, MASc, PEng Canadian Regional Engineer Asphalt Institute, Paving-grade asphalt binders are specified based

Read more ...

India’s Road Construction Sector Needs an Ecosystem of Safety
The Global Road Construction & Safety Conference 2022 will be held on 30th November 2022, at Hotel Taj Palace, New Delhi, in collaboration with CSIR- CRRI, Bitumen India Forum (BIF), National Highways Builders Federation (NHBF)

Read more ...

Colored Asphalt: The Changing Face of Road Construction in India
The road construction industry in India is undergoing a paradigm shift: strong demand, higher investments, and the emergence of newer and more innovative technologies is giving a renewed focus on sustainable developments. These technologies include

Read more ...

Economization of Road Subgrade Material by Mechanical Stabilization
Subgrade makes the formation level of the road crust. The material specifications of subgrade material are therefore more demanding than the soil used in general fill or embankment. In some construction projects, it becomes difficult to get the required subgrade

Read more ...

Perpetual Pavement: Way Forward from Design to Quality Construction
Atasi Das, Assistant Vice President, G R Infraprojects, explains the concept of the Perpetual Pavement in India’s expressway constructions and its practical implementation with due consideration of layers, materials, and thicknesses

Read more ...

Performance of Curing Compounds in Development of Strengths in Concrete Mix to be Used in the Construction of Rigid Pavements
Dr. Rakesh Kumar, Senior Principal Scientist & Pankaj Goel, Senior Technical Officer, Rigid Pavements Division,CSIR-Central Road Research Institute (CRRI), New Delhi, give information on the Performance of Curing Compounds in Strengthening

Read more ...