Well Foundations for Bridges are Obsolete

S.A.Reddi, Fellow Indian National Academy of Engineering

Introduction

Bridge foundations are the most complicated and difficult to construct. Unexpected difficulties cause delays, extra costs and revision of designs due to altered situations. Loss of human lives was normal rather than exception. In the Sixties, more than 50 lives were lost due to the accident during pneumatic sinking operations for well foundations of Mahanadi bridge in Orissa. For Kali Bridge at Karwar in Karnataka, pneumatic sinking was required for inspection of the founding surface of the wells. Apart from delays and extra costs, large number of workers suffered caisson disease. Due to difficulties in well sinking, two contractors left the job and the third took more than 5 years to complete the well foundations. Alternative construction techniques and equipments have emerged. With the introduction of advanced piling equipment, large diameter piles up to 3.5 m dia are easily realized at a fast rate, with a significant reduction in cost and material quantities. Bridges elsewhere are now constructed with pile foundations.

Well Foundations for Bridges are Obsolete
Figure 1: Brahmaputra bridge foundations No. 17 & 18
Pre-cast RC bored piles of 2.5m diameter was first successfully realized in India for the old Thana Creek Bridge constructed in 1960s. For the 13 Km long Saudi–Baharain Causeway large diameter pre-cast pre-stressed bored piles were adopted. By 2005, piles of 2-3 m dia, upto 120m deep are extensively used in the rest of the world. These new techniques eliminate complicated weather-dependent and risky operations in water. They have reduced the delays considerably and minimized the technical and financial risks. The development of modern techniques has considerably reduced quantities of materials used for foundations as well as energy consumption and environmental impacts.

Well Foundation Problems at Brahmaputra Bridge at Tezpur

The bridge was more than 3 km long with 26 spans of 120 m and 2 shore spans of 70 m each, founded on 12m dia Wells. Sinking well No.2 to full depth was not possible due to bouldery strata Despite best efforts, the well only went down by 35.25 m after three seasons and at extra cost! The well was plugged at RL 32.075 m and 5 nos 1.5 m dia RCC bored piles (25-35m) were provided to anchor the well, one in the middle through the dredge hole and 4 outside at the four corners. Further a launching apron of crated boulder 3 m thick was laid making a circle of 60 m dia around the well, at RL 61.00. These extra works caused further delay in the comp- letion of the substructure works.

This section of the article is only available for our subscribers. Please click here to subscribe to a subscription plan to view this part of the article.

Click Here
To Know More or to Contact the Manufacturer
Please let us know your name.
Invalid Input
Please let us know your Designation.
Please let us know your Contact Number.
Please let us know your email address.
Please brief your query.
Our other Value-Added Services:

To receive updates through e-mail on Products, New Technologies & Equipment, please select the Product Category(s) you are interested in and click 'Submit'. This will help you save time plus you will get the best price quotations from many manufacturers, which you can then evaluate and negotiate.

Invalid Input
Invalid Input
Invalid Input
As part of Northeast Policy, the Ministry of Railways took up the project of providing rail connectivity to Imphal in Manipur state. As per the detailed survey, the rail alignment takes off from existing Jiribam

Read more ...

Brahmaputra is one of the longest river in Asia with a total length of 2880 km & out of which 920km (approx.) lie in India. The New Brahmaputra Bridge @ Tezpur is one of the most challenging one, in the attempt to bridge

Read more ...

The road and railway crossing across the Brahmaputra on National Highway-52B is located at Bogibeel, about 17km downstream of Dibrugarh in Assam. The location is an area of high intensity rainfall (the annual rainfall ranges

Read more ...

The world has progressed beyond imaginations. Similar to the field of IT, Civil Engineering has also taken several steps forward to bring out innovative technologies to meet challenges of this world’s aspirations. Going forward from

Read more ...

The bridge lies in the state of Assam, but this location is usually referred to as upper Assam as it is far away from Guwahati and bordering China. The nearest airport is Dibrugarh. Then there is a drive of 65km into the

Read more ...

The Infrastructure Industry is continuously evolving; new roads, elevated corridors, expressways, railways, dedicated corridors, metros, mono-rails are being constructed all the time. They also require constant

Read more ...

The 6.5 feet wide walkway in the Hongyagu Scenic Area in Hebei province hangs 755 feet above the ground, and is the world's longest bridge, which opened in 2017-end. Designed by Tel Aviv architect Haim Dotan

Read more ...

Prestressed Concrete (PSC) structures especially bridges are being largely used all over the world due to their multifarious advantages in terms of structural behaviour, economy as well as aesthetical

Read more ...

Four Span Pipe Bridge
Distressed structures require necessary remedial measures in order to restore their original structural properties like strength and stiffness. Validating the effectiveness of the proposed qualitative remedial

Read more ...

Foot Bridges
Footbridges have a longer history than road or railway bridges. Ancient footbridges comprised of natural materials such as roots of trees, ropes, stones, masonry, and wood. Modern footbridges are built

Read more ...

Thane Creek Bridge
Load testing is done to determine the safe load carrying capacity of structures, determining if specific legal or overweight vehicles can safely cross the structure or needs to be restricted and the level of post

Read more ...

Bridge in Central Kerala
Cement concrete is a versatile building material and is the second most consumed material in the world, after water. It is made using porland cement, coarse, and fine aggregates, water and one or more

Read more ...

Concrete Road Bridges
Planning, design and construction of bridges and flyovers is very challenging at places with space constraints. There has been rapid development with the availability of high strength steel and concrete

Read more ...

Integral Abutment Bridges
The conventional bridges use expansion joints and bearings to accommodate the thermal movements of the bridge. However, they don't completely eliminate the distress caused because

Read more ...

Bridge Restoration
The use and advantages of Post Tensioning are very well known in the Civil Engg Industry as it has been in use for the last 40 to 50 years. Post tensioning is one of the best methods to induce stresses in the concrete

Read more ...

Signature Bridge
Wazirabad Bridge or Signature Bridge Project is an initiative of Delhi Government, planned during the Commonwealth Games. It was conceptualized to be a landmark tourist icon that would also speed

Read more ...

Integral Abutment Bridge
An integral bridge may be defined as having no expansion joints or sliding bearings, the deck is continuous across the length of the bridge. Integral bridges are alternatively referred to as integral abutment

Read more ...

Soil Structure Interaction
A type of bridge that is used extensively in road applications in particular is the integral abutment bridge (IAB). The concept of "integral abutment bridge" has recently become a topic of remarkable

Read more ...

Cracks in Ravi Bridge
Before carrying out any testing of the concrete structures using NDT methods, visual inspection of the structure is a must. Visual inspection is not confined to the surface, it also include examination of bearings

Read more ...

Mithi River Bridge
Strengthening of RCC structural elements is a common task for maintenance nowadays. For the purpose of strengthening, several materials and methods are available such as sprayed concrete

Read more ...

×
Sign-up for Free Subscription
'India Construction Week'
Weekly e-Newsletter on Construction Industry
Get the latest news, product launches, projects announced / awarded, government policies, investments, and expert views.