Confronting Issues: 12fth Plan Infrastructure Development Confronting Issues: 12fth Plan Infrastructure Development
Confronting Issues: 12fth Plan Infrastructure Development Confronting Issues: 12fth Plan Infrastructure Development

Various issues need to be addressed for the realization of infrastructure development initiative by the government during 12fth plan, reports P.P. Basistha.

The government has targeted a mammoth capital investment of $1 trillion for the development of infrastructure sector. However, before channelizing the investment for the infrastructure development programmes, many issues involving pre-feasibility studies, finance, litigation and others will have to be addressed, in order to neutralize time and cost overruns on the part of the project implementing agencies and developers.

A major issue that primarily needs to be addressed, is linking of funds with the pace of the project developments during different phases of construction. The implementing agencies and the contractors now regret that flow of funds are not actually linked to the pace of the development of the project. According to Mr. Chakanbabu, Executive Director, Central Public Works Department, “large scale cost overruns take place as the flow of funds from the implementing agencies are not synchronized according to the project schedules. Faced with delayed release of payments, the contractors ultimately resort to arbitration, as a result the project implementing agencies finally end up in paying up the contractor, eventually raising the cost of the project.” He explains, “the basis for liking of funds to the projects is actually based on the nature of the project. A project in its initial stages may need good deal of excavation or foundation work to be carried out, requiring adequate finances but in many cases owing to inadequate funding leading to cost and time overruns occurs to the project.”

Echoing his viewpoint, Mr. S.S. Johar, Chairman, C&C Constructions stating, “delay in approvals increases capital investments for the project. Dispute settlement process continues to be time consuming between the contractor and project implementing agencies. Delay in approvals continue to take place from local bodies. As a reason, actual project estimates made by the contractors goes haywire resultantly delaying the project.” “Despite the project being approved, providing physical possession of the land to the contractor gets extended by the project implementing agencies owing to lack of timely clearances.”

Agrees Mr. S.K. Kulkarni, Head-Business Development, GMR Highways says, “to make the projects commercially sustainable for the contractor, it is vital that frequent design changes have to be curtailed by the project implementing agencies. The overloading of vehicles should be stopped to minimize the maintenance cost of the BoT project developers.”

Confronting Issues: 12fth Plan Infrastructure Development

Obtaining timely clearances from local and other bodies continues to be major contentious issue behind development of projects. Mr. N Seethaiah, MD, Madhucon, Project Limited points out saying, “obtaining permission from the railways for constructing road over bridges, takes lot of time. Besides, getting right of way for aggregate quarries both for hydro, road and other core infrastructure projects by the contractor gets delayed, as the project implementing agencies, as well as the client continues to leave the onus of the same with the contractor. It is quite important that implementing agencies like NHAI or NHPC should get in place the right of way at the conceptualizing stage of the project.” According to Mr. Seethaiah, “single window departments should be in place at the central and state levels for project clearances where multiple bodies are involved.” Similar views are endorsed by Mr. Y.R. Patel, Chief Coordinator, Civil, Patel Infrastructure Private Limited. He says, “it is much pertinent that at least 80% of the land should be in possession with the project implementing agencies which is not the case.”

Mr. Nihar Ranjan. Dash, Director, Ministry of Steel points out, “getting possession of land and iron ore mines to support greenfield steel units continues to be major issue both with the government and private sector. The issues may be of local, the state and of central levels.” Getting possession of Chiria mines by steel authority of India Limited for the brown field expansion of its flagship Bhilai steel plant got delayed, before the PSU steel producing major finally got possession of the same owing to delayed environmental clearances at the central and state levels.

Private Investment

Confronting Issues: 12fth Plan Infrastructure Development
According to the infrastructure investment programme of the government, sizeable part of the targeted investment will come from private sector during the 12th plan period. Speaking at the recent conference on public private partnership in the development of infrastructure, Prime Minister, Dr. Manmohan Singh said, “PPP will continue to be the preferred mode of the government for development of infrastructure, as it will improve the quality of the projects as desirable construction practices will be put in place supported by the government. The ‘Model Concession Agreement (MCA) procedure of the government has been successful in attracting private investments in road, port and airport infrastructure development programme. However, it is quite important to note that, preliminary study, essentially involving bankability of the projects and finally their awarding is done in an appropriate manner, so the project becomes sustainable in the long run for the implementing agencies as well as the contractor.”

Confronting Issues: 12fth Plan Infrastructure Development
Making the projects bankable is a major issue for the present public private partnership initiative of the government. Experts unanimously point out that the loophole lies in improper selection of the project consultants by the project implementing agencies and project contractors for the preparation of the detailed feasibility report of the concerned project. According to Dr. M.L. Roychowdhury, Senior Project Consultant, Ghezri Eastern India Limited and Faculty of Civil Engineering, IIT Kharagpur and Dr. M. Bhowmick, Senior Faculty, Transportation, Indian Institute Management Kolkata, “making an appropriate assessment of traffic flow in any road or port infrastructure project is a much critical task. Estimated traffic flow in the project can go through changes owing to socio-economic factors, political, domestic as well as international economic factors. Assessment of the present and future situation is of vital importance. It should take into account holistic factors, to somewhat make an appropriate traffic projection by the project implementing agencies and that is where the role of consultants engaged for preparing the DPR’s actually come in to identify a bankable project, the area ironically which leaves much to be desired from consultants."

Confronting Issues: 12fth Plan Infrastructure Development

The experts point out examples of projects involving newly commissioned International Container Transshipment Terminal at Cochin by Dubai Ports World, or expansion of iron ore and coal handling terminal by Paradip Port, Hooghly River Bridge or second Bally or Vivekananda Bridge in Kolkata created through colossal investments. Second Bally bridge is the largest ever PPP initiative formed through a consortium of Indian and foreign companies. All the projects are yet to attain the desired commercial viability owing to inadequate traffic flows or volatility in traffic. The observations to an extent are approved by Mr. K. Suresh, Principal Secretary, Planning, Government of Madhya Pradesh, Member Secretary State Planning Commission and previous Chairman Chennai Port Trust.

However, speaking to NBM&CW, Mr. Pratip Chaudhuri, MD, State Bank of India & Ms. Chanda Kocchar, MD, ICICI Bank said, “it is pertinent that to make a more realistic assessment of traffic flows, historical traffic data should be made available by the state and the central government bodies to the project consultants. This will allow identification of bankable projects. On top of inadequate data, two to three weeks time is given to bidders for submission of request for qualification, which is grossly inadequate as they are not able to carry out bankability studies for the proposed project.” They said, “electronic tax collections should be in place to prevent possible leakage of revenue flow from the projects. Standardization of traffic flow studies have to be done. Due to non availability of standardized studies, financial leakage from the project takes place, as a result the projected cash flow is not realised from the infrastructure project.”

Confronting Issues: 12fth Plan Infrastructure Development
They insist, “to make GDP grow at 9 percent, it will be always essential for the government to develop infrastructure, as a reason issues of funding, especially those involving long gestation period will have to be addressed. Setting up of infrastructure, debt funding have to be made. Projects attracting less premium will have to be supported by viability gap funding.”

However apart from requisite financing, there are manifold risks that need to be addressed by project implementing agencies for timely completion of the projects. According to Mr. Kamal Verma, CEO, SREI Infrastructure, “there are prevailing risks in way of timely completion of projects. It is quite necessary that the risks should be identified and solutions to tackle the risks are put in place well in advance during the conceptuali- zation of the project.” He elaborated, “the risks are in nature of market revenue, design operating (for PPP projects), construction in terms of design, legal, environmental, and political.”

Confronting Issues: 12fth Plan Infrastructure Development

Legal risk is a major area of concern that should to be addressed. Expansion of major port projects, involving high capital investment have been slowed down by litigation issues. This is despite the government having a proper revenue sharing agreement in place for the concessionaire. Having been long overdue, the bidding process for Jawaharlal Nehru Port Trust’s 4th container terminal finally got through after four years, not before Mundra Port and Special Economic Zone (MPSEZ), moved the Mumbai high court after it was declared security clearance for the project by the Union Government. The lag in project was also due to a case fought by APM-Terminals after it was excluded from bidding due to a Government Policy. Bidders for the project included, DP world Private Limited, MPSEZ, Adani Enterprises Limited-Isolux Corsan Concessions SA, GVK Developmental Projects Private Limited, Samsung C&T Corp and Sterlite Industries (India)-Leighton Contractors (India) Pvt Limited.

The project is likely to be developed by PSA-ABG, emerging as the highest bidder, would be India’s largest container terminal by capacity and cost. The terminal will handle about 4 million TEU’s a year. However, commissioning of the terminal is projected to face cost escalation by about Rs.1,000 crore from its original cost of Rs.6,700 crore owing to two years delay over litigation. According to Shipping Ministry, there would be escalation clause for the project. The terminal is expected to take two years to complete post awarding of the tenders. However, as per recent reports, PSA is expressing its apprehensions in signing the concession agreement. The component of the 4th terminal will include construction of back yards, berths having length of 2kms.

The importance of addressing the confronting issues emanates from the fact that, in the present context of economic volatility, getting requisite finance back up for long- term projects is getting difficult owing to lesser availability of finance. Protracted delay in creating new projects, arising out of the issues may delay finance availability altogether, thereby hurting the business interest of all stakeholders in the sector in mid-term and long-term. This will ultimately take its toll on the economic growth.
Godrej Appliances Awards Contract for End-To-End Supply Chain to Delhivery Ltd.
Godrej Appliances, a business unit of Godrej & Boyce, has awarded the contract to build and manage the pan-India supply chain for their air-cooler business to Delhivery Ltd., a largest fully integrated logistics provider. Through this partnership, Delhivery

Read more ...

Infrastructure Sector to See Pre-Poll Boost in FY 2023-24
Having faced headwinds with slow pace of highway construction and port modernisation, besides project delays, the infrastructure sector is now set for a major boost in the pre-poll year of 2023, with a major budgetary and policy push from the

Read more ...

Construction costs up by 28% as of Nov 2022 but remain stable since March 2022: Colliers
As of November 2022, cost of construction has increased by 28% which is higher than the pre-pandemic (November 2019) levels; but continues to be stable compared to March 2022. The costs of key construction materials have jumped 32% in a span of three

Read more ...

Why Investors in India are Pivoting to REITs
Investment, income generation, and wealth creation are the cornerstone for living a purpose-driven and meaningful life. Traditionally, there have been two sources of investment and income generation- Real estate and stock market. In India and in other Asian economies

Read more ...

Real Estate in Resurgent Mode
Despite the severe global headwinds hitting the economy and leading to high inflation, the real estate sector, supported by the progressive government policies, has not only stood its ground, but has displayed remarkable growth. As the sector continues

Read more ...

Rise of Small Cities
Buoyed by the growing economic and business base, fast expanding infrastructure and connectivity, Tier 2 and Tier 3 cities are the new growth boosters of real estate. Particularly, post-pandemic, these cities have gained momentum to

Read more ...

One Year of PM Gati Shakti Expanding Frontiers
Launched in October 2021, the GIS- based Gati Shakti platform captures all utilities and network linkages in making it possible for various infrastructure focused ministries and departments to come together and take a coordinated approach towards faster

Read more ...

Asset Monetization picks pace; NHAI looks to fast-track asset monetization process; Fastag toll collections continue upswing
According to the latest Infrastructure report by Motilal Oswal Financial Services, 1H FY23 has been muted with only 810 kms of projects awarded till date. Owing to the weak 1H, NHAI would have to accelerate project awarding in 2H FY23 in order to meet its

Read more ...

Construction of GTI GX Wall as Dump Wall for Mining
Development of Gabion Wall (700m length, max height of 34m, and average height 25m Length) on east side of East Cell Red Mud Pond (RMP), including Design, Vetting, and SPCB Approval for Vedanta, Odisha. Due to space constraint, client wanted to construct soil

Read more ...

National Logistics Policy An Economic Booster
The National Logistics Policy (NLP) aimed at developing a technologically enabled, integrated, cost-efficient, resilient, sustainable, and trusted ecosystem for accelerated and inclusive growth, is giving a push to real estate and infrastructure

Read more ...

Upward Momentum Continues in Real Estate Sector in 2022: CBRE- CII
CBRE South Asia released its ‘Indian Realty – charting the growth roadmap for 2022’ report at CII Realty 2022 - 18th Edition of Conference Real Estate. The CBRE-CII joint report highlights key trends and projections for the Indian Real Estate sector for 2022

Read more ...

Only one-fourth of the road assets moved out of rough patch, post default: ICRA
ICRA has conducted a study of 1201 Build-Operate-Transfer (BOT) road projects which have defaulted during the period FY2011 – FY2022. Out of the 120 projects, 86 have defaulted during the operational phase while 34 projects defaulted during

Read more ...

InvITs: Why you need to include them in your investment portfolio
At a time when most traditional investment fields are yielding low returns, InvITs are emerging as a brilliant investment option for people looking for a diverse portfolio and who wish to stay invested for the long term. Nitan Chhatwal, MD, Shrem InvIT

Read more ...

Festive Realty Top Ten Trends to Drive Home Sales
The post-covid residential sales momentum is set to get a further boost in this festive season, notwithstanding headwinds in the form of rising interest rates and increase in home prices. Here are the Top 10 trends that will help drive festive home demand

Read more ...

Realty@75 - Reformed, Regulated, Reinvented & Responsible
Over the last 75 years of India’s Independence, the real estate sector has come a long way from an unorganised, unregulated family business to a corporatized, well-regulated, reformed, transparent, responsible, and future-ready industry. Vinod Behl

Read more ...

Growth & Trends Across All Real Estate Segments
Real estate investments register strong capital inflows, reach USD 3.4 billion in H1 2022. Foreign investors accounted for over 67% of total investment volume in Q2 2022. Office sector dominated investment activity with a share of about 57%

Read more ...

Land Monetization Promises & Pitfalls
A mega land monetisation plan through sale of surplus government and PSUs’ land is a part of Modi government’s ambitious National Monetisation Programme (NMP) to generate Rs 6 lakh crore of revenue over FY 2022-25. The success of this programme will depend

Read more ...

Making Urban India Sustainable Through Green Buildings
Buildings offer a huge opportunity to minimize energy consumption by merely changing the manner in which they are planned, constructed and operated. Jit Kumar Gupta, Retired Urban Planner, Advisor Town Planning, Punjab Urban Development Authority

Read more ...

Road Ahead for Real Estate Prospects & Challenges
The recent headwinds in the form of higher cost of construction and interest rates may only have some short-term impact on the recovery of the real estate sector, post-covid. The mid to long-term growth prospects, however, remain intact due to strong fundamentals

Read more ...

Infrastructure Development in India 2023 & Beyond
India’s infrastructure outlook over the next decade presents a bright picture. It is lined with attractive government schemes and a pipeline of major projects - supported by significant funding and financing. For construction equipment manufacturers

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.
Click here to subscribe.
×