Constructing Bridges Right: Risk Management for Large-Scale Projects

Constructing large bridge projects entails managing multifaceted risks, spanning from product quality to project management. Mitigation strategies involve thorough planning, stakeholder engagement, regulatory compliance, and proactive risk monitoring. Successful project delivery demands meticulous attention to detail, commitment to quality and safety, and effective risk mitigation throughout the project lifecycle. By identifying, assessing, and addressing risks early, project teams can ensure the delivery of large bridge projects that meet performance standards, regulatory requirements, and stakeholder expectations, leaving a lasting positive impact on communities and infrastructure landscapes.

Vivek Singh, Founder BuildStreet Project Management Services, Lucknow

Introduction

Constructing large bridge projects requires meticulous planning, proactive risk management, and stringent quality assurance measures to ensure the safety, durability, and functionality of the final product. In this article, we delve into the various risk factors affecting both product quality and other project management aspects, offering insights into their general mitigation strategies and the imperative role they play in successful project delivery. Please note that the specific mitigation measures can be drawn only by the site team by involving all the stakeholders of the project.

Constructing large bridge projects

Risk Factors Affecting Product Quality

1. Structural Integrity

Inadequate design or construction practices can compromise the stability and safety of the bridge structure, leading to catastrophic failures.

Selection of suitable design standards, thorough structural analysis, adherence to design codes, and onsite inspections are essential for mitigating this risk.

2. Design

Poor design choices or inaccuracies in calculations can result in structural deficiencies.

Engaging experienced professionals and conducting comprehensive design reviews and proof checks are vital mitigation strategies. Continuous support from the design team is also imperative to mitigate design risk.

3. Workmanship

Substandard workmanship during construction can lead to defects compromising the quality and durability of the structure.

Providing adequate training, adequate supervision, and enforcing strict adherence to standards mitigate this risk. Maker & Checker methodology is effective in mitigating workmanship related risks.

4. Geotechnical Factors

Unforeseen ground conditions, such as soil instability, pose risks to the foundation and support systems.

Not only thorough geotechnical investigations and appropriate design measures are critical for mitigation but also the confirmation of the strata before starting the actual construction are suggested mitigation measures.

5. Environmental Factors

Exposure to severe environmental conditions can hasten the degradation of materials. Additionally, floods and river meandering pose separate risks to the integrity of the structure.

Identifying level of severity and accordingly selecting durable materials, applying protective coatings, and implementing monitoring programs mitigate environmental risks. Design of preconstruction activities and supporting structures are the mitigation measures for flood and meandering.

6. Construction Methodologies

Inappropriate construction techniques and lack of adherence with the SOPs & methodologies can lead to defects and compromises in quality.

Detailed construction plans, specialized training, strict supervision and modern technologies are key mitigation measures.

7. Material Quality

Inferior materials can compromise structural strength and durability.

Establishing stringent material specifications, having a robust procurement, storage & disbursement system and conducting quality assurance and quality control testing mitigate this risk.

8. Environmental Impact

Construction activities can have adverse environmental effects.

Developing and implementing environmental management plans help minimize environmental risks.

9. Quality Assurance & Quality Control (QA/QC)

Inadequate QA/QC processes and its implementation can result in construction defects.

A well-defined and robust QA/QC program shall be made a part of the contract, regular independent inspections & audits, and addressing non-conformances promptly mitigate this risk. Having a separate in-house QC team equipped with digital QC tools is an effective mitigation measure.

10. Safety Protocols

Failure to prioritize safety can lead to accidents and injuries affecting both the progress and cost of the project along with the morale of the stakeholders.

A well-defined and robust EHS program shall be made a part of the contract. Implementing comprehensive safety programs, training, enforcement of EHS regulations, regular independent inspections & audits, and addressing non-conformances promptly are essential mitigation measures.

Risk Factors Affecting Project Management

1. Delays in Land Acquisition

Delay in land acquisition can disrupt project schedule, increase costs, strain contracts, challenge stakeholder relations, and jeopardize project feasibility.

Having a dedicated LA team, correct Land Acquisition Plan, timely action, coordination with revenue officers for identification of land owners and timely & lawful payments, mobilising the contractor after major or 100% acquisition completed are few suggested mitigation measures.

2. Socio-political factors

Socio-political factors, such as changes in government policies, public opinion, or local regulations, can disrupt project continuity, delay approvals, increase uncertainty, and lead to opposition, impacting project schedule, costs, and feasibility.

Mitigation measures for socio-political risks include stakeholder engagement, regulatory compliance, political risk assessment, effective public relations, establishing legal frameworks, and continuous risk monitoring and pro-active actions to pre-empt and handle disruptions and ensure project success.

3. Unforeseen Site Conditions

Unexpected geological conditions can lead to delays and additional costs for remediation. There may certain un-foreseen socio-political factors also. Selection of competent investigation agency and expert, along with adherence to codal provisions on frequency and depth of investigation the expert shall have discretion to decide based upon the site situations. For unforeseen socio-political situations continual monitoring and proactive approach is the best mitigation measure.

4. Weather Delays

Adverse weather conditions can disrupt construction schedules and increase costs.

Mitigation measures for adverse weather conditions include monitoring forecasts, factual and realistic scheduling based upon historical weather data and locally available knowledge, suitable design of supporting structures, site preparation, material protection, workforce safety protocols, alternative work plans, and contractual provisions for extensions or compensation. These strategies minimize disruptions and costs, ensuring construction progress despite challenging weather conditions.

5.Changes in Scope

Modifications to the project scope can result in schedule delays and cost overruns.

Correctness of the Detailed Project Report is the key mitigation measures for modifications to the project scope. This includes thorough scope planning, correctness of DPR drawings, realistic scheduling and accurate cost estimation. In construction phase early identification of any changes, clear communication with stakeholders, impact assessment of changes, quick action, and formal change control processes are measures to minimize delays and cost overruns while ensuring project objectives are met.

6. Delays in Material Delivery

Material delays can disrupt project schedules and increase costs.

Mitigation measures for material delays involve proactive supply chain management, early procurement planning, supplier diversification, identification of fast moving materials, buffer stock maintenance, alternative shipping options, alternative material sourcing, and clear communication with suppliers to minimize disruptions, maintain project schedules, and mitigate cost escalations.

7.Labour Shortages

Shortages of skilled labour can lead to schedule delays and compromises in quality.

Mitigation measures for shortages of skilled labour involve proactive workforce planning, labour pool diversification, recruitment initiatives, appropriate facilities for the work force, training programs, subcontractor collaboration.

8. Regulatory Approvals

Delays in obtaining regulatory approvals can result in project delays and increased costs.

Mitigation measures for delays in regulatory approvals involve Quality of DPR, early engagement with regulatory authorities, clarity in responsibility, thorough understanding of approval processes, proactive compliance with regulations, clear communication, expedited approval pathways where possible, contingency planning for potential delays, and regular follow-up to ensure timely approvals, minimizing project delays and cost escalations.

9.Cost Overruns

Inaccurate cost estimates or changes in project scope can lead to cost overruns.

Mitigation measures are similar to those suggested under “Changes in Scope”.

10. Currency Fluctuations

Fluctuations in currency exchange rates can impact project costs.

Mitigation measures for currency exchange rate fluctuations include financial hedging instruments, contractual provisions for currency risk allocation, local currency procurement, cost estimation in stable currencies, periodic budget reviews, and contingency funds to absorb currency-related cost variations, ensuring project financial stability despite currency fluctuations.

11. Inflation

Rising inflation rates can erode project budgets and affect project feasibility. Mitigation measures for rising inflation rates involve accurate cost forecasting, inflation indexing in contracts, periodic budget reviews and adjustments, proactive cost-saving measures & value engineering, negotiation with suppliers for fixed prices, utilising financial instruments like inflation-indexed bonds, and contingency planning to absorb cost increases, ensuring project feasibility despite inflationary pressures.

Conclusion

Addressing these multifaceted risks requires a comprehensive approach that integrates rigorous planning, effective communication, and proactive risk management practices. By identifying, assessing, and mitigating risks early in the project lifecycle, project teams can ensure the successful delivery of large bridge projects that meet performance standards, regulatory requirements, and stakeholder expectations. Only through meticulous attention to detail and a commitment to quality and safety can large bridge projects achieve their intended objectives and leave a lasting positive impact on communities and infrastructure landscapes.
NBM&CW - JUNE 2024
Impact of Baltimore Bridge Collapse on Machinery Supply in the US

Impact of Baltimore Bridge Collapse on Machinery Supply in the US

Alexander Jones, Research Analyst, delves into the impact of Baltimore Bridge collapse on the agricultural and construction machinery supply chain in the United States. The tragic incident in which a container ship collided with a support

Read more ...

Comparative Analysis: Japanese vs Indian Bridge Fabrication Techniques

Comparative Analysis: Japanese vs Indian Bridge Fabrication Techniques

This technical paper delves into a comparative analysis of steel bridge fabrication methods employed in Japan and the traditional practices in India, with a specific focus on the Mumbai-Ahmedabad High-Speed Rail (MAHSR) project's adaptation

Read more ...

Remotely Piloted Aerial Vehicle (RPAV) Based Bridge Monitoring

Remotely Piloted Aerial Vehicle (RPAV) Based Bridge Monitoring

Dr. Naveet Kaur, Senior Scientist, Bridge Engineering & Structures Division, CSIR-CRRI, New Delhi, shares information on the various types of applications of RPAV technology in BHM, including visual inspection, non-destructive testing, and structural health

Read more ...

Prestressing Concepts, Systems & Technologies in Bridges

Prestressing Concepts, Systems & Technologies in Bridges

Prestressing works as an active force in the structure, opposite to applied tensions. There are several types of prestressing such as Internal Prestressing, External Prestressing, Bonded Prestressing, Unbonded Prestressing, etc. Pre-tensioning and Post-tensioning

Read more ...

Structural Integrity Assessment of Submerged Bridges Using Robotic Inspection and Scour Survey

Structural Integrity Assessment of Submerged Bridges Using Robotic Inspection and Scour Survey

In a developing country like India, roads, rails and bridges are amongst the most important infrastructure assets that connect every corner of the country. Roads and bridges tend to undergo wear and tear with aging. When they get submerged

Read more ...

Structural Retrofitting of Chitpore Bridge

Structural Retrofitting of Chitpore Bridge

The Chitpore Bridge was repaired using anti-corrosive treatment, rebuilding of concrete section with micro concrete and polymer, followed with strengthening by using SRM C-wraps and SRM C- Laminates of carbon fiber. After successful completion

Read more ...

Design Concept of Iconic Pedestrian Bridges - Atal, Sambhaji, and Deccan

Design Concept of Iconic Pedestrian Bridges - Atal, Sambhaji, and Deccan

Theme-based concepts of structural forms and designs of bridges are developed through collaborative efforts of the architects and engineers to maintain their aesthetics and structural efficiency. Any bridge or infrastructure is designed for

Read more ...

Construction of Balason Bridge in Darjeeling District @ West Bengal - An Engineering Feat

Construction of Balason Bridge in Darjeeling District @ West Bengal - An Engineering Feat

Situated amidst picturesque surroundings, Balason Bridge is located about 50 km from Siliguri Town, 17 km from Mirik Town and 80 km from Darjeeling Town. The Extension of Balason Bridge @ Dudhia is located 25 km from Siliguri Town in the state of West

Read more ...

Dextra supplies Mechanical Rebar Couplers and Post-Tensioning Bar Systems to new Zuari Bridge in Goa

Dextra supplies Mechanical Rebar Couplers and Post-Tensioning Bar Systems to new Zuari Bridge in Goa

An 8-lane cable-stayed bridge being constructed over the river Zuari in South Goa, has taken engineering to new heights. This is the second longest and widest cable-stayed bridge in India; it will serve Expressway NH-66 that runs between Panaji

Read more ...

Construction Industry - Progressing Towards A 'Digital' Future

Construction Industry - Progressing Towards A 'Digital' Future

The Indian construction and engineering industry is poised for significant growth with a projected expansion of 6.6% in real terms. As part of the ambitious Pradhan Mantri Gati Shakti Master Plan, worth $1.3 trillion, India’s infrastructure development

Read more ...

NHAI invites bids ₹244-cr six-lane flyover & two-lane ROB in Odisha

NHAI invites bids ₹244-cr six-lane flyover & two-lane ROB in Odisha

NHAI invites bids for six-lane flyover and two-lane ROB in Odisha with an investment of ₹244.32 crore. The Ainthapali junction project on NH-53 (Old NH-6) in Sambalpur involves the rehabilitation, upgradation, and augmentation

Read more ...

Synergising Aatmanirbhar Bharat and Operational Preparedness: Launch of Indigenous Modular Bridge in Sikkim

Synergising Aatmanirbhar Bharat and Operational Preparedness: Launch of Indigenous Modular Bridge in Sikkim

Enhanced operational preparedness along the borders and the need to be self-reliant are two major aspects that have seen a substantial impetus over the last few years. The Border Roads Organisation (BRO) has been a key contributor to the infrastructure

Read more ...

Architectural System for Arch Bridges

Architectural System for Arch Bridges

Dextra India’s architectural systems mainly include Tension Rods and Compression Struts, which creates functionally effective and aesthetically pleasing structures. Featuring a wide range of sizes and accessories in various steel grades and in both

Read more ...

Load Testing of Various Types of Bridge Superstructures

Load Testing of Various Types of Bridge Superstructures

Er. Vivek Abhyankar describes the steps and aspects of load testing of various types of superstructures, along with some cautionary measures and points to ponder upon by the designers, site engineers, and testing agencies. The information provided will be

Read more ...

Innovative Steel Plate Girders With Corrugated Webs

Innovative Steel Plate Girders With Corrugated Webs

Girders with corrugated steel webs represent a new innovative system which has emerged in the past decade. These girders have thinner webs, higher fatigue resistance, and are more economical, easier to fabricate, more aesthetic, and provide faster construction

Read more ...

My Tryst with the National Namaste Signature Bridge

My Tryst with the National Namaste Signature Bridge

The iconic National Namaste Signature Bridge in Delhi over the river Yamuna appears languid in perpetual motion in the tradition of the Calatrava’s Bridges in motion, symbolizing nationalism in its visual form. V N Heggade, FNAE, Structural Consultant, Mumbai

Read more ...

Construction of Foundation & Sub-Structure of Bogibeel Rail-Cum Road Bridge Over River Brahmaputra- An Engineering Marvel

Construction of Foundation & Sub-Structure of Bogibeel Rail-Cum Road Bridge Over River Brahmaputra- An Engineering Marvel

The former Prime Minister of India Shri H D Devagowda laid the foundation stone of the Bogibeel Bridge on January 22, 1997 at Kulajan (Assam). After 5 years of laying of the foundation, on April 22, 2002 the Prime Minister of India Shri Atal Behari Vajpayee

Read more ...

Construction of World's Tallest Rail Bridge in India

Construction of World's Tallest Rail Bridge in India

As part of Northeast Policy, the Ministry of Railways took up the project of providing rail connectivity to Imphal in Manipur state. As per the detailed survey, the rail alignment takes off from existing Jiribam

Read more ...

To get latest updates on whatsapp, Save +91 93545 87773 and send us a 'Saved' message
Click Here to Subscribe to Our eNewsletter.