SoilTech Mk. III - 3rd Generation nano-polymer stabilization
Prestige Golfshire

Prestige Estates decided to use SoilTech to treat the roads at the new Golfshire project. SoilTech was selected because of its high-speed construction characteristics and superior quality. Prestige’s Project Manager Mr. Hara Kumar said that by using SoilTech, the budgeted cost of the project was reduced by 25%.
The total arterial road requirement of the project was 7.5 km in length with two carriageways of 7.5 metre average width each. The project, which started in August 2008 during the monsoon season, was completed and handed over to the developer by November-end, 2008.
70,000 litres of SoilTech was used. The standard process, as recommended for the usage of polymer-based soil stabilizer, was followed at all levels. It included: