Mezzo Eccezionale

Use AutoTURN® to design infrastructure adjustments to safely operate trucks transporting wind turbine components.

Engineer Alessio Gori - collaborator at POLITECNICA INGEGNERIA ED ARCHITETTURA SOC. COOP. (Infrastructure division - Head Office Firenze)


Narrow mountain roads, steep hills and challenging ‘S’ curves are just part of the landscape in the ‘toe’ of Southern Italy, where wind farms are becoming a common part of the countryside. With green technology like wind farms gaining popularity as generators of clean, efficient energy sources, technology and engineering are coming together to make these projects as safe and cost-effective as possible.

In Reggio Calabria, the ENEL Green Power project proposed 2 wind farms development to be constructed in two areas: Piani di Lopa with 14 wind turbines rated output 0.85 MW and Campi S.Antonio with 25 wind turbines rated output 0.85 MW, within the boundaries of the three southern Italian municipalities of Bagaladi, Montebello Jonico, and Motta San Giovanni.

The Aspromonte region infrastructure network has a limited number of paved roads. They are mostly classified as "mountain roads", both for the geometric road characteristics and for horizontal curves of low radii. The location of Piani di Lopa and Campi S.Antonio wind farm sites, which experts say are excellent for the wind and the rated power output, means engineers must study and plan the routes carefully prior to the transportation stage of the wind turbines components.

Special Software Required

Due to the conditions, use of specialized software simulating oversize vehicle paths is important for evaluating how the transportation of wind turbine components along the provincial roads might be achieved. Two routes in particular: Strade Proviciale (SP) 3 and 107, from Reggio Calabria harbour to the project sites presented challenges to the engineers.

Definizione veicolo
Figure 4: Definizione veicolo
The objective of the path simulation along the provincial roads SP 3 and SP 107 was to verify the priori conditions of the existing infrastructure. The actual tests have been set aside because they would have affected the road traffic and delayed the project schedule. Moreover, it has been possible to identify possible adjustments to the existing infrastructure in order to safely operate the oversized vehicles. Local engineering professionals were called in to inspect the overall topography of the route to assess any challenges. They measured the topography and the most critical curves along the route. They also tested the vehicle swept path of an oversized vehicle with an unloaded trailer.

The aspects listed below are potential issues in the traditional approach, which is suitable for short routes and/or simple studies:
  • The route length (40km)
  • The number of potentially critical points (about 150);
  • The presence of bridges, with geometry shown to be unsuitable for oversize vehicle paths.
AutoTURN, developed by Canadian software developer Transoft Solutions and distributed by One Team S.r.l in Italy was selected as the software for the simulation. The software allowed ENEL Green Power to perform vehicle swept path analysis and simulate the driving conditions of the area.

Tipologico veicolo Autoturn
Figure 5: Tipologico veicolo Autoturn
AutoTURN® includes a large selection of predefined vehicles, organized in international libraries and the software performs the simulation of "elementary" manoeuvres as well as of "simple" vehicles, trucks and special vehicles. The last ones are mainly common in Australian and North American regions (called "road train", combination of truck and 2 or more trailers). With the possibility of customizing the AutoTURN® library, defining the "vehicle type" and "ad-hoc" simulation profiles have been fundamental design aspects.

The oversize vehicle geometry and the steering characteristics of each component have been reproduced in a plan and meets the guidelines regulating the automatic steering of rear axles of the semi-trailers in relation to the front truck axles (Fig.4). Through a range of speeds, from 5km/h to 20km/h, each iteration showed the swept path of the simulated vehicle matching the swept path of the field test vehicle accurately. (Fig.5)

Choosing the Vehicles, Simulating the Route with AutoTURN

Melca Transporti worked with ENEL Green Power to conduct the path simulations. The inspection process designed by the two companies helped identify critical points along the route and the company made adjustments to ensure the equipment could be transported safely. After this process, the companies used an unloaded vehicle to successfully test the path and the convoys drove the route safely without delays or issues.

montaggio
Figure 2: montaggio
The vehicle type was selected by determining the characteristics of the three basic components that have to be transported from the production site to the building site. The basic components are:
  • fibreglass blade: length 26m, height 2.50 m
  • single section tower: width 3.60m, height 3.60m, length 25m
  • nacelle (to be installed at the top of the generator): width 2.50m, height 3.00m, length 7.00m, weight 40 tons
The components are assembled with a mobile crane (Fig.2)

Wind turbine components are transported to the project site with wheeled vehicles, classified as "oversize transport vehicle", pursuant to Nuovo Codice della Strada (the new Highway Code). In accordance with the indications of the wind turbine producers, two "vehicle types" have been defined:
  1. Semi-trailer truck transporting a metal structure containing 3 "blade" components;
  2. Semi-trailer truck transporting the tower sections (Fig.3): the evaluated section is the critical one for its geometry; it is where the nacelle sits on the trailer. The nacelle also houses the rotational movement of the 3 fibreglass blades.
Figure 3
Figure 3:

The two "vehicle types" definition has been fundamental because type 1 has optimized the dimensions related to the length of the freight while type 2 has shown the issues related to the semi-trailer truck width. The vehicle manoeuvre was conducted on both types of vehicles concurrently. The analysis was based on the hypothesis of keeping general traffic on the Piani di Lopa roads separate from the lower speed semi-trailer traffic. In order to ensure the safety margin between the simulation and the real path, the semi-trailer truck with steering axles have been taken into account. However, they have not been provided with a remote control of the steering angle of each axle. The decision to not include this variable in the path simulation is related to a larger flexibility in the vehicle selection for the company responsible for the transport execution.

Confronto interventi
Figure 6: Confronto interventi

Simulations and other editing operations are managed within the CAD-based program and this kind of versatility is built into the software. Customization of design attributes is an integral part of the software allowing simultaneous visualization of multiple vehicle combinations including:
  1. The precise position of the truck and semi-trailers during the manoeuvre
  2. The convoy path with distinct single paths of rear and front wheels
  3. The vehicle clearance, including the trailer ground clearance
After topographic measurements were made, the 40 km delivery route from Reggio Calabria to the project site has been performed, revealing several adjustment points. (Fig.6, 7)

intervento tornante
Figure 7: intervento tornante

The articulated vehicle simulation was performed with AutoTURN® and the path manoeuvres have been defined and designed, preventing errors in path modelling due to possible design inexperience with the semi-trailer truck. Without the aid of AutoTURN®, the path analysis would have been performed qualitatively, deducing the vehicle clearance from the turn radius values and then overlapping the oversize vehicle swept paths to the topographic measurements.

intervento con paratia di micropali
Figure 8: intervento con paratia di micropali

Intervento ponte
Figure 9: Intervento ponte
This qualitative approach doesn't consider system analysis; in fact, in the typical "S" road curve case, the use of the geometric method would mislead the engineers because it doesn't correctly analyse single critical points in relation to the project plan. The close distance between two "S"-curves suggests a behaviour which is difficult to define with "swept path" analysis. In AutoTURN® this problem is avoided because the design path is built into the software’s vehicle libraries for the exact vehicle type being studied.

At a later stage of the two vehicle types path simulation, the required adjustments to the existing infrastructure were identified, including about 100 small scale "ad-hoc" projects, like bedrock excavation to widen the road, pile bulkhead structures (Fig.8) creating manoeuvring space, removal and replacement of direction signs and safety barriers and removing trees. From an economic standpoint, it is important to identify any conflicts along the route (Fig.9), including lighting and telephone wiring. AutoTURN allows the planning to take place ahead of time, speeding up the permit stage and allowing for repositioning or replacement of any obstacles along the way.

The oversize convoy path along the 40km route, with more than 100 adjustment points, has not found issues or conflicts with any obstacles along the path geometry (Fig.10, 11), showing the reliability of AutoTURN® for projects of this kind.

particolare manovre su ponte
Figure 10: particolare manovre su ponte

transito mezzo
Figure 11: transito mezzo

Lifting & Specialized Transport — October-December 2018

Incorporating Laser Tech for Creation of Heavy-Duty Warehouse Flooring
India is fast becoming a digital economy with smartphones and the internet reaching even the most remote areas. There is a boom in online shopping, which is driving the need for upscaling the logistics industry and increasing the need

Read more ...

Tackling Challenging Strata in Building Sardar Sarovar Dam One of the Largest Dams in the World
Deep Foundations Institute of India (DFI of India) held a webinar under its Groundwork program on “Foundation Treatment for Concrete Gravity Dam: A Case Study of Sardar Sarovar Dam” on 18 January 2022. It covered topics like

Read more ...

CONTAKT Smart Solution for Planning, Monitoring and Documentation
With the sensor-based CONTAKT construction site software, Doka offers a digital solution that brings the construction project planned in BIM to life on the construction site. The new Fröschl office building is an

Read more ...

Shiva Statue at Nathdwara, Rajasthan
Nathdwara near Udaipur in Rajasthan is famous for the Shrinathji Temple. This holy town now boasts a 351 feet (107m) tall statue of the trident-wielding, stoic, and compassionate Lord Shiva - the largest Shiva statue

Read more ...

Exposed Reckli Finish Retaining Wall
The Reckli Finish Exposed Retaining Wall at Sabarmati Riverfront in Ahmedabad, using a 9m high Exposed Retaining Wall with a textured finish, and outer face using Formliner Formwork (known as Reckli), has grabbed the eyes of the world. Besides

Read more ...

Delhi Metro Terminal 1 IGI Airport Terminal
One of the great benefits of Delhi Metro Phase 3 is that the domestic terminals of the Indira Gandhi Intl’ Airport have got Metro connectivity - a boon to the city’s domestic air passengers. While the Airport Express Link provides

Read more ...

Atlas Copco XA316 and XAT266 portable air compressors for Mumbai underground metro line
Atlas Copco portable air compressors have been deployed for the first underground metro line in Mumbai, and they are not just under the supervision of Mumbai Metro Rail Corporation Limited (MMRCL) but also under

Read more ...

Cranes in Full Force at - India's Major Road Project
The 135-km, 11,000 crores Eastern Peripheral Expressway-2 which was inaugurated recently by the Prime Minister, connects towns of UP and Haryana and act as an outer ring road for the capital. It is the country's

Read more ...

Indira Paryavaran Bhawan - First On-site Zero Net Energy Building of India
A zero-energy or a net zero building is a building with zero net energy consumption from outside source, which means that the total amount of energy used by the building on an annual basis is almost equal to

Read more ...

Making of a Green Data Centre
Data centres make up 3% of global energy consumption. The main reason behind data centres being major energy guzzlers is the IT processing power, which has increased substantially to meet the growing

Read more ...

Apollo ValueTec Plant Gives Competitive Edge to Rana Builders
Dhaka-based Rana Builders (Pvt.) Ltd. specialises in construction of roads, bridges and buildings. When purchasing a new asphalt-mixing plant, it wanted a product that would help meet its objective of on-time delivery

Read more ...

BHAI concrete batch mix plant working at Asia’s largest waste-water treatment plant
Delhi Jal Board is setting up a 318 MLD (70 MGD) wastewater treatment plant at GT Karnal Road on the outskirts of Delhi. The ₹414.78 crore project, said to be the largest in Asia, is being constructed by EPC contractor-Larsen & Toubro

Read more ...

The Fast Lane to Growth
When the National Highways Authority of India (NHAI) last widened the Vijayawada-Chilakaluripet Highway in the early 2000s, the country was at the beginning of its exponential economic growth. Since then, the nation’s GDP

Read more ...

Sany cranes deployed at Suzlon India's wind power project
Project developers are deploying new cranes and advanced transportation to enable faster and safer completion of their projects. Suzlon India's wind power project at Agar in Madhya Pradesh, is one such site

Read more ...

Insitu Investigation of Cinder Mound For Building Construction - A Case Study
Cinder is a waste generated as coal residues from the blast furnace of thermal power plant. It was accumulated over a long periods near railway station, Jamshedpur, Jharkhand, India. This dumping

Read more ...

SoilTech Mk. III - 3rd Generation nano-polymer stabilization
Golfshire is a super-premium residential project in Bangalore, comprising luxury villas, a 18-hole PGA standard golf course, a large convention centre with seating capacity of 5000, and a 5-star hotel. The project is

Read more ...

Especially Designed Rope Suspended Platform for Dam & Silo Projects
New Age Construction Equipment Engineering Company is one of the leading manufacturers of construction equipment like Rope Suspended Working Platforms (Gondolas/ Cradles), Bar Bending Machines

Read more ...

New Age Offers Customized Solutions with Higher Productivity & Safety
As a leading manufacturer of construction equipment, we believe in superior performance, higher productivity & safety, faster execution and timely completion of projects,” says Mr. Jayesh Vadukiya

Read more ...

Rehabilitation of National Highway at Tripura-Assam
The National Highway NH-44 is a major road artery for the North-East. The stretch of this highway leading to the border of Assam and Tripura (two states in the north-east of India), is the only land-link between

Read more ...