Foundation Stability of Existing Buildings near Upcoming Structures

Er. Vivek Abhyankar, Deputy GM (Design), L&T, Mumbai & Dr. N. Subramanian, Consulting Structural Engineer, Gaithersburg, MD, USA

There are several failures of buildings and bridges and other constructed facilities; it is important to learn from these failures so that such catastrophes do not occur in the future (Feld and Carper, 1996, Levy and Salvadori, 2002, Raikar, 1987, and Salvadori, 1990). Failure of buildings due to construction of a deep trench in the adjoining plot is not a new phenomenon, although it is undesirable. Recently, a building collapsed in Bengaluru into the adjoining trench which had been dug for a new construction, to replace an iconic theatre building. Similar fatal collapses have occurred in various other parts of India and across the world.

Foundation Stability of Existing Buildings near Upcoming Structures

Manmade trenches and slopes or natural landslides are equally alarming and devastating for existing buildings. A boundary wall of a multistory building in Wadala (Mumbai) collapsed due to a landslide in June 2018. There was the pile foundation failure followed by the complete collapse of a G+13 building in Shanghai (Fig 1 & 2).

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 1: Schematic of the collapse of G +13 building in Shanghai (Subramanian, 2009)

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 2: (a) Building on the verge of collapse (source: Google), (b) Collapsed wall in Wadala, Mumbai near a multi-storey building (Source: www.timesnownews.com)

Fundamental Behavior of Soil and the Phenomenon of Building Collapse Due to Adjoining Excavation
Earth or soil has a defined safe bearing capacity, which is derived from the adhesion between soil particles and their shear strength based on its Cohesion C and angle of internal friction φ. Another important criterion for deciding the SBC of soil strata is the settlement. The shear strength and settlement are dependent on the Cohesion C, angle of internal friction φ, void ratio and the internal pore water pressure. A typical three phase diagram of soil is indicated in fig. 3 (ref. NPTEL courses). When the air voids get filled with water during rainy season or for other reasons, then there is buoyancy as well as loss in shear strength of soil.

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 3: Three phase system of soil

When the soil is loaded with surcharge on the top, the behavior differs as per the particle size (sand, silt or clay); but primarily the voids may get compressed and there will be a lateral movement to maintain the volumetric stability (Poison’s effect). This generates the lateral earth pressure; and depending on the freedom of movement it could be further classified as – ‘active’, ‘passive’ or ‘at rest’ earth pressure.

Now let us image a building adjoining to which a trench is excavated. Excavation of trench leads to imbalance of forces in the soil particles on the vertical face of the trench. If the shear strength (Q = C + σ tanφ) is higher than that of the unbalanced lateral force (ka.γ.H) then the vertical cut is stable, for example, often we find several workers / plumber / electrical or telephone line repair workers dig small size trenches adjacent to the building and fill back after the repair work is over, but the building does not collapse. But if the trench size is enormously large and deep (extending below the foundation level, or ground water table or if the sides of the trench is un-protected or if there is seismic activity or heavy rains, etc) then there is always a danger of collapse of the building.

The excavation contractor should always consult qualified and experienced structural /geotechnical engineer to ‘maintain’ proper equilibrium of forces on the cut earth face. Depending on – (1) the type of strata (soil, silt, clay, gravel, rock, mixed strata), (2) depth of the excavation, (3) extent of pore water pressure, (4) extent of surface surcharge, i.e. weight of building, (5) seismic zone, (6) duration of exposed cut, and (7) distance of the cut from existing building foundations, a suitable treatment should be provided, as described further in this paper (See also Yu, S., and Geng, 2009).

Case Studies
In urban areas, the cost of every foot of a land is very high, hence we notice very congested development of plots almost touching each other (Fig. 4 and 5 show typical structures in congested areas of a few metro cities in India).

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 4: Densely populated houses in (a) Delhi and (b) Mumbai city (Source: Google)

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 5: Densely populated houses in (a) Kolkata and (b) Chennai city (Source: Google)

Due to the high land cost in cities, the land owners often explore the option of ‘underground basements’. When deep excavations are done very close to the existing buildings, there will be large lateral deflection of the retaining wall, which will lead to movement of ground below the foundation of existing building and subsequent cracks and tilting of the building (Fig. 6)

Foundation Stability of Existing Buildings near Upcoming StructuresFigure 6: Lateral deflection of the excavated face, followed by sinking / rotation of adjoining building (Source: Tang, 2014)

1990 Excavation Collapse at 14th and H Streets, N.W. Washington, D.C.
An open excavation, 150 ft. x 208 ft. by 47 ft. deep for a 12-story office building with four levels of parking at 14th and H Streets, N.W., Washington, D.C., collapsed on November 19, 1990 at approximately 8:30 p.m (Fig 7). Construction had stopped for the day at the time of this accident. Hence no injury or death was reported, though there was significant potential for casualties.

Foundation Stability of Existing Buildings near Upcoming Structures

The National Office of the Occupational Safety and Health Administration (OSHA) investigation began soon after the accident and included observation of the collapsed structure and geotechnical and structural analysis of the excavation support system. Based on this investigation, OSHA concluded that:
  • The internal support system erected at the construction site, was not capable of resisting the soil load which could be reasonably expected. Certain members and their connections were not adequately designed to suit the field conditions for the expected loads.
  • The spacer beams (outlooker beams) between the wale and the soldier beams and their connections and the sloping wale were most highly stressed and contributed to the collapse.
2009 Pile foundation failure and subsequent collapse of a G+13 building in Shanghai
On June 27, 2009 at 5.30 am, an unoccupied 13-storey block of flat building, still under construction, at Lianhuanan Road in the Minhang district of Shanghai city, China toppled over and ended up lying on its side in a muddy construction field (See Fig. 1 and 8). One worker was killed. The investigation report concluded that this collapse was caused by earth, excavated along the building on one side with a depth of 4.6 m, for an underground car park, and piled up to heights of up to 10 m on the other side of the structure, as seen in Fig. 1 and 8 (Subramanian, 2009, and Wang et al., 2017). The weight of overburden earth created a pressure differential, eventually weakening the foundations and causing them to fail. This situation might have been aggravated by several days of heavy rain leading up to the collapse.

2018 Landslide near a multistory building in Wadala, Mumbai
In June 2018, the compound wall of Lloyd Estate in Wadala, Mumbai collapsed, leading to several cars caving into the neighbouring under-construction site of Dosti Realty, loose soil from the spot slid away, triggering fears of another landslide at the spot [see Fig. 2(b)].

2020 Collapse of two buildings into adjacent trench in Bengaluru
On July 29, 2020, right behind what was once the iconic Kapali Cinema Theatre in the Majestic area, Bengaluru, two leaning buildings (three-storey hotel and a four-storey PG accommodation), collapsed but fortunately there were no casualties as the police had evacuated all the inhabitants. The building contractor had dug a 65-foot-deep trench (to build four basements, a ground floor and five floors on a 50,000 sq foot plot), without putting in place adequate support. This apparently caused the two adjacent buildings to collapse into the trench. The Majestic area once had ponds and lakes and it is speculated that the raising ground water might have contributed to the weakening of the soil and subsequent collapse of the buildings into the trench, whose three sides were only soil nailed and without constructing any retaining structure (see Fig. 9).

Foundation Stability of Existing Buildings near Upcoming Structures

Treatments to Avoid Such Failures
As mentioned earlier, the treatment of exposed surfaces depend on (1) the type of strata (soil, silt, clay, gravel, rock, mixed strata), (2) depth of the excavation, (3) extent of pore water pressure, (4) extent of surface surcharge, i.e. weight of building, (5) seismic zone, (6) duration of exposed cut, and (7) distance of the cut from existing building foundations.

Following are the popular treatments:

1. Bare Exposed face – When the depth of cut is fairly shallow, the loads/surcharge is lesser in magnitude or located far away, the soil is sufficiently strong (hard rock or weathered rock) and the duration of exposed cut is short (one or two weeks) then the slope need not be treated after consultation with the competent authority.

2. Exposed face with shotcrete – When all the conditions are same as case one but there is minor seepage from crevices in the strata or fear of falling soil particles from the exposed face pockets, then same can be addressed using shotcrete. In some cases the shotcrete could be supported with a wire mesh. Such slopes can fairly work for longer time and depths up to 2 to 3m. But care should be taken that the seepage is not pronounced; otherwise it may endanger the bonding of shotcrete with the strata.

3. Soldier piles and timber planks lagging – When the soil is strong but with higher loads, and shallow depth of the cut, solider piles and timber planks lagging as shown in Fig. 10.

4. Cantilever Sheet pile protected face – When deeper excavation (say up to 5 to 6m depth) is carried out to retain comparatively heavy surcharge (say up to G+5 storey building with foundation depth deeper than the excavation), with fairly good soil strata and for a longer duration of pit but without any seepage estimated from the base of the pit and when stringent limit on the soil settlement/movements at the tip of the wall, then cantilever sheet pile wall is a good solution.

Steel sheet piles can also be used to retain railway/road embankments while doing excavation closer to the tracks. Steel sheet piles are slightly costlier and required to be driven with the vibro-hammers. They are reusable; a greater number of repetitions can recover the initial investment cost. But while driving the piles adjacent to buildings with fragile glass façade, care shall be taken to reduce the vibrations generated during the pile driving operations (otherwise, breaking of glass panels may occur and be reported).

Anchored Sheet pile protected face – In conditions same as above but with larger depth of excavations and stringent control on the soil settlements/movement at the top of the wall, it is better to use a waler beam and anchors to support the wall at the top, also as shown in Fig.11.

Foundation Stability of Existing Buildings near Upcoming Structures

In some cases, instead of using rolled interlocked steel sheet piles, the contractors also have used hollow sheet circular liner to retain the soil. In some of the cases, the passive anchors are not possible or permitted to be used (private property outside or a water body, etc.); in such cases instead of using prestressed anchors often the struts are used from outside, as shown in Fig. 12. In underground metro stations, this is a popular option.

The analysis of these problems can be done using software programs like Plaxis 2D, Wall-up and Midas NX-GTX, Geo-Studio, Deep-Ex etc. When the soil retention problem is more advanced in terms of loads, precision, depth, and time duration, then a permanent solution is required. Following methods of construction provides a permanent solution for the earth retention near the buildings (Fig 13).
  1. Continuous (touching) piled wall
  2. Secant pile wall.
  3. Diaphragm walls.
Foundation Stability of Existing Buildings near Upcoming StructuresFigure 13: (a) Continuous piled wall, (b) Secant pile wall and (c) Diaphragm walls

Instrumentation and Monitoring
In major and long duration projects (like underground metros or deep basements of buildings), during construction, the ground movement of adjoining structures may tilt, shift or settle and hence need to be monitored carefully. Tilto-meters, crack monitoring devices, gauges etc., need to be planned and carefully installed, maintained and monitored on a daily/weekly basis (as per the nature of the job). The stresses in the struts are also monitored and denoted as – (a) GREEN or Safe level, (b) BLUE Level (i.e. maintenance cycle to start), (c) YELLOW Level or Alert level (i.e. force exceeded the safe limit but within yield), (d)RED Level or Alarm level (force is reaching towards yield limit – prestressing to be done).

Summary and Conclusions
Failure of buildings due to construction of deep trench in the adjoining plot is uncommon and undesirable; however such failures have been witnessed in the past. A few past case studies are described which include (1) the 1990 excavation collapse at 14th and H Streets, N.W. Washington, D.C, USA, (2) the 2009 pile foundation failure and subsequent collapse of a G+13 building in Shanghai, China, (3) The 2018 landslide near a multistory building in Wadala, Mumbai and (4) the recent collapse of two buildings into adjacent trench in Bengaluru.

Treatments have to be done to the exposed vertical cut surfaces in order to avoid such failures. The type of treatment depends on (1) the type of strata (soil, silt, clay, gravel, rock, mixed strata), (2) depth of the excavation, (3) extent of pore water pressure, (4) extent of surface surcharge, i.e. weight of building, (5) seismic zone, (6) duration of exposed cut (7) distance of the cut from existing building foundations. The possible treatments include (1) leaving the bare exposed face as it is, in the case of shallow cuts, (2) Applying shotcrete to the exposed face of soil with or without wire mesh, (3) Providing soldier piles and timber planks lagging, (4) Providing cantilever sheet pile protected face, (5) providing anchored sheet pile protected face, (6) having continuous piled wall, (7) constructing a secant pile wall, and (8) building a diaphragm wall. In major long duration projects, it may be necessary to continuously monitor the ground movement and take appropriate action.

References
  • Feld, J., and Carper, K.L. (1996), Construction Failure, 2nd Edition, Wiley Inter-science, New York, 528pp.
  • Jin, J.S., M. Ayub and F. Liu (1991) “Investigation of November 19, 1990, Excavation Collapse at 14th and H Streets, N.W. Washington, D.C.”, U.S. Department of Labor, Occupational Safety and Health Administration, Washington, D.C., 109 pp. https://www.osha.gov/sites/default/files/2020-01/1991_05.pdf
  • Levy, M., and Salvadori, M. (2002) Why Buildings Fall Down: How Structures Fail, W.W. Norton & Co., New York, 336pp.
  • Raikar, R. N. (1987) Learning from Failures: Deficiencies in Design, Construction and Service, R&D Centre, Structwel Designers & Consultants, Mumbai, 423 pp.
  • Salvadori, M. (1990) Why Building Stand Up, The Strength of Architecture, W. W. Norton & Company, New York, 320 pp.
  • Subramanian, N. (2009) Rare Foundation Failure of a Building in Shanghai, China, New Building Materials & Construction World (NBM & CW), Aug., pp.100-105
  • Tang, Y.-G.(2014) “Probability-based serviceability evaluation of buildings adjacent to an excavation using random finite element method”, International Journal of Computational Methods, Vol. 11, No.2, Mar. 21 pp. https://doi.org/10.1142/S0219876213420061
  • Yu, S., and Geng, Y., (2019) “Influence Analysis of Underground Excavation on the Adjacent Buildings and Surrounding Soil Based on Scale Model Test”, Advances in Civil Engineering, Jan., pp.1-15. https://doi.org/10.1155/2019/6527175
  • Wang W. D., Q. Li, Y. Hu, J. W. Shi, and C.W.W. Ng (2017), “Field Investigation of Collapse of a 13-Story High-Rise Residential Building in Shanghai”, Journal of Performance of Constructed Facilities, ASCE, Vol. 31, No.4, Aug.
  • ASCE website and various newspapers feeds
Considerations for Site Selection for Engineering Plant Projects
Site selection is the first and most important factor for location of any Engineering Plant Project as they involve huge construction costs. An unsuitable or wrong project site can result in great loss and may also lead to delays or failure of the project. Anil Kumar Nanda

Read more ...

Construction Mishaps - A Question Mark on Quality & Safety
Zainab Faridi compiles a series of recent construction mishaps that not only underscore the perils faced by Indian construction workers but also expose the urgent need for stricter quality check parameters, a skilled workforce, accountable project management

Read more ...

Decarbonizing Construction Industry for a Greener Future
A recent report by Deliotte - Shell indicates that the construction sector accounts for 37% of global CO2 emissions, of which 16% represent embodied carbon, that is carbon dioxide coming from material sourcing and manufacturing, logistics, and construction

Read more ...

Policy Prescription for Circular Economy to Boost Infra Construction
At a time when India is pushing policy reforms in a big way to provide a major boost to its economy, the generation of colossal 9.46 million tons of plastic waste every year and 150 metric tons of construction waste annually (about 40% of the global

Read more ...

7 Years of RERA Of Promising Gains, Challenges & Pitfalls
After seven years of its journey, the landmark reform of RERA (Real Estate Regulatory Act) has made some remarkable gains in terms of regulating the sector and protecting the interests of homebuyers. Especially considering that two crucial years were

Read more ...

National Ropeway Development Programme to Boost Real Estate
A massive USD 15 billion National Ropeway Development Programme of the Central Government, currently underway, will provide a major aerial connectivity boost to real estate, especially in Tier 2-3 cities that have high tourism potential. A Rs 1.25 lakh crore

Read more ...

J&K Realty and Infrastructure Development on Fast Track
As Jammu & Kashmir prepares to host G-20 Tourism Meet in Srinagar from 22-24 May 2023, the strides made by the Union Territory on urban development (in a run up to this conclave following the abrogation of Article 370 in August 2019), will provide

Read more ...

Ashoka Buildcon Achieves Largest Continuous Concrete Pour for Building Project
Ashoka Buildcon Limited has several prestigious projects under its belt and has to its credit notable record-breaking achievements - the latest being casting of a raft with 12400 cubic meters of concrete. With this feat, the company is eager to get

Read more ...

Investment Bonanza in UP to Fast-Track - Real Estate & Infrastructure Development
Riding high on landmark reforms and performance-driven governance, Uttar Pradesh has received a record investment proposals of over 33.50 trillion from Indian and foreign investors at the recently organised 3-day Global Investor Summit (GIS) in Lucknow

Read more ...

Mega Projects: Redefining Geographies
Mega infrastructure projects like flyovers, elevated roads, highways, metros, bridges, tunnels, expressways, etc, are redefining how we interact with our surroundings; in fact, Infrastructure is intrinsically linked to everyday life and is a defining

Read more ...

Major Connectivity Projects to Transform Urban Development Landscape of Delhi-NCR
With some state elections and general elections in sight, the Modi government has pulled out all stops to put its mega infrastructure projects on fast track for the socio-economic upliftment of people. A number of such key infrastructure projects

Read more ...

Women in Construction - Diverse Perspectives Will Drive Progress
India’s construction industry is advancing and embracing new technologies, and thereby throwing up exciting opportunities for women to grow professionally in traditionally male-dominated roles. With the advent of robotics, digital twins, and remote

Read more ...

Dola Roychowdhury - Founder Director, GCube Consulting Engineers LLP
The pay parity issue is very subtle and fragmented. It doesn't exist at entry levels any longer - but tends to widen as you go up the chain and hit that invisible ceiling. Compared to the global gender ratio of about 12%, India's female ratio is much lowe

Read more ...

Minimol Korulla - Maccaferri ISEAP
The global Infrastructure Construction industry currently has a female workforce ratio of 10% to 14%, while in India it is 8% to 12%. However, the representation of women in senior managerial roles is less than 2% - both globally and in India. The lack

Read more ...

Rubee Kongbrailatpam - Public Works Department, Manipur
The shift in perspective towards women's roles in the construction industry and the de-genderization of roles is a significant step towards creating a more inclusive and diverse workforce. Stereotypes and prejudices against women in construction

Read more ...

Dr. Ambika Behl - CSIR-Central Road Research Institute
Gender-based discrimination, the harsh work environment of construction sites, lack of knowledge about the industry, and a shortage of successful women in construction as role models, present significant barriers to entry for women. In India, the

Read more ...

Atasi Das -  G R Infraprojects, Gurugram
It's time to change the myth that "the infrastructure industry is a man's world and that it is not really a place for women." By promoting equal opportunities and gender sensitivity in the workplace, we can encourage more women to pursue a career in

Read more ...

Shruti Choudhari - BL Kashyap and Sons
Over the past decade, we have witnessed significant changes at BL Kashyap, including women-led planning, design, and HR departments. We have a majority of women in the tender and contracts department as well as women on-site in key roles during

Read more ...

Sandhya Rasakatla - Hindustan Zinc
Gender-based bias and stereotypes continue to be prevalent in many industries, including the construction industry, where women often face challenges due to the perception that they are less capable than men. However, it is important to recognize

Read more ...

Yogeshwari Rane - Hindustan Zinc
As we are moving towards highly mechanized mines, the overall perception of mining industry as a male-dominated industry is changing since it is no more about just physical labour. As the mining industry has traditionally been considered a physically

Read more ...