Ken MathersKen Mathers, Chief Executive Officer, Linking Melbourne Authority, Australia
Overview
A 39 kilometer toll motorway was constructed on budget (A$2.5 billion) and five months ahead of time. It was opened in June 2008. This project involved 17 interchanges, 88 bridges and twin three lane, 1.6 km tunnels. It has three lanes in each direction for 33 km and two lanes in each direction for 6 km. EastLink connects the eastern suburbs of Melbourne and was delivered under a Public Private Partnership (PPP) arrangement by Connect East (listed on the Australian Stock Exchange) for the Victorian Government agency, Southern and Eastern Integrated Transport Authority (SEITA). Project development was undertaken by two of Australia’s largest contracting organisations, Thiess and John Holland, in a joint venture arrangement.
 
Arun KumarArun Kumar, Professor of Infrastructure Management Queensland University of Technology, Brisbane, Australia
This paper describes the uniqueness of the project, construction practices and the working relationship with owners and contractors that led to a successful outcome. This project has set new standards in design, construction speed, safety, environmental impact, community engagement and significantly enhanced the urban amenity of the corridor.

Background
EastLink MotorwayFigure 1: EastLink Motorway overview
The road reserve for this corridor was planned in the early 1960’s. Environmental impact statements were developed and consulted with the community living along the corridor in the 1990’s. As Melbourne continued to expand, the construction of the Motorway became imperative. Work commenced in March 2005 and was completed in June 2008. An overview of the motorway section is being presented in Figure 1.

Performance Based Specifications
Right at the tendering stage, considerable thought was given to encourage competition in the private sector to achieve the best outcome for the Motorway. One of the key elements was devising the performance based specifications that would make it clear what was needed without specifying how it should be achieved. Interestingly, the document produced was a fraction of the size of a normal specification, yet spelt out the State’s requirements. It had set targets such as a 100 year design life for structures.

The specifications provided for the road to fall within a certain route envelope but the exact alignment was variable; the shape of the interchanges was open to variation, and the pavement had to perform to a certain standard yet its make-up was not prescribed. Urban design had to be a part of the mix and the bids had to show that they reflected community expectations along the route. The requirement of the tolling system was that it had to be fully electronic and it had to be interoperable with other electronic toll roads in Australia. Toll levels were not prescribed with the only requirement deemed that escalation had to match movements in the Consumer Price Index (CPI) with changes being applied annually. Both design and construct contracts were self-monitored by Quality Assurance (QA) procedures and checks as work progressed.

The Independent Reviewer
The Independent Reviewer (IR) was appointed jointly by the Government and the Concessionaire. The IR’s role involved a general overview and reasonable checking in order to be satisfied that the various detailed checks and monitoring processes were carried out correctly and, in order to ensure compliance with the design construction requirements. This organisation reported jointly to the two employers, ensuring impartiality between the two client sides. All design and construction information developed by the contractor had to be provided to the IR who had the responsibility to certify completion before the road could be opened.

Working Arrangements
EastLink MotorwayFigure 2: The road headers carving the rock away with multi-toothed rotating pick-axes
For the processes to be efficient, tight timelines for making comments were agreed by all parties to ensure the contractor was not unduly held up waiting for responses. This arrangement was successful as effective working relationships and flexibility were established between the people working on the project (the contractor and the two client bodies). An electronic tracking system was implemented and improved the efficiency of the documentation flow.

Another efficient process implemented was that construction itself was subjected to Quality Assurance (QA) processes. The contractor was responsible for auditing and guaranteeing its own systems according to appropriate QA standards.

The Construction Challenge
The Tunnel: The construction of the $600 million twin tunnels was a complex operation. The diameters of each tunnel exceeded 16 meters with special ventilation buildings at the exits. These buildings incorporated large fans to capture the air leaving the tunnel and the car exhaust contained in it. The excavation was undertaken by four large machines known as road headers. These have a rotating head with cutting teeth at the end of a pivoting boom for cutting away the material at the heading of the tunnels, Figure 2.

The tunnel was also fully “tanked.” This means that it was made watertight, rather than allowing water to trickle in the tunnel and then draining it out. This was done by having a circular cross section for the tunnel and using a drainage blanket and waterproof lining, Figure 3. An overview of the tunnel is presented in Figure 4.

EastLink MotorwayFigure 3: Full tanking (waterproofing) with a membrane

The Bridges: For most of the 88 bridges, pre-cast reinforced concrete units were used for speed, quality and economy. In the case of an operational railway line which overpassed the new road, the construction schedule was planned in such a way that it was closed only for a very short time. This was achieved by first, installing the foundations and final columns of the new bridge and then the crosshead supports for the bridge super structure.

EastLink MotorwayFigure 4: Tunnel overview

EastLink MotorwayFigure 5: Newly constructed bridges over the motorway
The foundations of the four-span bridge comprised 1.8 metre diameter bored concrete piles which could be installed outside the train “envelope,” Pairs of the piles at each of three pier positions and for the abutments were put in through the existing rail embankment. They went into the ground as support but stood free in the top few metres once the ground was excavated around them, forming the columns of the bridge. The super structures, complete with new rail tracks for the new railway overpass, was built alongside the operational railway on the extensions of the crossheads. Times for completion is simultaneously with the bridge structure. The super structure was slid in after a weekend so that the railway was ready for the peak rail operation at the beginning of the working week.

A 500 tonne mobile crane was used for lifting heavy crossheads and beams for bridge construction throughout the project. Some of the bridges including the rail bridge over the motorway are shown in Figure 5.
 
EastLink MotorwayFigure 6: Free flow electronic tolling system
Use of precast segments for construction: The contractor decided to establish a special precasting yard for the manufacture of pre-cast reinforced concrete elements. During the two year operation, the yard produced over 23,000 pre-cast units, of a wide variety from bridge beams and parapet panels to assorted noise wall panels, retaining wall fascia units and bridge pier sections. This ensured tight quality control of all structural elements and other pre-cast products and achieved a better result than that normally achieved by onsite casting. Most of the bridge beams were Super Tee Beams, a V-shaped trough with a flat base and flat projections at the top. The special design was developed in Australia and is now widely used on major road projects. A key advantage of the design is that it can be produced in various depths for different span lengths. The tolling system: A multi-lane free-flow Electronic Toll Collection (ETC) system was used. The recognition by vehicles is automatic through electronic tags mounted inside the vehicle which are not required to slow down or stop as they pass under the toll gantries. This electronic tag complies to agreed standards and can be used throughout Australia on all other toll roads. Along its 39 km length EastLink has 13 tolling points each with two gantries (Figure 6). This tolling system has the ability to handle 4.5 million vehicle passages (transactions) per day. The twin gantries also enable vehicle detection systems to record registration plate details should vehicles not be equipped with the electronic tag. Video tolling is also possible.

EastLink MotorwayFigure 7: Typical coloured noise wall

Noise walls: Over 13,000 noise wall panels were installed. The sections of noise walls were different in shape and colour to improve the visual appearance and better integrate with the surrounding environment and look as natural as possible. Typical wall panels, including transparent sections, as shown at Figures 7 and 8 were manufactured precast at the precast fabrication yard.

EastLink MotorwayFigure 8: A typical noise wall along the Motorway

Road construction: The construction work involved three lanes in each direction for 33 km, two lanes in each direction for 6 km. This involved over 7 million cubic metres of earthworks, 1.1 million tones of asphaltic concrete, and 380,000 cubic metres of concrete. Asphalt laying was a highly coordinated large scale logistics exercise in its own right during construction (Figure 9).

EastLink MotorwayFigure 9: Asphaltic concrete laying

Concluding Remarks
EastLink has proven to be one of the most successful toll road projects in Australia delivered as a Public Private Partnership. Thirty months after opening, traffic growth is continuing at an incredible 10% per annum and neighbouring communities are praise worthy of the delivered outcomes.

Key success factors included clarity in contractual documentation and understanding of the roles of respective parties, early establishment of organisational structures, the rapid recruitment and training of human resources, establishment of a project specific pre-casting yard, bridge construction using standardised pre-cast elements to the maximum extent possible, establishment and retention of highly effective working relationships between the project parties, continuous community engagement and the early resolution of construction issues, as well as environmental enhancements and the provision of urban amenity outcomes throughout the corridor.
Effective Materials Management in Construction Projects
While materials count for a considerable amount of construction costs, the way materials are managed seems to be improvised rather than approached methodically. In the construction industry, one of the common challenges people face

Read more ...

Sustainable Operations Management of High-Rise Project
With an ambition of providing housing for all citizens in India, the drive towards resource efficiency building operations is all-time high given the constraints in allocation of resources and their utilization, writes Mamta Rawat of Conserve

Read more ...

Benefits of Project Management in Developing India’s Infrastructure
During the past couple of years, India has enjoyed the privilege of being amongst the most favored investment destinations of the world. With the sharp vision of Prime Minister Narendra Modi and compelling

Read more ...

Arbitration and Conciliation (Amendment) Ordinance 2015 Provisions & Legal Issues
In a significant development for Indian arbitration law, the President of India has formally adopted the Arbitration and Conciliation (Amendment) Ordinance 2015 (the "Ordinance"), which will bring about major and long-awaited reforms to arbitration in India. The Ordinance amends Arbitration and Conciliation Act 1996 and seeks in particular to eliminate

Read more ...

Raj Kalady
In the last two decades, India has emerged as one of the fastest-growing economies in the world. According to a Citi group report, following the reforms undertaken by Government of India, the GDP is

Read more ...

A Study of Constructability Issues Related to Various Stages of Design and Construction Process
The increasing levels of competition and the introduction of manufacturing concepts within the industry led to specialization. Such specialization led to the separation of design and construction facilities. The increasing complexity of many projects makes it more and more difficult for the designers to be fully aware of all the implications of their

Read more ...

Construction Claims
With growing standards, advanced technologies, and owner-desired additions and changes, construction projects are becoming more and more complex, while the successful completion of projects has been thought to depend mainly

Read more ...

Obligations of Parties & Provisions of Claims in Modern Construction Contracts
Construction contracts usually contain notice-of-claim provisions. The contractor must, within a stated period of time, notify the project owner in writing of any occurrence which may give rise to a claim for additional compensation under the contract. The policy behind these requirements is sound. Owners should have the opportunity to respond to

Read more ...

Termination of Contract
Most commercial construction contracts include provisions allowing either party to terminate a contract for cause (also referred to as a termination for "default"). Unlike terminations for convenience,

Read more ...

Position of Engineer & Independent Engineer In Standard Forms of Contracts
The engineer is generally responsible for issuing the completion certificates and supervising any tests that have been contractually agreed as well as establishing that payments to the Contractor can be made, in funded

Read more ...

Study on Project Schedule and Cost Overruns - Expedite Infrastructure Projects
The KPMG in India – Project Management Institute (PMI) study was initiated on the request of MoSPI, which highlights the major reasons for schedule and cost overruns across major sector's infrastructure

Read more ...

PPP Audit of Infra Project - Importance and Implication
Purnima Bajpai, Reliance Infrastructure, Pune. A contentious issue in the context of PPP arrangements and their audit relates to the scope of audit by Supreme Audit Institutions (SAI), in view of the

Read more ...

Modern Data Collection Techniques for Management of Road Assets
It is now well established that decision on maintenance, rehabilitation and upgradation/ improvement measures needs to be based on an objective assessment (with an analytical approach) to

Read more ...

Management of Quality Quantity and Speed
Management is the need of today. Management has been included in various specialised fields now like environment, tourism, hotel, information technology etc. apart from traditional courses like finance, human resource, operation and marketing. In the management concept, management sets the goals based on quantities for individuals and performance

Read more ...

An Innovative Tool to Teach and Train
The world is expanding and indeed expanding at a breath neck pace, Expansion of our world requires construction of new Industries and Production process from commissioned industries. No

Read more ...

Augmenting Public Private Partnership (PPP) in Infrastructure Projects Through Project Management and Accountable Governance in India
India is only second among the emerging economies next to China. With an average GDP rate of 7.5% and upside, the demand to improvise infrastructure is magnanimous. The average spending capacity

Read more ...

Safety Planning and Administration
Theoretically Safety means the absence of danger at work which is made possible by eliminating hazards that create danger. ILO, in one of their documents, state "A thing is provisionally categorized as safe if the risks are deemed

Read more ...

A Legal Analysis of Some Clausal-Related Disputes in Construction Contracts
The contractor under a construction contract is invariably required to carry out and complete the project by a specified date. This requirement is often accompanied by an obligation to produce a construction programme and to keep it up to

Read more ...

Termination of Contract Under New FIDIC
The termination of a relationship in a construction contract can often come as a surprise causing both confusion and resentment. Negotiations can escalate into protracted and costly disputes. Employers believe their

Read more ...

Construction / Project Management For Highway Tunnels
The topic under discussion has two aspects: (1) Construction of road tunnel, (2) its operation after completion of the job. It is understood that the present issue which is under examination pertains to Rohtang Pass Highway

Read more ...